42
|
Thursday, June 21, 2012, 13:38 |
Isaac Earle | Standard Operation | Target 2 | Cooling | T2 Water Package Started | The T2 water package was reconnected
to the target and started after being shut-off
since April 12, 2012. The M9 and M20 |
|
|
47
|
Tuesday, July 03, 2012, 13:23 |
Isaac Earle | Standard Operation | Target 2 | Target | T2 Plug Block Replaced & Beam Blockers Tested | The T2 plug block was replaced and the
M9 and M20 beam blockers were tested. The
plug block did not interfere with the travel |
|
|
49
|
Monday, July 09, 2012, 17:17 |
Isaac Earle | Standard Operation | Target 1 | Target | BL1A Start-Up Prep | - T1 & T2 targets switched to
"remote" control
- Both target ladders were moved |
|
|
63
|
Thursday, November 22, 2012, 17:22 |
Isaac Earle | Standard Operation | Target 1 | Active Sump | RH Lab Active Sump Released | On Wednesday November 21 at approximately
9am the level of the Remote Handling active
sump was inspected and found to be at approximately |
|
|
65
|
Tuesday, January 08, 2013, 09:27 |
Isaac Earle | Standard Operation | Target 2 | Target | BL1A Air Amplifier turned off for duration of shutdown. | The BL1A air amplifier
has been shut down by closing the air supply |
|
|
67
|
Friday, January 11, 2013, 15:48 |
Isaac Earle | Standard Operation | Target 1 | Target | BL1A Tunnel Accessed | The BL1A tunnel was accessed to drain
and sample T2 cooling package water. A
puddle of water was noticed in the South |
|
|
68
|
Monday, January 14, 2013, 16:55 |
Isaac Earle | Standard Operation | Target 2 | Target | Target Move & Damaged Profile Monitor | The T2-MK1 target (spare T2 target) was
transported from the hot cell to the storage
pit today. |
|
|
70
|
Monday, January 21, 2013, 16:18 |
Isaac Earle | Standard Operation | Target 2 | Target | T2 Cooling Package Water Released | The T2 cooling package water was drained
to the BL1A active sump, refilled, cycled,
and drained again. Samples of T2 cooling |
|
|
77
|
Friday, April 12, 2013, 13:28 |
Isaac Earle | Standard Operation | Target 1 | Cooling | Cooling Packages Leak Tight | The T1 and T2 expansion tanks were
filled on Monday April 8th. There was
no change in the level when inspected today |
|
|
79
|
Wednesday, April 17, 2013, 16:43 |
Isaac Earle | Standard Operation | Target 2 | Target | T2 target installed; Vacuum leak-tight; Monitors OK; T2 ready for beam | The T2-MK2 target was transferred from
the storage pit to the beam line yesterday
(April 16th). The field was measured |
|
|
80
|
Wednesday, April 17, 2013, 16:45 |
Isaac Earle | Standard Operation | Target 1 | Target | T1-MK1 Target Leak Checked | The T1-MK1 target was leak checked
on April 15th at the T1 monolith by Ron Kuramoto
and Edi Dalla Valle. No leaks were |
|
|
89
|
Wednesday, September 25, 2013, 14:05 |
Isaac Earle | Standard Operation | Target 1 | Active Sump | RH Lab Active Sump Level Sensor Inspected | A notification was received that the RH
lab active sump level sensor is due for annual
inspection. The sensor was tested and |
|
|
97
|
Wednesday, January 15, 2014, 15:38 |
Isaac Earle | Standard Operation | Target 2 | Water Leak | Suck Tube Drained and Rinsed | The suck tube vessel was drained, rinsed,
and transported to the active sink area in
the Meson Hall Hot Cell Lab. There |
|
|
98
|
Friday, January 17, 2014, 10:10 |
Isaac Earle | Standard Operation | Target 1 | Cooling | T1/T2 Cooling Packages & Air Amplifier Shut Off | In preparation for Edi to vent the
BL1A vacuum volume, the T1 and T2 cooling
packages were both shut off. They will |
|
|
99
|
Friday, January 17, 2014, 15:41 |
Isaac Earle | Standard Operation | Target 1 | Target | Water Purged from T1 & T2 Targets | Water was purged from the T1 and T2 targets
using compressed air. The water is
stored in a labeled bucket on the BL1A blocks |
|
|
101
|
Wednesday, January 22, 2014, 15:41 |
Isaac Earle | Standard Operation | Target 2 | Water Leak | Water Drained From Suck Tube Released | After approval from RPG, the water
drained from the suck tube, which was stored
in a bucket in the RH lab active sink area, |
|
|
102
|
Thursday, February 06, 2014, 17:05 |
Isaac Earle | Standard Operation | Target 1 | Cooling | T1 & T2 Cooling Package Filters Changed | Water was drained from the T1 and T2 cooling
packages, samples taken, and delivered to
RPG. |
|
|
103
|
Thursday, February 13, 2014, 14:27 |
Isaac Earle | Standard Operation | Target 2 | Target | T2 Target Moves | The T2-MK1 target was moved from the beam
line to the target storage pit in position
4. The target was measured to be 30mSv/hr |
|
|
106
|
Monday, March 24, 2014, 18:14 |
Isaac Earle | Standard Operation | Target 2 | Cooling | T2 Cooling Package & Air Amplifier Started | Bill Rawnsley completed an electrical check
of the T2 profile monitor today from the
Meson Hall mezzanine - All OK. |
|
|
110
|
Thursday, April 03, 2014, 10:19 |
Isaac Earle | Standard Operation | Target 2 | Cooling | T2 Cooling Package Resin Can Replaced | The resin can was removed from the T2 cooling
package and transported to the warm cell.
A replacement can with fresh resin |
|
|
111
|
Thursday, April 03, 2014, 13:43 |
Isaac Earle | Standard Operation | Target 2 | Target | T2 Profile Monitor OK | T2 Profile Monitor actuation was tested
today from the control room and all is working
properly. The position (IN / OUT) also |
|
|
112
|
Thursday, April 03, 2014, 16:35 |
Isaac Earle | Standard Operation | Target 1 | Cooling | T1 Cooling Package Started | The T1 cooling package was started
around 2pm today. There was no change
to the T1 volume vacuum during startup. |
|
|
113
|
Monday, April 14, 2014, 15:30 |
Isaac Earle | Standard Operation | Target 2 | Target | T2 Target Moved to Position 4 | The T2-MK2 target (currently installed
in the beamline) was moved from position
0 to position 4 (10cm Be) using the portable |
|
|
117
|
Tuesday, June 03, 2014, 22:56 |
Isaac Earle | Standard Operation | Target 2 | Target | T2 Target Position Moves (Development Shift) | The T2 target was moved from Position 4
to Position 0 at 11:15am so the profile monitor
could be used during the development shift. |
|
|
128
|
Tuesday, November 18, 2014, 10:52 |
Isaac Earle | Standard Operation | Target 1 | Active Sump | RH Hot Cell Lab Active Sump Released | Release of the Remote Handling Hot
Cell Lab active sump water was completed |
|
|
130
|
Friday, December 19, 2014, 14:35 |
Isaac Earle | Standard Operation | Target 2 | Other | Amplified Air Shut Off | The BL1A amplified air system has been
shut off, and will remain off until required
for BL1A start-up in Spring 2015 (the lower |
|
|
132
|
Monday, January 05, 2015, 15:08 |
Isaac Earle | Standard Operation | Target 2 | Water Leak | Cooling Packages Re-Started; Suspect External Water Leak at T2 Package | Pumping was restored to 1A today by Vacuum
Group and the beam line returned to normal
vacuum levels. Both cooling packages |
|
|
134
|
Monday, January 12, 2015, 16:35 |
Isaac Earle | Standard Operation | Target 1 | Cooling | T1 & T2 MRO Status | The following tasks have been performed
at T1:
- T1 monolith painted using grey |
|
|
135
|
Wednesday, January 14, 2015, 13:32 |
Isaac Earle | Standard Operation | Target 1 | Target | T1-MK2 Moved from B/L to Storage Pit | The T1-MK2 target was transferred from
the beam line to the storage pit in hole
#5 using the transfer flask. A maximum |
|
|
136
|
Wednesday, January 14, 2015, 15:06 |
Isaac Earle | Standard Operation | Target 1 | Other | Active Item Stored in East Hot Cell | The active item discovered on January 9,
2015 outside the BL1A bootbox has been moved
to the Meson Hall east hot cell for storage. |
|
|
142
|
Friday, February 20, 2015, 13:55 |
Isaac Earle | Standard Operation | Target 2 | Target | T1 & T2 Target Moves | - The T1-MK1 target was moved from the
hot cell to storage pit hole #3 (ready as
T1 spare) |
|
|
145
|
Thursday, March 12, 2015, 10:51 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Pos'n 4 Elevation Measurements | Elevation measurements of the T2-MK2 target
were taken in the hot cell to confirm previous
records in preparation for the T2 Protect |
|
|
148
|
Monday, April 20, 2015, 11:42 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Target & T2 Protect Moved | The T2-MK2 target was moved from
the hot cell to the beam line. The T2 Protect
Monitor was moved from the beam line to the |
|
|
149
|
Tuesday, April 21, 2015, 12:59 |
Isaac Earle | Standard Operation | Target 1 | Target | T1-MK2 target moved from storage pit to beam line | The T1-MK2 target was transported
from the storage pit to the beamline. The
target measured approximately 10mSv/hr at |
|
|
150
|
Tuesday, April 21, 2015, 13:38 |
Isaac Earle | Standard Operation | Target 1 | Target | Air Amplifier Started. T1 & T2 Profile Monitor Actuation Checked | The lower air amplifier has been
started, and air supplied to the T1 and T2
areas by opening the appropriate ball valves |
|
|
152
|
Wednesday, April 22, 2015, 15:15 |
Isaac Earle | Standard Operation | Target 1 | Cooling | T1 and T2 Cooling Packages Ready | Both cooling packages are running steadily
with the targets in Position 0.
The demin flow (Q2) for both was |
|
|
155
|
Thursday, April 23, 2015, 16:29 |
Isaac Earle | Standard Operation | Target 1 | Target | T1 & T2 Profile and Protect Monitors Electrical Check Completed | An electrical check has been completed
for the T1 & T2 Profile and Protect Monitors
by Dave Cameron and Mike Russell. They |
|
|
156
|
Friday, April 24, 2015, 11:53 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Target Info Sheet & Elevations | T2-MK2 target information sheet, beam spot
measurements, and elevations were updated
and delivered to Operations. PDF copy attached. |
|
|
159
|
Friday, May 08, 2015, 09:48 |
Isaac Earle | Standard Operation | Other | Other | BL1A Blocks Restored | Replacement of the BL1A blocks was completed
yesterday (May 8, 2015) in preparation for
first beam down 1A on May 12th. The |
|
|
160
|
Tuesday, May 12, 2015, 21:20 |
Grant Minor | Standard Operation | Target 1 | Target | T1 & T2 Targets moved from pos. 0 to pos. 4 | Grant moved the T1 and T2 targets from
position 0 to position 4 this evening at
around 9pm. |
|
|
164
|
Tuesday, June 23, 2015, 10:24 |
Isaac Earle | Standard Operation | Other | Other | BL1A Holding Tank Water Released | The water in the BL1A holding tank
was released to the city sewer. This
water was sampled, tested, and approved for |
|
|
167
|
Wednesday, July 15, 2015, 10:33 |
Isaac Earle | Standard Operation | Target 1 | Cooling | T1 & T2 Cooling System Check | - All T1 and T2 values on XTPAGE were stripped
back to April 1, 2015: All systems
appear to be functioning normally, nothing |
|
|
172
|
Monday, September 28, 2015, 10:29 |
Isaac Earle | Standard Operation | Other | Active Sump | RH Hot Cell Lab Active Sump High Level Sensor Tested | The RH hot cell lab active sump high
level sensor was tested as part of the yearly
scheduled inspection. High water level |
|
|
174
|
Wednesday, September 30, 2015, 17:07 |
Isaac Earle | Standard Operation | Target 2 | Target | Target Moves for Profile Check - Possible Motor or Control Box Failure | The T1 and T2 targets were moved to position
zero, then back to the target position today
so that beam profile could be checked using |
|
|
176
|
Friday, October 02, 2015, 17:25 |
Ron Kuramoto | Standard Operation | Target 1 | Target | Raise Target to lower Rad levels for 1AM7 repair | Today the T1MK2 target was moved from Position
4 to Position 0 to lower the Rad fields for
the 1AM7 repair in the 1A Tunnel. The Rad |
|
|
177
|
Monday, October 05, 2015, 15:25 |
Isaac Earle | Standard Operation | Other | Other | Old T2 Protect Monitor Cassette Update | The T2 protect monitor cassette removed
in April 2015 (see E-log #154) was surveyed
today. It was approximately 3mSv/hr |
|
|
182
|
Tuesday, October 13, 2015, 10:52 |
Isaac Earle | Standard Operation | Target 1 | Target | T1 & T2 Target Ladder Moves | The T1 and T2 targets were both moved
from Position 0 to Position 4 at approximately
2:30am on Saturday October 10th using the |
|
|
185
|
Monday, January 18, 2016, 17:19 |
Isaac Earle | Standard Operation | Target 1 | Cooling | T1 & T2 Packages Drained; BL1A Holding Tank Released | The T1 and T2 cooling packages were
drained to the BL1A holding tank on Jan 8
2016. The volumes were 100L and 80L |
|
|
187
|
Wednesday, February 03, 2016, 17:35 |
Isaac Earle | Standard Operation | Target 2 | Cooling | T2 MRO Work | The following work was performed at the
T2 cooling package and target between Jan
25 - Feb 3, 2016: |
|
|
193
|
Thursday, March 31, 2016, 11:48 |
Isaac Earle | Standard Operation | Target 1 | Target | T1 & T2 Beryllium Target Manufacturing Complete | Manufacturing of a new batch of T1 and
T2 beryllium targets has been completed.
The job was completed under Machine |
|
|
196
|
Monday, April 11, 2016, 13:54 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Target Transported from BL to HC | The T2-MK2 target was transported from
the beam line to the hot cell using the transfer
flask. The target was measured to be |
|
|
197
|
Friday, April 15, 2016, 14:54 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Target Changes & Return to Beamline | On April 11th the T2-MK2 target was flushed
with water, then overnight with air at 5psi
supply pressure. The target ladder |
|
|
198
|
Wednesday, April 20, 2016, 10:01 |
Isaac Earle | Standard Operation | Target 1 | Target | T1/T2 Monitor Electrical Check Complete | Mike Russell from Diagnostics Group has
completed an electrical check on the T1 and
T2 profile and protect monitors. He |
|
|
200
|
Friday, May 13, 2016, 15:04 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Position 4 Adjusted to +1.5mm Offset | The T2-MK2 target at Position 4 has been
adjust to approximately +1.5mm offset. This
causes the ladder to be moved downwards, |
|
|
201
|
Wednesday, June 15, 2016, 11:00 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Target Moved to Position #1 | Position #4 on the T2-MK2 target
has now reached the maximum beam time. The
target was moved to Position #1 at the nominal |
|
|
212
|
Monday, January 09, 2017, 15:07 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Target Moved from BL to HC | The T2-MK2 target assembly was moved
from the beam line to the hot cell today.
A maximum field of 203mSv/hr was measured |
|
|
213
|
Thursday, January 12, 2017, 09:21 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 Position 1 Beam Spot | The beam spot on the 10cm beryllium
target in Position 1 on T2-MK2 (Target ID:
"OCT.06#3") was measured and photographed |
|
|
214
|
Thursday, January 19, 2017, 08:55 |
Isaac Earle | Standard Operation | Target 1 | Cooling | T1 MRO work complete | The following work was completed on
the T1 cooling package:
- water drained to BL1A holding |
|
|
215
|
Wednesday, March 15, 2017, 16:13 |
Isaac Earle | Standard Operation | Other | Active Sump | Meson Hall Hot Cell Lab Active Sump Water Released | On March 13th in the morning the
Meson Hall Hot Cell Lab active sump reached
the high level sensor. The system responded |
|
|
229
|
Tuesday, October 10, 2017, 12:09 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 position 4 target changed | The following work was performed on
the T2-MK2 target assembly during the 2017
fall shutdown: |
|
|
232
|
Wednesday, January 10, 2018, 17:45 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 beam spot photos, M20BB moved to storage pit | The T2-MK2 target was moved from
the beamline to the hot cell on January 8th.
The field at 0.5m was 130mSv/hr. Photographs |
|
|
233
|
Thursday, March 22, 2018, 17:24 |
Isaac Earle | Standard Operation | Other | Active Sump | RH Lab active sump released | The RH Lab active sump level reached
the high limit yesterday due to an overflow
of the ultrasonic cleaner in the Rad Waste |
|
|
234
|
Wednesday, March 28, 2018, 10:12 |
Isaac Earle | Standard Operation | Other | Other | Five waste pails moved to East Vault Tunnel for storage | Five 5 gallon metal pails with active
waste were moved from the Warm Cell to the
Cyclotron East Vault Tunnel today for long |
|
|
235
|
Friday, April 06, 2018, 15:05 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 target MRO | The following is a summary of MRO work
done on the T2-MK2 target during the 2018
shutdown:
|
|
|
243
|
Tuesday, August 28, 2018, 11:16 |
Isaac Earle | Standard Operation | Other | Other | South TNF Holding Tank water released | The water in the South TNF Holding
Tank was released today under work permit
#C2018-08-28-3. The tank contained |
|
|
253
|
Tuesday, December 17, 2019, 12:39 |
Isaac Earle | Standard Operation | Other | Other | 55 gallon drum and old M9 service stand moved to Rad Waste Pit | The following items were moved today from
the Warm Cell to the Rad Waste Pit for long
term storage: |
|
|
262
|
Monday, April 06, 2020, 15:02 |
Isaac Earle | Standard Operation | Target 2 | M9 | M9 beam blocker returned to beamline | The M9 beam blocker was returned to the
beamline today using the RH shielded transport
flask. The top flange o-ring was replaced |
|
|
271
|
Tuesday, November 24, 2020, 15:10 |
Isaac Earle | Standard Operation | Target 2 | Target | Additional targets added to T2-MK1 ladder | The following work on the T2-MK1
target was completed sporadically over the
last few months: |
|
|
273
|
Wednesday, March 31, 2021, 16:15 |
Matthew Gareau | Standard Operation | Target 1 | Target | T1-MK1 target exchange | March 29 Monday
- moved T1-MK1 target from beamline
to hotcell (field from target 15mSv/hr |
|
|
275
|
Wednesday, April 14, 2021, 14:30 |
Isaac Earle | Standard Operation | Other | Active Sump | RH Lab Active Sump pumped out | The RH Lab Active Sump reached the
high level sensor at some point overnight
before the April 8th work day. Maico |
|
|
285
|
Wednesday, March 16, 2022, 14:16 |
Matthew Gareau | Standard Operation | Other | Cooling | T1/T2 water packages drained to B1A AWHT, tested, and released. Also solenoid valve SV1 broken | The T1/T2 water packages were drained
into the B1AAWHT (280L), the water was sampled
and tested by RPG, results included in elog. |
|
|
286
|
Wednesday, April 13, 2022, 12:31 |
Adam Newsome | Standard Operation | Target 2 | Target | T2-MK2 moved: from target station to storage | The T2-MK2 target was moved from the target
station to the storage area (position 3).
Upon removal, it was measured with a pole |
|
|
287
|
Wednesday, April 13, 2022, 12:33 |
Adam Newsome | Standard Operation | Target 2 | Target | T2-MK1 moved: from storage area to target station | The T2-MK1 target was moved from the storage
area (formerly position 4) to the target
station. Services were reconnected in order |
|
|
289
|
Wednesday, May 04, 2022, 11:27 |
Adam Newsome | Standard Operation | Target 2 | M9 | M9 and M20 Beam Blocker Actuation Test | The beam blockers for M9 and M20 were actuated,
and vacuum was monitored to ensure no disruptions.
Both actuation tests were successful. Motion |
|
|
291
|
Thursday, May 05, 2022, 14:39 |
Adam Newsome | Standard Operation | Target 1 | Target | T1-MK1 and T2-MK1 profile monitor actuation test | The profile monitor actuation tests were
completed for T1 and T2. No abnormalities
were noticed in vacuum during either test. |
|
|
292
|
Wednesday, May 25, 2022, 10:15 |
Adam Newsome | Standard Operation | Target 1 | Target | T1-MK2 moved from hot cell to storage area | The T1-MK2 target was moved from the hot
cell to the storage area, in position 5.
Note: manual nudging of the flask was required |
|
|
293
|
Wednesday, May 25, 2022, 10:16 |
Adam Newsome | Standard Operation | Target 2 | Target | T2-MK2 moved: from storage location to hot cell | Target T2-MK2 was moved from the storage
location (formerly position 3) to the hot
cell in preparation for replacement of end |
|
|
299
|
Monday, August 22, 2022, 09:01 |
Adam Newsome | Standard Operation | Other | Active Sump | Active Sump Draining | On Aug. 18, 2022, Operations informed RH
group that an alarm activated for the full
status of the MHESA B1 RCR1 Lab holding tank. |
|
|
300
|
Tuesday, August 23, 2022, 14:36 |
Adam Newsome | Standard Operation | Other | Other | BL1A Holding Tank - Level Check | The water level inside the BL1A active
water holding tank was checked today (Aug.
23, 2022). The tank is essentially empty |
|
|
302
|
Thursday, September 15, 2022, 14:34 |
Adam Newsome | Standard Operation | Target 2 | Target | T2-MK2 target elevations measurement | The target elevations measurement and beam
spot checks were completed on Sept. 15, 2022.
This was done after a July 2022 target exchange |
|
|
303
|
Friday, September 23, 2022, 10:51 |
Matthew Gareau | Standard Operation | Target 2 | Target | Target T2-MK2 moved to storage pit | The T2-MK2 target was transported from
the east hot cell to the storage pit at position
3. |
|
|
309
|
Monday, January 16, 2023, 09:54 |
Adam Newsome | Standard Operation | Other | Cooling | T1 and T2 - Cooling Package Drained | On Jan. 13, the T1 and T2 cooling package
water reservoirs were drained to the BL1A
holding tank. Water samples were obtained |
|
|
330
|
Tuesday, June 06, 2023, 15:42 |
Albert Kong | Standard Operation | Target 1 | Cooling | T1 Heat Exchanger Low Flow Diagnostics | On May 31, the low active water in BL1A
was turned off briefly and upon re-starting,
the flow to the T1 heat exchanger was very |
|
|
335
|
Monday, December 04, 2023, 09:22 |
Albert Kong | Standard Operation | Target 2 | Cooling | T2 TGT Low Flow | See Cyclotron fault 16553.
"B1A:T2CS:FGTGT readback is
toggling at the warn limit of 3.0 GPM and |
|
|
336
|
Wednesday, January 10, 2024, 12:25 |
Albert Kong | Standard Operation | Other | Cooling | T1/T2 cooling packages drained | Jan 10, 2024:
The cooling packages for T1/T2 was
drained this morning. ~150 L from each of |
|
|
337
|
Wednesday, January 10, 2024, 12:47 |
Albert Kong | Standard Operation | Target 1 | Target | T1 target ladder exchange (T1-MK1 to hot cell roof, T1-MK2 from pit to station) | T1-MK1 was moved from the target station
to the hot cell roof.
Radiation surveys report 140 mSv/hr |
|
|
339
|
Monday, January 15, 2024, 16:36 |
Albert Kong | Standard Operation | Target 2 | Cooling | T2 Resin Flask Exchange | The resin flask on the T2 cooling package
was exchanged today (new resin can prepped
in the morning). |
|
|
340
|
Monday, January 15, 2024, 16:47 |
Albert Kong | Standard Operation | Other | Cooling | T1/T2 Cooling Pkg. Prep for Refill + Leak Check At Pressure | The following tasks were completed
in preparation of re-filling the T1 and T2
cooling packages: |
7x |
|
341
|
Friday, January 19, 2024, 17:07 |
Albert Kong | Standard Operation | Other | Target | T1/T2 Profile Monitor, TGT Ladder, CUNO filter leak, Motor Coupling Inspection, + M9/M20 Blocker Actuation | The following tasks were completed:
Yesterday (Jan 18), the
T1/T2 cooling packages were inspected for |
7x |
|
342
|
Thursday, February 01, 2024, 11:14 |
Albert Kong | Standard Operation | Target 1 | Hot Cell | T1-MK1 Flush and Purge on Hot Cell | The recently removed T1-MK1 target ladder
was flushed with city water for ~30s at all
target positions. It was then purged with |
|
|
343
|
Thursday, February 01, 2024, 11:16 |
Albert Kong | Standard Operation | Other | Cooling | Spent resin can rinse, purge, and drying | The recently removed resin can from
the T2 target station was rinsed with city
water and flushed with compressed air for |
|
|
348
|
Thursday, May 23, 2024, 17:10 |
Albert Kong | Standard Operation | Target 1 | Target | T1-MK1 Target Exchange (+ leak fix, service panel changes, coupler exchange) | On May 23, 2024 two sets of plugs from
position 1 and 3 and a 12mm Be target from
position 5 (serial #109) was removed from |
36x |
|
350
|
Wednesday, July 17, 2024, 15:05 |
Adam Newsome | Standard Operation | Other | Other | Safety Walkaround Complete - Meson Hall HC/WC Area | A safety walkaround for July 2024 was completed
by A. Kong.
Results can be found in the master |
|
|
351
|
Tuesday, August 06, 2024, 11:35 |
Albert Kong | Standard Operation | Other | BL1A Holding Tank | BL1A and RH Active Sump Draining | The RH active sump was drained (over Jul
31-Aug 01), in total approximately 5500 L
of water was sent to city sewage. |
|
|
352
|
Thursday, August 22, 2024, 15:16 |
Adam Newsome | Standard Operation | Other | Active Sump | Active sump filled ~600L with grey water from RCR1 sump replacement | During a replacement of the RCR1 active
sump (mechanical services group), approximately
600L of non-active grey water was released |
|
|
354
|
Monday, September 09, 2024, 16:31 |
Albert Kong | Standard Operation | Other | Active Sump | Active Sump High Level Sensor Testing | The active sump high level sensor was tested
and correctly alarmed locally. However the
alarm in the MHESA RCR lab did not make any |
|
|
356
|
Wednesday, October 30, 2024, 15:10 |
Albert Kong | Standard Operation | Target 1 | Target | T1-MK1 Electrical Check on Hot Cell | T1-MK1 electrical checks were completed
on the hot cell. Specifically the profile
and protect monitors were checked (assistance |
7x |
|
358
|
Friday, January 10, 2025, 18:36 |
Albert Kong | Standard Operation | Other | Cooling | T1/T2 cooling packages drained | The T1 and T2 cooling packages were drained
starting at 14:36, by 14:48 both expansion
tanks had dried, meaning the draining rate |
|
|
10
|
Friday, January 13, 2012, 17:04 |
Isaac Earle | Repair | Target 2 | Target | Broken Part found on M20 Beam Blocker | While wrapping up vacuum seal bearing
replacement on the M20 beam blocker I found
a piece of hard black material approximately |
|
|
11
|
Wednesday, January 18, 2012, 12:01 |
Isaac Earle | Repair | Target 2 | Target | Broken M20BB Bearing Removed, New Design Complete | The broken M20 beam blocker plastic
shaft bearing was removed. Measurements
of the bearing as well as the shielding disc |
|
|
12
|
Friday, January 20, 2012, 10:23 |
Isaac Earle | Repair | Target 2 | Target | M20 BB Shaft Bearing Replaced | The replacement shaft bearing was machined
by Maico Dalla Valle and installed in the
beam blocker. Smooth operation of the |
|
|
13
|
Monday, January 23, 2012, 15:27 |
Isaac Earle | Repair | Target 2 | Target | M20BB returned to beam line. M9BB moved to hot cell. | M20 beam blocker was transferred from the
hot cell to the beam line.
M9 beam blocker was transferred from |
|
|
16
|
Thursday, February 02, 2012, 16:54 |
Isaac Earle | Repair | Target 2 | Cooling | T2 Device Air Line Issue | While checking operation of the M9 and
M20 beam blockers earlier this week, a strange
noise was noticed coming from the T2 cooling |
|
|
17
|
Thursday, February 09, 2012, 17:19 |
Isaac Earle | Repair | Target 1 | Cooling | T1 & T2 General MRO | The following work was performed
on the T1 cooling package:
- New filter housing installed for |
|
|
18
|
Tuesday, February 21, 2012, 09:56 |
Isaac Earle | Repair | Target 2 | Target | Air Supply Check Valve & Q4 Flow Transducer | The faulty air pressure supply check
valve for M9BB, M20BB, and T2 Profile Monitor
was replaced. |
|
|
19
|
Tuesday, March 06, 2012, 15:27 |
Isaac Earle | Repair | Target 1 | Target | Quick Connect Fittings on T1 Target | The air hoses for the profile monitor
supply line were inspected and no cracking
was found (was found on T2). The quick |
|
|
20
|
Tuesday, March 20, 2012, 10:31 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Cooling Package - Potential Water Leak | The T1 expansion tank warning level sensor
had tripped and the level was approximately
1cm from the base of the tank. No trip |
|
|
21
|
Wednesday, March 21, 2012, 17:28 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Package Water Leak - Update | The water level in the T1 cooling
package expansion tank was checked again
today approximately 24 hours after it was |
|
|
22
|
Thursday, March 22, 2012, 13:58 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Package Water Leak - Update | Vacuum group pumped down on the T1
& T2 volumes (because there is no cold
trap on the T1 pump) for approximately 1 |
|
|
23
|
Friday, March 23, 2012, 14:50 |
Isaac Earle | Repair | Target 1 | Target | T1 Target Leak - Update | The T1-MK2 target was transferred from
the beam line to the hot cell. Water
was seen in the bottom of the target pipe |
|
|
24
|
Tuesday, March 27, 2012, 13:14 |
Isaac Earle | Repair | Target 1 | Target | Water removal from T1 monolith | All water was removed from the base of
the target hole in the T1 monolith using
a suction tube device and wypalls. Video |
|
|
25
|
Monday, April 02, 2012, 15:18 |
Isaac Earle | Repair | Target 1 | Target | T1-MK1 Installed in Beam Line | The T1-MK1 target was transferred
from the storage pit to the beam line. Services
were hooked up and the cooling package was |
|
|
27
|
Wednesday, April 04, 2012, 15:51 |
Isaac Earle | Repair | Target 2 | Target | BL1A Update | Vacuum interlock defeat jumpers were removed
for T1 and T2. The interlock was tested
by venting the T1 and T2 volumes. Both |
|
|
28
|
Thursday, April 05, 2012, 12:14 |
Isaac Earle | Repair | Target 1 | Target | T1 & T2 Profile Monitors | Controls Group replaced the wiring and
wire harness for the profile monitor limit
switches on T2. The monitor was actuated |
|
|
30
|
Wednesday, April 11, 2012, 17:02 |
Isaac Earle | Repair | Target 2 | Target | T2 Vacuum Interlock & Expansion Tank Level Sensor | The problem with the T2 vacuum interlock
was fixed by restarting the "Crate TG1"
control panel microprocessor. The T1 |
|
|
32
|
Monday, April 23, 2012, 09:55 |
Isaac Earle | Repair | Target 1 | Target | Hot Cell Manipulator Broken Cable | While working on the leak repair
of the T1-MK2 target in the hot cell on Friday
April 20th, a cable snapped on the slave |
|
|
33
|
Thursday, May 24, 2012, 18:26 |
Isaac Earle | Repair | Target 2 | Cooling | Water Leak From T2 Cooling Package (Disconnected from Target) | Today I noticed a "NOT OK"
signal from T2 water expansion tank warning
level sensor. I checked the water level |
|
|
34
|
Monday, May 28, 2012, 17:17 |
Isaac Earle | Repair | Target 2 | Cooling | T2 Water Loss Update | The T2 cooling package, the top of
the T2 monolith, and the Hansen water connections
which connect the package to the target were |
|
|
35
|
Wednesday, May 30, 2012, 15:39 |
Isaac Earle | Repair | Target 1 | Target | West Side Manipulator Removed from Hot Cell | The west side manipulator was removed
from the hot cell using the new manipulator
removal frame. The operation went smoothly |
|
|
36
|
Wednesday, June 06, 2012, 08:48 |
Isaac Earle | Repair | Target 1 | Target | Manipulator Repair Complete | Repair of the west side hot cell
manipulator was completed and the manipulator
was re-installed into the hot cell. No |
|
|
38
|
Thursday, June 07, 2012, 18:08 |
Isaac Earle | Repair | Target 1 | Target | Hot Cell Manipulator Broken Tape | A tape snapped on the west side manipulator
today while working on the T1-MK2 target
repair. The tape travels through to |
|
|
39
|
Friday, June 08, 2012, 16:52 |
Isaac Earle | Repair | Target 1 | Target | Broken Manipulator Tape Update | The broken tape on the west side
hot cell manipulator was found to be one
of two "Z motion slave tapes". |
|
|
40
|
Friday, June 08, 2012, 17:01 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 Leak Repair Update | A leak check was performed on the
T1-MK2 target in the hot cell today and confirmed
successful leak-free installation of the |
|
|
41
|
Monday, June 18, 2012, 16:27 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 Profile and Protect Monitor Electronics Check | Bill Rawnsley and Mike Russell performed
a 'blip' test on the T1-MK2 profile monitor
and protect monitors today. A possible |
|
|
46
|
Friday, June 29, 2012, 14:18 |
Isaac Earle | Repair | Target 1 | Target | Manipulator Repair Complete | Repair of the west side hot cell
manipulator was completed and the manipulator
was re-installed into the cell. The |
|
|
48
|
Friday, July 06, 2012, 16:03 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 Target Repair Complete | Target elevation measurements and
beam spot plots were completed on the T1-MK2
target and the target is now fully repaired |
|
|
50
|
Wednesday, July 11, 2012, 17:51 |
Isaac Earle | Repair | Target 1 | Target | T1 Target Swap | BL1A was started yesterday and brought
up to 10 |
|
|
53
|
Friday, July 27, 2012, 14:48 |
Isaac Earle | Repair | Target 1 | Target | T1-MK1 Target Repair Update | - T1MK1 target transferred from storage
pit to hot cell (max field: 4700 |
|
|
54
|
Wednesday, August 08, 2012, 14:40 |
Isaac Earle | Repair | Target 1 | Target | T1-MK1 Target Repair Complete | - Re-wired profile monitor was received
from Probes Group and installed on the target |
|
|
55
|
Friday, September 07, 2012, 16:35 |
Isaac Earle | Repair | Target 2 | Target | T2-MK1 Target Repair Completed | - Profile monitor wiring harness
checked by Bill Rawnsley using resistor pack
--> OK |
|
|
56
|
Friday, September 07, 2012, 16:39 |
Isaac Earle | Repair | Target 1 | Target | RH Lab Crane Repaired | The "west" button on the
crane pendant was broken, and the crane would
occasionally continue moving west when the |
|
|
58
|
Tuesday, September 25, 2012, 16:31 |
Isaac Earle | Repair | Target 1 | Target | T1/T2 Controls | - The target control software was
modified to reference the correct pot. look-up
table for the target at T1 (T1-MK1) |
|
|
59
|
Friday, September 28, 2012, 15:19 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 Delta Seal Leak | After removal of the leaky
target cassette at position 3, plugs were
installed on the target ladder and a leak |
|
|
60
|
Wednesday, October 24, 2012, 17:34 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 Target Repair Complete | The target ladder was detached, old delta
seals removed, sealing surfaces cleaned using
scotchbrite pad and a dremel tool, and delta |
|
|
61
|
Wednesday, October 24, 2012, 17:38 |
Isaac Earle | Repair | Target 2 | Target | T1 & T2 Target Ladder Control System Status | During the recent shutdown for the
T2/M9 joint repair Graham Waters replaced
the corrupted application code on the controller |
|
|
62
|
Tuesday, November 13, 2012, 16:26 |
Isaac Earle | Repair | Target 1 | Target | Manipulator Repair Complete | Repair of the west side manipulator
in the west hot cell was completed today.
Part of the repair was done by entering |
|
|
69
|
Monday, January 21, 2013, 11:57 |
Isaac Earle | Repair | Target 2 | Target | Flask Repair | On January 15th, when attempting
to move the T2 target from the beam line
to the hot cell, the latch mechanism on the |
|
|
76
|
Tuesday, April 09, 2013, 17:06 |
Isaac Earle | Repair | Target 1 | Target | T1 Target Electronics Check | The T1-MK1 target protect and profile monitor
electronics were 'blip' tested by Bill Rawnsley
on April 5, 2013. The response from |
|
|
83
|
Friday, May 31, 2013, 16:07 |
Isaac Earle | Repair | Target 1 | Target | Power Supply Fan Failure | Today (May 31, 2013) I was contacted
regarding a burning smell and high temperatures
around the T1/T2 controls racks. Erwin |
|
|
84
|
Tuesday, June 04, 2013, 13:42 |
Isaac Earle | Repair | Target 1 | Target | T1 and T2 Power Supply Fans Replaced | Replacement of the power supply fans
for the T1 Power Supply, T2 Power Supply,
as well as an additional power supply in |
|
|
85
|
Friday, August 23, 2013, 10:39 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Cooling Package Inlet Pressure (P1) Sensor | The T1 cooling package inlet pressure
(P1) has been dropping since approximately
May 5, 2013 from the regular operating pressure |
|
|
86
|
Monday, September 09, 2013, 16:13 |
Isaac Earle | Repair | Target 2 | Cooling | Drop in T2 Cooling Package Water Level | On September 9th in the morning Ron
Kuramoto noticed that the T2 cooling package
expansion tank level was reading NOT OK for |
|
|
87
|
Monday, September 09, 2013, 16:22 |
Isaac Earle | Repair | Target 1 | Cooling | T1 P1 Transducer Replaced | The BL1A tunnel was accessed today
to assess a faulty reading from the T1 cooling
package inlet pressure transducer (T1P1). |
|
|
88
|
Wednesday, September 11, 2013, 16:13 |
Isaac Earle | Repair | Target 2 | Cooling | T2 Cooling Package Water Leak Repair | The T2 cooling package was uncovered
this morning and a leak was found coming
from the Swagelok ball valve on the 3/4" |
|
|
91
|
Tuesday, November 12, 2013, 11:49 |
Isaac Earle | Repair | Target 1 | Target | MH Hot Cell Lab Manipulator Overhaul | Complete overhaul of all manipulators
in the Remote Handling Hot Cell Lab in the
Meson Hall was performed by Peter Dudley |
|
|
92
|
Friday, November 22, 2013, 20:26 |
Grant Minor | Repair | Target 2 | Water Leak | T2 Water Leak - Target Assembly Removed and Water Sucked Out of B/L | T2 target water leak was identified earlier
this morning.
Isaac Earle, Ron Kuramoto and Keith |
|
|
93
|
Saturday, November 23, 2013, 18:37 |
Isaac Earle | Repair | Target 2 | Target | T2-MK1 Installation | - T2-MK1 target transported from the storage
area by Isaac and Grant and installed at
the T2 monolith. All services were |
|
|
94
|
Tuesday, November 26, 2013, 10:33 |
Isaac Earle | Repair | Target 2 | Target | T2-MK2 Water Flush | The T2-MK2 target in the hot cell
was flushed with water and then purged with
air so that stagnant water is not left sitting |
|
|
95
|
Monday, January 06, 2014, 15:55 |
Isaac Earle | Repair | Target 2 | Target | T2-MK2 Repair | The leaking 10cm Be target was removed
from position 3 on the T2-MK2 target ladder
and the water ports were blanked-off with |
|
|
96
|
Thursday, January 09, 2014, 15:21 |
Isaac Earle | Repair | Target 2 | Target | T2-MK2 Electrical Check | An electrical check was performed
on the T2-MK2 profile monitor by Bill Rawnsley.
All signals produced the expected response, |
|
|
100
|
Monday, January 20, 2014, 11:51 |
Isaac Earle | Repair | Target 2 | Water Leak | Water Leak from Meson Hall Mezzanine Near T2 | A water leak developed this morning
from a city water supply line at a hose connection
near the T2 expansion tank. Water was |
|
|
104
|
Monday, March 03, 2014, 11:55 |
Isaac Earle | Repair | Target 2 | Target | T2 Protect Monitor Moved to HC | The T2 Protect Monitor was transported
from the beam line to the hot cell this morning
using the transport flask. The move |
|
|
105
|
Tuesday, March 11, 2014, 13:50 |
Isaac Earle | Repair | Target 2 | Target | T2 Protect Monitor Returned to Beam Line | After the monitor assembly was moved to
the hot cell, electrical checks were performed
by Bill Rawnsley which showed the same results |
|
|
109
|
Tuesday, April 01, 2014, 10:17 |
Isaac Earle | Repair | Target 2 | Target | T2 Profile Monitor Actuation - Fault Report | The T2 profile monitor cannot be actuated
from the control room. When the solenoid
valve that supplies air to the air cylinders |
|
|
114
|
Friday, May 02, 2014, 15:49 |
Isaac Earle | Repair | Target 2 | Target | T2 Protect Monitor Elevation Correction | When beam was started in mid-April, it
was observed by Operations Group that with
the beam centered vertically within the protect |
|
|
115
|
Monday, May 05, 2014, 15:46 |
Isaac Earle | Repair | Target 2 | Target | T2 Protect Returned to B/L | The T2 protect monitor was returned to
the beam line using the shielded flask. The
alignment pin did not align with the hole |
|
|
118
|
Wednesday, July 02, 2014, 16:56 |
Isaac Earle | Repair | Target 1 | Cooling | T1-P2 and T2-P1 pressure transducers replaced. | The T1-P2 (outlet) pressure transducer
was replaced to address an erroneous signal.
The XTPAGE value now reads as expected. |
|
|
119
|
Monday, August 11, 2014, 16:57 |
Isaac Earle | Repair | Target 2 | Other | Air Amplifier Increased Cycle Rate | On Friday August 8th Ron Kuramoto observed
that the Meson Hall air amplifier cycle speed
had increased. Cycle time measurements |
|
|
120
|
Wednesday, August 13, 2014, 16:34 |
Isaac Earle | Repair | Target 1 | Other | Amplified Air Leak Narrowed Down to T1 Area | During the maintenance day today,
amplified air to the T1 area was valved off
in an attempt to pin point the location of |
|
|
121
|
Thursday, September 11, 2014, 15:36 |
Ron Kuramoto | Repair | Target 2 | Water Leak | 1A Tunnel T2 Cu-ALCW water leak | On Sep. 3rd
during the 6 hr maintenance day, Doug Preddy |
|
|
122
|
Thursday, October 16, 2014, 17:44 |
Ron Kuramoto | Repair | Target 2 | Water Leak | 1A Tunnel T2 Cu-ALCW water leak repair |
|
6x |
|
123
|
Thursday, November 06, 2014, 17:18 |
Ron Kuramoto | Repair | Target 2 | Cooling | 1AT2 Collimator B, faulty Thermister water out temperature | On 14Oct2014, the 1AT2 Collimator B water
outlet temperature rose to 100o
C. |
|
|
124
|
Thursday, November 06, 2014, 17:22 |
Ron Kuramoto | Repair | Target 2 | Cooling | 1AT2, faulty Thermister water out temperture |
|
|
|
125
|
Friday, November 14, 2014, 17:30 |
Isaac Earle | Repair | Target 1 | Target | T1-MK1 Target Failure / T1 Target Swap | -
On Nov 13 at ~1am the BL1A vacuum went bad.
The T1 and T2 volumes were isolated |
|
|
127
|
Monday, November 17, 2014, 10:25 |
Isaac Earle | Repair | Target 1 | Other | Amplified Air Leak In T1 Area Repaired | While the 1A blocks over the T1 area were
removed last week the opportunity was used
to investigate an air leak on the amplified |
|
|
129
|
Tuesday, December 09, 2014, 14:45 |
Isaac Earle | Repair | Target 1 | Target | T1-MK1 Repair Status (Pos'n 1 Plug Leak) | Between Nov 14 ~ Dec 9 the following
activities took place:
- The leaky 10mm Be target at pos'n |
|
|
133
|
Wednesday, January 07, 2015, 17:27 |
Isaac Earle | Repair | Target 2 | Water Leak | Water Leaks at T2 Cooling Package | The T2 cooling package was visually inspected
today after blocks were removed. With
the cooling package off the following leaks |
|
|
137
|
Friday, January 23, 2015, 13:28 |
Isaac Earle | Repair | Target 2 | Cooling | T2 Cooling Package Thermistor Defeats | Both defeats applied to T2 cooling package
thermistors were removed today (Col. B interlock
was jumpered, and the target water inlet |
|
|
138
|
Tuesday, January 27, 2015, 17:38 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Cooling Package 3/4" Valves Rebuilt - T1 MRO Complete | - Both 3/4" ball valves on the T1
cooling package target water circuit were
rebuilt, leak tested with house air pressure, |
|
|
140
|
Friday, February 06, 2015, 12:39 |
Isaac Earle | Repair | Target 1 | Target | T1-MK1 Repair Status (Pos'n 1 Plug Leak) | The T1-MK1 target is currently in
the hot cell for repair of a leak at position
1. See E-Log #129 for details on previous |
|
|
141
|
Wednesday, February 18, 2015, 14:49 |
Isaac Earle | Repair | Target 1 | Target | T1-MK1 Repair Complete | This is a continuation of work detailed
in E-Log #129 and #140.
- Static water test performed on |
|
|
144
|
Wednesday, March 04, 2015, 18:08 |
Isaac Earle | Repair | Target 2 | Cooling | T2 Cooling Package MRO Update | The following work was done today at the
T2 cooling package:
- Remainder of #4 Hansen o-rings |
|
|
146
|
Tuesday, March 31, 2015, 17:40 |
Isaac Earle | Repair | Target 2 | Cooling | T2 Thermistors Replaced | The Inlet (T1), Outlet (T2), Col.A (T6),
and Col. B (T7) thermistors at the T2 cooling
package all gave intermittent faulty readings |
|
|
158
|
Friday, May 01, 2015, 16:01 |
Isaac Earle | Repair | Target 1 | Other | RH Warm Cell Used by Beamlines Group for TNF Heat Exchanger Leak Check | The Meson Hall RH Lab Warm Cell was used
by Beamlines Group for hydrostatic testing
of the TNF heat exchanger. The location |
|
|
161
|
Monday, May 25, 2015, 12:48 |
Isaac Earle | Repair | Target 1 | Controls | T1/T2 Controls System Crash | At 9:15am this morning BL1A tripped off
due to loss of the watchdog signals for the
T1/T2 control system. Graham Waters |
|
|
170
|
Wednesday, August 19, 2015, 12:10 |
Isaac Earle | Repair | Other | Other | Warm Cell Water Window Seal Replacement Status | The following tasks were completed over
the past 2 weeks:
- Aquarium Technology Ltd. (UK) was |
6x |
|
171
|
Thursday, August 27, 2015, 15:47 |
Isaac Earle | Repair | Other | Water Leak | Warm Cell Water Window Seal Replacement Update | Since the previous E-Log the following
tasks have been completed:
- Panel spacer rods installed at |
|
|
173
|
Monday, September 28, 2015, 11:33 |
Isaac Earle | Repair | Other | Water Leak | Warm Cell Water Window Repair Complete | The warm cell water window tanks were filled
on September 17 after 2 weeks of curing time.
A water leak was found coming from |
|
|
175
|
Thursday, October 01, 2015, 11:43 |
Isaac Earle | Repair | Target 2 | Target | T2-MK2 Target Ladder Drive Motor Failure | The stepper motor that drives the
target ladder on T2-MK2 has failed. This
is the cause of the difficulty moving the |
|
|
179
|
Friday, October 09, 2015, 14:56 |
Isaac Earle | Repair | Target 2 | Other | T2 Protect Monitor Replacement | On Monday Oct 5th a decision was
made to uncover and remove the T2 Protect
Monitor due to faulty readings. The |
9x |
|
180
|
Friday, October 09, 2015, 15:18 |
Isaac Earle | Repair | Target 2 | Target | T2-MK2 Check at Hot Cell and Motor Drive Cable Replacement | While the T2 monolith was uncovered for
T2 Protect repair (see previous e-log), it
was decided that the T2 target should be |
7x |
|
181
|
Friday, October 09, 2015, 15:52 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 Protect Monitor Replacement and Inspection | When the damage to the T2 Protect Monitor
was found to be caused by flying debris from
a vacuum spike (see e-log #179), it was decided |
12x |
|
183
|
Thursday, November 05, 2015, 17:07 |
Isaac Earle | Repair | Target 2 | Target | T2-MK1 Profile Monitor Repair and Pos'n 3 Target Removal | The following work was performed on the
T2-MK1 target. The profile monitor
and monitor cage on this target were damaged |
8x |
|
188
|
Wednesday, February 24, 2016, 13:03 |
Isaac Earle | Repair | Other | Other | Target Flask 2-Ton Hoist Chain Twist Corrected | A 1/2 turn twist in the target flask
hoist chain has been corrected to address
a deficiency observed by inspectors by Gordon |
|
|
208
|
Friday, September 30, 2016, 16:54 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 - New Beryllium Targets Installed | The following work was performed
on the T1-MK2 target assembly during the
September 2016 Mini-shutdown: |
|
|
209
|
Friday, September 30, 2016, 16:59 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Cooling System Inlet Pressure Transducer Replaced | The T1 cooling system inlet pressure
transducer (EPICS ID: B1A:T1CS:PGIN, Omega
part # PX315-100GI) began failing in August |
|
|
211
|
Thursday, November 17, 2016, 17:58 |
Isaac Earle | Repair | Target 2 | Cooling | T2 Heat Exchanger Secondary Side Solenoid Valve Failure | At approximately 11am today the T2
cooling package heat exchanger secondary
side water flow suddenly dropped from ~11gpm |
|
|
216
|
Monday, March 27, 2017, 16:15 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Cooling System Target Water Return Hose Damaged | The 18' shielding block which lies west
of the T1 cooling package was removed on
Friday Mar 24 so that vacuum equipment could |
|
|
222
|
Tuesday, May 09, 2017, 16:35 |
Isaac Earle | Repair | Target 2 | Cooling | T2 target water flow gauge paddle wheel changed | During the target move on Thursday
May 4th the paddle wheel and paddle wheel
shaft for the T2CS:FGTGT sensor were changed |
|
|
224
|
Monday, July 10, 2017, 16:20 |
Keith C Ng | Repair | Target 2 | Target | T2 Heat Exchanger Secondary Side Solenoid Valve Failure | The T2 heat exchanger secondary side solenoid
failed on July 9 at approximately 19:30 (EPICS
ID: B1A:T2CS:SVSEC). The valve was |
|
|
225
|
Tuesday, July 25, 2017, 19:23 |
Isaac Earle | Repair | Target 2 | Cooling | T2 Heat Exchanger Secondary Side Solenoid Valve Failure (again) | At approximately 13:50 today the
T2 cooling system secondary side solenoid
valve (T2CS:SVSEC) failed to a closed position. |
|
|
230
|
Thursday, October 26, 2017, 16:12 |
Isaac Earle | Repair | Target 1 | Cooling | T1 collimator solenoid valve replaced | Around 10pm on Sunday Oct 22 beam
was tripped multiple times due to low flow
for the T1 collimator cooling circuit (B1A:T1:FGCOL). |
|
|
238
|
Thursday, May 10, 2018, 15:23 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 protect monitor and profile monitor replaced | During first injection of beam down 1A
problems were encountered with the T1 protect
monitor. Testing was done by Probes |
|
|
239
|
Friday, June 01, 2018, 17:50 |
Isaac Earle | Repair | Target 1 | Cooling | T1 collimator solenoid valve coil replaced | Flow stopped through the T1 collimator
cooling loop around the same time as a power
bump this afternoon. The problem was |
|
|
240
|
Tuesday, July 03, 2018, 11:09 |
Isaac Earle | Repair | Target 1 | Cooling | T1 cooling package outlet water pressure sensor replaced | The T1 cooling package outlet water
pressure sensor (B1A:T1CS:PGOUT) was replaced
this morning with a new unit. Over |
|
|
241
|
Monday, July 23, 2018, 09:39 |
Isaac Earle | Repair | Target 1 | Cooling | T1 collimator solenoid valve failed - Solenoid replaced | On Saturday July 21st the T1 Collimator
solenoid valve would not re-open after tripping
closed due to a (planned) loss of vacuum. |
|
|
242
|
Thursday, August 23, 2018, 11:52 |
Isaac Earle | Repair | Target 1 | Cooling | T1 cooling package pump failure and replacement | On Wednesday August 15th the T1 cooling
package tripped off, and could not be restarted.
On the EPICS screen the pump device went |
|
|
244
|
Thursday, September 06, 2018, 13:49 |
Isaac Earle | Repair | Target 1 | Cooling | T1 cooling package secondary side solenoid failed | On Friday Aug 31 at approximately
3am T1CS:FGSEC dropped to 0gpm flow.
This was confirmed to be a real reading when |
|
|
245
|
Thursday, October 25, 2018, 08:58 |
Keith C Ng | Repair | Other | Other | T1 collimator valve solenoid coil replaced again | On
23rd October we restarted the T1 and T2 water
packages after the mini shutdown and after |
|
|
248
|
Friday, January 25, 2019, 10:53 |
maicodallavalle | Repair | Other | Cyclotron electrical | Cyclotron Elevating system Motor electrical wire repairs | 2018 Cyclotron lid up problem. Station
#9 was found to have the motor
wires along the beam plain had damaged wire |
|
|
250
|
Tuesday, April 16, 2019, 15:35 |
Keith C Ng | Repair | Other | M9 | M9 project post shutdown summary | Completed work at m9 beam line:
- Removed existing service stand
and associated cable and water services. |
|
|
251
|
Wednesday, May 22, 2019, 14:25 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 target moved to HC; T1-MK1 target moved to BL | After extensive
testing over the last 2 weeks it was determined |
|
|
255
|
Thursday, January 30, 2020, 17:55 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 target assembly repair completed in hot cell | The following work was done to the T1-MK2
target in the hotcell between the dates of
May 24, 2019 - Jan 30, 2020 (See E-Log #251 |
|
|
259
|
Wednesday, March 04, 2020, 13:42 |
Ron Kuramoto | Repair | Other | Other | B/L 1A vacuum air leak repair | A 4” Marmon aluminum blank-off
flange and o-ring were replaced on the south
port of the T1 target monolith vacuum vessel. This |
|
|
270
|
Tuesday, October 27, 2020, 14:01 |
Isaac Earle | Repair | Target 2 | Cooling | T2 Collimator flow meter paddle wheel replaced | The T2 Collimator A flow meter signal (B1A:T2:FGCOLA)
began fluctuating and occasionally reading
0gpm on Sunday Oct 25 causing BL1A trips |
|
|
295
|
Wednesday, July 06, 2022, 12:49 |
Matthew Gareau | Repair | Other | Other | Helium line damage, and hotcell window oil leaking | Today myself and Adam Newsome started the
leak detection steps for a target exchange
and notice that the Helium line was not connected/broken |
|
|
296
|
Wednesday, July 06, 2022, 12:49 |
Adam Newsome | Repair | Other | Hot Cell | Hot Cell - Helium wand tubing broken | The tubing for the helium wand inside the
hot cell is broken and needs to be replaced.
More tubing has been ordered and the job |
|
|
298
|
Thursday, July 28, 2022, 12:51 |
Adam Newsome | Repair | Other | Hot Cell | Meson Hall Hot Cell - Nuclear Ventilation Issue | It was reported today by Peter Bratt that
the nuclear ventilation system for the hot
cell is not functioning. At this time, the |
|
|
307
|
Wednesday, January 11, 2023, 15:22 |
Adam Newsome | Repair | Target 2 | Target | T2 Target Ladder Motor - Coupling Failure | It was reported on Dec. 20, 2022 that when
Operations attempted to run the target ladder
motor, it was unresponsive. A fault report |
|
|
312
|
Monday, January 16, 2023, 15:06 |
Adam Newsome | Repair | Other | Active Sump | RH Active Sump - draining flow rate sensor repair | The flow rate sensor used to monitor the
drain rate from BL1A holding tank to active
sump, located in the active sump area, was |
|
|
314
|
Tuesday, January 17, 2023, 13:49 |
Adam Newsome | Repair | Other | Active Sump | Active Sump - Valve V6 Leaking | It was noticed today (2023-01-17) that
the valve V6, used in draining the BL1A Holding
Tank to the Active Sump, was leaky. This |
|
|
318
|
Friday, February 17, 2023, 14:36 |
Albert Kong | Repair | Other | Water Leak | T1/T2 Water Cooling Package Ball Valve Replacement | 5 and 3 Swagelok ball valves were replaced
from the T1 and T2 cooling packages respectively.
These are compression fit valves, |
|
|
324
|
Monday, March 06, 2023, 16:58 |
Albert Kong | Repair | Target 2 | Cooling | M20 O-Ring Replacement and Valve Replacement Leak Check | We replaced tha O-ring on M20 at
T2 and brought the target station down to
vacuum, which allowed the target water pump |
|
|
329
|
Thursday, May 11, 2023, 11:28 |
Adam Newsome | Repair | Target 1 | Target | T1-MK1 - broken target ladder motor coupler repaired | See Cyclotron Fault 15787. The target ladder
motor failed to move to the commanded position
during a test. The T1 area was uncovered |
|
|
332
|
Thursday, August 03, 2023, 10:33 |
Albert Kong | Repair | Target 2 | Cooling | T2 Expansion Tank Water Level Low (Leak Identified) | The water level in the T2 cooling system
expansion tank dropped to below the trip
treshold of 20 cm (ref Cyclotron fault #16123), |
7x |
|
344
|
Thursday, February 15, 2024, 12:38 |
Riley Sykes | Repair | Other | Hot Cell | Indium Extruder Hand Pump | Feb 1 2024
Hand Pump observed to be losing pressure
at full extension of cylinder, seals likely |
|
|
347
|
Tuesday, May 07, 2024, 13:21 |
Albert Kong | Repair | Target 2 | Cooling | T2 Cooling System Expansion Tank Ultrasonic Level Sensor Repair | At ~8am on May 06, the expansion tank level
sensor for the T2 cooling system suddenly
became noisy. |
|
|
178
|
Tuesday, October 06, 2015, 14:04 |
Isaac Earle | Other | Other | Controls | Instructions for loading display screen for T1/T2 | The following instructions were provided
by Graham Waters:
|
|
|
191
|
Thursday, March 24, 2016, 14:46 |
Isaac Earle | Other | Other | Other | TNF / 500MeV Resin Cans Removed from Storage Pit #1 | Three used TNF / 500MeV system cooling
system resin cans were removed from the Meson
Hall target storage pit (two from Hole #1, |
|
|
199
|
Friday, April 22, 2016, 14:45 |
Isaac Earle | Other | Other | Active Sump | RH MH Hot Cell Lab Active Sump Water Released | The Remote Handling Hot Cell Lab Active
Sump has been released to city sewer following
the procedure in Document-64834. The |
|
|
203
|
Tuesday, June 28, 2016, 08:32 |
Isaac Earle | Other | Other | Active Sump | RH MH Hot Cell Lab Active Sump Overflow | A call was received from the MCR
at approximately 21:30 on Monday June 27th
to report that active drains in the east |
|
|
204
|
Tuesday, June 28, 2016, 16:28 |
Isaac Earle | Other | Other | Active Sump | RH MH Hot Cell Lab Active Sump High Level Sensor Test | The high level sensor for the Meson
Hall Hot Cell Lab Active Sump was tested
today and worked as expected. When |
|
|
205
|
Wednesday, July 06, 2016, 13:31 |
Isaac Earle | Other | Other | Active Sump | Active Sump RCR Lab and MCR Alarms Not Working - Suspect Controls Issue | Further tests were done on the active sump
high level float switch today. The
switch was triggered 1 time by filling the |
|
|
223
|
Monday, May 15, 2017, 16:55 |
Isaac Earle | Other | Target 2 | Target | T2 profile monitor actuation issue | On Thursday May 11th operators attempted
to move the T2 profile monitor (T2-MK2) to
the IN position but were unsuccessful. The |
|
|
226
|
Thursday, July 27, 2017, 08:57 |
Isaac Earle | Other | Target 2 | Cooling | Failed T2CS:SVSEC valves investigation | The three failed T2 cooling system
secondary side solenoid valves were tested
yesterday to try to determine the problem. |
|
|
246
|
Thursday, November 01, 2018, 13:57 |
Keith C Ng | Other | Other | Other | nuclear venillation in hot cells not working | Randomly checked on the nuclear ventilation
for the Meson Hall Hotcells and discovered
they were not running again (both magnahelic |
|
|
254
|
Monday, January 20, 2020, 16:07 |
Isaac Earle | Other | Other | Other | Second 55-gal drum moved to cyclotron east vault tunnel | The second (and final) 55 gallon
drum containing active items from the Meson
Hall East Hot Cell was transported today |
|
|
288
|
Thursday, April 14, 2022, 14:38 |
Adam Newsome | Other | Target 2 | Diagnostics | Issue with Protect Monitor SHV Cable | Diagnostics group (Shengli Liu) noted a
lack of connectivity between control panel
and T2 Protect Monitor via the high voltage |
|
|
294
|
Wednesday, June 08, 2022, 08:59 |
Adam Newsome | Other | Target 2 | Cooling | T2 flow rate sensor (BL1A:T2CS:FGTGT ) - warning and trip limits adjusted | See fault 14966:
Normal
0
|
|
|
297
|
Wednesday, July 06, 2022, 12:52 |
Adam Newsome | Other | Other | Hot Cell | Potential hot cell window oil leak | Some oil was noticed around the hot cell
window, on the control panel, and on the
ground below the control panel. A leak is |
|
|
306
|
Tuesday, January 03, 2023, 07:42 |
Adam Newsome | Other | Other | Active Sump | Active Sump - Level Check | The sump level was checked by Robin Swanson
on Dec. 31, 2022. It was essentially empty
- see attached photo. |
|
|
331
|
Tuesday, July 18, 2023, 09:14 |
Adam Newsome | Other | Target 1 | Cooling | T1 Cooling Package: target flow (FGTGT) sensor noise issues | Between 1:00 pm and 6:00 pm on July 17,
2023, the T1 target cooling water flow rate
sensor exhibited some noise which resulted |
|
|
346
|
Wednesday, April 03, 2024, 10:48 |
Adam Newsome | Other | Other | BL1A Holding Tank | BL1A Holding Tank - water level check | As of 2024-04-03, the BL1A Holding Tank
water level is approximately 580L. It is
recommended to drain the tank prior to the |
|
|
349
|
Friday, June 28, 2024, 15:44 |
Albert Kong | Other | Other | Transfer Flask | Inspection of Primary Target Transfer Flask |
Normal
0
|
|
|
353
|
Monday, September 09, 2024, 09:39 |
Albert Kong | Other | Target 2 | Cooling | B1A:T2CS:FGSEC:RDFLOW noisy, CYCLOTRON Fault 17321 | Secondary flow sensor B1A:T2CS:FGSEC:RDFLOW
on the T2 cooling station suddenly became
very noisy at around 11 pm, 01 September |
|
|
355
|
Thursday, October 10, 2024, 12:24 |
Adam Newsome | Other | Other | Hot Cell | Safety Walkaround Complete - Meson Hall HC/WC Area | A safety walkaround was completed for the
Meson Hall Hot/Warm Cells.
The resulting spreadsheet can be |
|
|
3
|
Friday, November 04, 2011, 13:36 |
Isaac Earle | Maintenance | Target 2 | Target | Kaon Target (Training) | Moved Kaon Target from storage
pit to remote handling hot cell using flask
as training exercise. Safety surveyor |
|
|
4
|
Tuesday, December 20, 2011, 09:54 |
Isaac Earle | Maintenance | Target 1 | Target | Replaced T1-MK1 Target Ladder | Replaced T1-MK1 target ladder with the
new ladder design which has an integrated
upper slide plate (2 less sealing locations) |
|
|
5
|
Thursday, December 22, 2011, 15:27 |
Isaac Earle | Maintenance | Target 1 | Target | T1-MK1 Transferred to Storage Pit | T1-MK1 target transferred from hot
cell to storage pit position #3 to free up
the hot cell in preparation for shut-down |
|
|
6
|
Thursday, January 05, 2012, 10:18 |
Isaac Earle | Maintenance | Target 2 | Cooling | Swapped Resin in T2 Cooling Package | Drained T2 cooling package water, collected
sample and delivered to RPG. Swapped
resin can, refilled, and restarted cooling |
|
|
7
|
Thursday, January 05, 2012, 10:21 |
Isaac Earle | Maintenance | Target 1 | Cooling | Defeated T1 and T2 cooling package vacuum interlocks. | Defeated T1 and T2 cooling package
vacuum interlocks at 1-C panel on South mezzanine
in Meson Hall to allow cooling packages to |
|
|
8
|
Friday, January 06, 2012, 15:37 |
Isaac Earle | Maintenance | Target 2 | Target | Transferred M20 beam blocker to hot cell | Uncovered T2 monolith and transferred M20BB to hot cell using flask. |
|
|
9
|
Thursday, January 12, 2012, 11:34 |
Isaac Earle | Maintenance | Target 2 | Target | Replaced M20 Beam Blocker Vacuum Seal O-Rings | Replaced M20 beam blocker vacuum
seal o-rings. Old o-rings were noticeably
harder, but not brittle or cracked. Applied |
|
|
14
|
Wednesday, January 25, 2012, 13:26 |
Isaac Earle | Maintenance | Target 2 | Target | M9BB Returned to Beam Line | M9 beam blocker returned to beam line.
T2 target disconnected, picked up
using flask, and returned to beam line as |
|
|
15
|
Monday, January 30, 2012, 16:44 |
Isaac Earle | Maintenance | Target 1 | Cooling | Completed T1 Cooling Package MRO | Replaced
all o-rings and filters on the T1 cooling
package. Replaced resin can. Refilled |
|
|
26
|
Tuesday, April 03, 2012, 15:55 |
Isaac Earle | Maintenance | Target 1 | Target | T1 Ladder Position Look-up Tables Updated | Graham Waters has activated the appropriate
target ladder position look-up tables for
the T1-MK1 target which was installed in |
|
|
29
|
Thursday, April 05, 2012, 15:22 |
Isaac Earle | Maintenance | Target 1 | Target | T1 & T2 Profile and Protect "Blip" Test | Diagnostics group completed their
"blip" signal response tests on
the T1 and T2 profile and protect monitors. |
|
|
31
|
Thursday, April 12, 2012, 15:19 |
Isaac Earle | Maintenance | Target 2 | Target | T2 Target Water Drained | In preparation for extended periods
of the T2 volume being vented during the
M20 repair, the T2 water package was shut-off, |
|
|
37
|
Wednesday, June 06, 2012, 08:58 |
Isaac Earle | Maintenance | Target 2 | Target | T2 Monolith Leak Check | While leak checking components in
the M20 front end on May 25th, the top of
the T2 monolith was also checked by flooding |
|
|
44
|
Friday, June 22, 2012, 13:54 |
Isaac Earle | Maintenance | Target 2 | Target | Air Amplifier Rebuild Complete | A full rebuild of the upper air amplifier
was completed. New anodized aluminum
barrels were installed (replacing the old |
|
|
45
|
Tuesday, June 26, 2012, 09:05 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 & T2 Target Water Flow Transducers Serviced | The target water outlet flow transducers
on the T1 and T2 cooling packages were serviced
(new shaft, paddle wheel, & o-ring) to |
|
|
57
|
Thursday, September 13, 2012, 18:09 |
Isaac Earle | Maintenance | Target 1 | Cooling | September Shutdown T1 & T2 MRO | The following tasks were performed
during the 2012 September Shutdown:
- Both targets moved to position |
|
|
64
|
Monday, December 10, 2012, 15:42 |
Isaac Earle | Maintenance | Target 1 | Target | T1-MK2 Target Maintenance | - T1-MK2 target moved from storage pit
to hot cell
- Removed unused proximity sensor |
|
|
66
|
Tuesday, January 08, 2013, 10:52 |
Isaac Earle | Maintenance | Target 2 | Target | T2-MK1 Target Maintenance | - T2-MK1 target transported from storage
pit to hot cell
- Proximity sensor removed |
|
|
71
|
Tuesday, January 29, 2013, 15:55 |
Isaac Earle | Maintenance | Target 2 | Cooling | T2 H.E. Transported to Warm Cell | Friday Jan 25:
- Both sides of heat exchanger drained,
disconnected, and capped |
|
|
72
|
Tuesday, February 05, 2013, 09:50 |
Isaac Earle | Maintenance | Target 2 | Target | T2-MK2 target moved from beam line to hot cell | The T2-MK2 target was transported from
the beam line to the RH hot cell. The
profile monitor was secured in the 'in' position |
|
|
73
|
Wednesday, March 06, 2013, 12:13 |
Isaac Earle | Maintenance | Target 2 | Cooling | T2 Heat Exchanger MRO | - The new tube array was picked up from
Kaltech on Feb 8th (observed vessel holding
60psi on hydro test at their shop) |
7x |
|
74
|
Monday, March 18, 2013, 15:17 |
Isaac Earle | Maintenance | Target 2 | Target | T2-MK2 Target Maintenance and Re-Wiring | - T2-MK2 target moved from beamline to
hot cell (Feb 4th)
- Steel target support shield installed |
|
|
75
|
Tuesday, March 26, 2013, 10:55 |
Isaac Earle | Maintenance | Target 1 | Target | T1-MK1 Re-wiring and MRO Complete | The following work was performed
on the T1-MK1 target:
- Unused proximity sensor removed |
|
|
108
|
Friday, March 28, 2014, 13:59 |
Isaac Earle | Maintenance | Target 2 | Cooling | T2 P1 Transducer and T2 Q1 Flow Meter Replaced | The T2 P1 pressure transducer (Omega PX315-100GI)
and T2 Q1 Proteus flow meter (0150SSTF3)
have been replaced with new units to address |
|
|
131
|
Monday, December 22, 2014, 14:31 |
Isaac Earle | Maintenance | Target 2 | Water Leak | Drop in T2 water level | This morning at 5:30am the T2 cooling package
expansion tank switched to WARNING LEVEL
NOT OK. There was no change in BL1A |
|
|
139
|
Monday, February 02, 2015, 16:06 |
Isaac Earle | Maintenance | Target 2 | Cooling | T2 MRO Status | - T2-MK2 target (currently in the T2 monolith)
purged with air
|
|
|
186
|
Monday, January 25, 2016, 16:54 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 MRO Work | The following work was performed at the
T1 cooling package and target between January
18-21, 2016: |
|
|
219
|
Tuesday, April 11, 2017, 17:02 |
Isaac Earle | Maintenance | Target 2 | Cooling | T2 Cooling System MRO | The following work has been completed
on the T2 cooling package:
- T2 system drained to South TNF |
|
|
228
|
Tuesday, August 29, 2017, 12:17 |
Isaac Earle | Maintenance | Target 1 | Target | T1-MK1 and T2-MK1 Hansen water fittings replaced | The #6 male Hansen fittings for the
T1-MK1 and T2-MK1 targets (both currently
stored in the target storage pit) were replaced |
|
|
236
|
Tuesday, April 10, 2018, 11:20 |
Isaac Earle | Maintenance | Other | Cooling | T1 and T2 cooling package shutdown MRO work | The following work was performed
on the T1 and T2 cooling packages during
the 2018 shutdown: |
|
|
237
|
Friday, April 13, 2018, 14:21 |
Isaac Earle | Maintenance | Other | Other | M20 beam blocker MRO and T1/T2 final checks | The M20 beam blocker main shaft seals were
replaced as per the T1/T2 target device maintenance
schedule. Both air cylinders were found |
|
|
247
|
Thursday, January 10, 2019, 13:51 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 and T2 cooling packages inspected | The T1 and T2 cooling packages were inspected
today while running. No water leaks
were observed at either package including |
|
|
249
|
Tuesday, February 26, 2019, 10:55 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 and T2 MRO work and solenoid valve change summary | The following work was completed between
Jan 16 - Feb 19, 2019:
T1 and T2 cooling packages |
|
|
256
|
Wednesday, February 05, 2020, 14:53 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 & T2 cooling package MRO work completed | Annual MRO work on the T1 and T2
cooling packages is now complete. The
following tasks were performed: |
|
|
257
|
Monday, February 10, 2020, 14:51 |
Isaac Earle | Maintenance | Other | Other | T1-MK2 target and M9BB moved | The T1-MK2 target was moved from
the hot cell to Hole #5 in the storage pit.
The M9 beam blocker was then moved from the |
|
|
261
|
Monday, March 23, 2020, 16:13 |
Isaac Earle | Maintenance | Other | Other | M9 beam blocker MRO completed | M9 beam blocker MRO work was completed
in the hot cell today. This included
replacement of the main shaft seals and replacement |
|
|
269
|
Wednesday, August 19, 2020, 12:57 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1/T2 MRO summary for 2020 shutdown | The following work was completed during
the 2020 shutdown period for BL1A (Jan-Aug
2020): |
|
|
274
|
Friday, April 09, 2021, 12:42 |
Matthew Gareau | Maintenance | Target 2 | Cooling | Changed the paddle wheel, o ring, and shaft in the Collimator A flow meter at the T2 package | With the assistance of Maico we changed
the paddle wheel, o ring, and shaft in the
Collimator A flow meter (Q4) at the T2 package. |
|
|
276
|
Thursday, February 17, 2022, 13:03 |
Matthew Gareau | Maintenance | Target 1 | Target | T1 MK2 wire scanner and protect monitor test removal and reattachment with pin straightening | this Work was done on 09 Dec 2021.
Since Isaac Earle was leaving Triumf
he was giving us (maico, chad, adam, and |
|
|
277
|
Thursday, March 10, 2022, 11:18 |
Adam Newsome | Maintenance | Target 2 | Cooling | Changed paddle wheel, o-ring, and shaft in flow sensors at T2 cooling package | The paddle wheels, o-rings, and shafts
were changed at the T2 cooling package for
the following sensors: |
|
|
278
|
Thursday, March 10, 2022, 13:57 |
Adam Newsome | Maintenance | Target 1 | Cooling | Changed paddle wheel, o-ring, and shaft in flow sensors at T1 cooling package | The paddle wheels, o-rings, and shafts
were changed at the T1 cooling package for
the following sensors: |
|
|
279
|
Friday, March 11, 2022, 15:05 |
Adam Newsome | Maintenance | Target 1 | Cooling | O-rings on T1 cooling package water reservoir changed | The four o-rings on top of the T1 cooling
package water reservoir were changed as per
the recommended 5 year replacement schedule. |
|
|
280
|
Friday, March 11, 2022, 15:06 |
Adam Newsome | Maintenance | Target 2 | Cooling | O-rings on T2 cooling package water reservoir changed | The four o-rings on top of the T2 cooling
package water reservoir were changed as
per the recommended 5 year replacement schedule. |
|
|
281
|
Friday, March 11, 2022, 15:08 |
Adam Newsome | Maintenance | Target 1 | Cooling | Filters replaced: T1 cooling system | All filters were replaced for the T1 cooling
system: demineralizing resin circuit, target
water system, and M15. |
|
|
282
|
Friday, March 11, 2022, 15:09 |
Adam Newsome | Maintenance | Target 2 | Cooling | Filters replaced: T2 cooling system | All filters were replaced for the T2 cooling
system: demineralizing resin circuit and
target water system. |
|
|
283
|
Monday, March 14, 2022, 14:08 |
Adam Newsome | Maintenance | Target 1 | Cooling | T1 cooling system: filled, tuned, leak-checked | The T1 cooling system was refilled with
water via the expansion tank until the tank
level read approximately 38 cm. |
|
|
284
|
Monday, March 14, 2022, 14:09 |
Adam Newsome | Maintenance | Target 2 | Cooling | T2 cooling system: filled, tuned, leak-checked | The T2 cooling system was refilled with
water via the expansion tank until the tank
level read approximately 38 cm. |
|
|
290
|
Thursday, May 05, 2022, 14:38 |
Adam Newsome | Maintenance | Target 2 | Controls | T2-MK1: profile monitor actuation check and repair to connector | An attempt was made to actuation the T2
profile monitor, however it showed up in
EPICS as being not present. Furthermore, |
|
|
301
|
Tuesday, August 30, 2022, 14:24 |
Adam Newsome | Maintenance | Other | Hot Cell | Nuclear Ventilation - Filter Change | Mechanical Services Group changed the pre-filter
in the ventilation system on Aug. 29, 2022
as per work permit C2022-08-29-2. |
|
|
304
|
Tuesday, October 04, 2022, 09:59 |
Adam Newsome | Maintenance | Target 2 | Cooling | T2 cooling package maintenance - mini-shutdown 2022 | The following maintenance tasks were performed
during mini-shutdown of 2022 with the goal
of resolving the Fault 14966 (target water |
|
|
305
|
Tuesday, October 11, 2022, 11:27 |
Adam Newsome | Maintenance | Target 1 | Cooling | T1 inlet pressure transducer replacement | A fault was reported June 21, 2022 (Fault
15033) regarding T1 inlet pressure warnings... |
|
|
308
|
Thursday, January 12, 2023, 10:36 |
Adam Newsome | Maintenance | Target 1 | Water Leak | T1 and T2 - Cooling Package Water Leaks - Ball Valves | Upon uncovering the T1 and T2 areas to
prepare for regular cooling package maintenance,
it was discovered that multiple ball valves |
|
|
310
|
Monday, January 16, 2023, 15:01 |
Adam Newsome | Maintenance | Target 1 | Cooling | T1 Cooling Package MRO - 2023 Shutdown | T1 Cooling Package MRO began Jan. 16, 2023.
The following maintenance tasks have |
|
|
311
|
Monday, January 16, 2023, 15:04 |
Adam Newsome | Maintenance | Target 2 | Cooling | T2 Cooling Package MRO - 2023 Shutdown | T2 Cooling Package MRO began Jan. 16, 2023.
The following maintenance tasks have |
|
|
313
|
Tuesday, January 17, 2023, 13:46 |
Adam Newsome | Maintenance | Other | Active Sump | Filter Change: RH Active Sump and BL1A Holding Tank Drain Output | The CUNO filters were changed 2023-01-17
for:
BL1A Holding Tank drain |
|
|
315
|
Wednesday, February 01, 2023, 14:23 |
Albert Kong | Maintenance | Target 1 | Cooling | T1 Cooling Package: flow test after resin exchange / valve leak check / faulty(?) dial pressure gauge | Maico/Eric/Albert:
The expansion tank in T1 was filled
to ~36cm in the morning. |
|
|
316
|
Thursday, February 02, 2023, 10:35 |
Albert Kong | Maintenance | Target 1 | Cooling | T1 Cooling Package Draining (Prep for Valve Replacement) | Water reservoir in T1 started draining
at ~7.30 am, will leave till tomorrow or
overnight to fully drain. |
|
|
317
|
Thursday, February 02, 2023, 15:14 |
Albert Kong | Maintenance | Target 1 | Cooling | T1 Cooling Package: Leaked Valve Inspection | A 0.75" SwageLok ball valve that was
taken out from the T1 cooling package was
inspected (SS-45S12). |
|
|
319
|
Tuesday, February 21, 2023, 16:56 |
Albert Kong | Maintenance | Target 2 | Other | M20 BB moved to meson hall hot cell roof | The M20 beam blocker was moved from the
T2 monolith to the meson hall hot cell with
the remote handling flask (completed ~4pm). |
|
|
320
|
Wednesday, March 01, 2023, 13:10 |
Albert Kong | Maintenance | Other | Cooling | T1/T2 Water Cooling Package Heat Exchanger Ball Valve Replacement | 3x 3/4" swagelok ball valves (2x at
T2 and 1x at T1) were replaced after the
water cooling line was shut off at the BL1A |
|
|
321
|
Thursday, March 02, 2023, 06:59 |
maicodallavalle | Maintenance | Target 1 | Cooling | Refilled Expasion Tank | I have refilled the water package on T1
with DI water. The Expansion Tank is at 37cm.
This may change when pump is turned on. |
|
|
322
|
Thursday, March 02, 2023, 07:04 |
maicodallavalle | Maintenance | Target 2 | Cooling | Refilled Expasion Tank | I have filled the water package on T2 with
DI water. The expansion tank is at 38.1cm.
This may change when the pump is turned on. |
|
|
323
|
Friday, March 03, 2023, 16:00 |
Albert Kong | Maintenance | Target 2 | Other | M20 Return to T2 Monolith + Vaccum Leak / T1-T2 Valve Re-inspection | We moved M20 back to the T2 monolith
and re did the connections for air + limit
switches + T2 profile monitor air. |
|
|
325
|
Wednesday, March 15, 2023, 15:56 |
Albert Kong | Maintenance | Target 2 | Controls | T2 - M9 and M20 beam blocker actuation and vacuum test | We tested the actuation of the M9/M20
beam blockers on the T2 monolith (3-4pm).
Vacuum levels remained steady throughout |
6x |
|
326
|
Thursday, March 30, 2023, 13:17 |
Albert Kong | Maintenance | Other | Target | Air Amplifier Testing: M9 BB (AKA T2 blocker), M20 BB, T2 MK1 prof. monitor, T1 MK1 prof. monitor actuation | We tested the air amplifiers by actuating
the beam blockers and profile monitors on
the T1 and T2 target stations. |
|
|
327
|
Thursday, April 06, 2023, 13:35 |
Albert Kong | Maintenance | Target 1 | Controls | T1 Motor Controller Hearbeat Trip (+T2 Heartbeat Trip) | The T1 motor controller hearbeat tripped
(noticed this morning).
This does not seem prevent beam delivery |
|
|
328
|
Wednesday, May 03, 2023, 10:06 |
Adam Newsome | Maintenance | Other | Hot Cell | Meson Hall Hot Cell - Nuclear Ventilation HEPA Filter Changed, Operational | The HEPA filter in the nuclear ventilation
system for the Meson Hall Hot Cell was changed
and tested by mechanical services under work |
|
|
333
|
Tuesday, October 17, 2023, 10:16 |
Eric Lahe | Maintenance | Other | Active Sump | Testing the Remote Handling Lab Active Sump Level Sensor | The level sensor for the active sump in
the RH lab was tested.
The level sensor is working properly |
|
|
334
|
Tuesday, October 17, 2023, 14:25 |
Albert Kong | Maintenance | Other | Other | T1/T2 Air Amplifier Spool O-Ring Servicing | Today we re-lubricated the o-rings on the
top air amplifier for T1/T2, and replaced
the o-rings on the bottom air amplifier with |
|
|
338
|
Thursday, January 11, 2024, 15:10 |
Albert Kong | Maintenance | Other | Cooling | T1/T2 Cooling Pkg. Proteus Paddle Wheel Maintenance, CUNO Filter Replacement, and Fitting Inspection | The following tasks were performed:
All electrical, water,
and pneumatic connections to the T1 target |
|
|
345
|
Thursday, February 15, 2024, 14:53 |
Albert Kong | Maintenance | Target 2 | Air amplifiers | T2 Lower Air Amplifier Maintenance/Rebuild | The lower amplifier for the T2 target station
air supply was removed for teardown, inspection,
and rebuild. |
|
|
357
|
Friday, November 29, 2024, 11:57 |
Adam Newsome | Maintenance | Other | Hot Cell | Hot cell and warm cell maintenance tasks | The following maintenance tasks were completed
on 2024-11-29 by A. Newsome, A. Kong, A.
Tam, M. Dalla Valle: |
|
|
2
|
Thursday, June 30, 2011, 16:47 |
John Wong | Development | Target 1 | Target | Testing Elog | blah blah blah.... fjda;jfeowifjoajglfa;nafg |
|
|
43
|
Friday, June 22, 2012, 13:48 |
Isaac Earle | Development | Target 1 | Cooling | T1 & T2 Expansion Tank Level Sensor Recording Enabled | Mike Mouat enabled recording for T1 and
T2 expansion tank warning and trip level
sensors on XTPAGE/XSTRIP. |
|
|
51
|
Tuesday, July 17, 2012, 15:30 |
Isaac Earle | Development | Target 1 | Cooling | T1 & T2 Expansion Tank Level Warnings Added | Mike Mouat and Juan Pon have modified
the control system so that the control room
will receive a message when the warning or |
|
|
52
|
Monday, July 23, 2012, 16:01 |
Isaac Earle | Development | Target 1 | Target | Target Flask Seismic Restraint Clamps Installed | Installation of the seismic restraint
clamps has been completed for the MK1 and
MK2 target flasks in the Remote Handling |
|
|
78
|
Friday, April 12, 2013, 17:33 |
Isaac Earle | Development | Target 1 | Cooling | T1 & T2 high-temp limit switch installation, wiring, and commissioning complete | Installation, wiring, and commissioning
of the high temperature limit switches for
the T1 and T2 cooling packages was completed |
|
|
81
|
Friday, April 19, 2013, 09:55 |
Isaac Earle | Development | Target 1 | Cooling | T1&T2 cooling package safety/standards compliance upgrade complete (SASP0120) | Yesterday (April 18th) the T1 and T2 cooling
package PRV outlet lines were routed to the
active drain in the 1A tunnel. All |
|
|
82
|
Tuesday, May 14, 2013, 13:26 |
Isaac Earle | Development | Target 1 | Target | T1 & T2 Profile Scan | The T1 and T2 profile monitors were used
during today's development shift. Target
ladder movement for T1 was done at the panel |
|
|
90
|
Wednesday, October 23, 2013, 15:30 |
Isaac Earle | Development | Target 1 | Cooling | T1 & T2 High Temp Safety Switch Tested | An end-to-end test was performed
on the new T1 and T2 high temperature safety
switches yesterday during the maintenance |
|
|
107
|
Tuesday, March 25, 2014, 18:24 |
Isaac Earle | Development | Target 2 | Water Leak | Water Detecting Sensor Install at T1 & T2 | Water detecting strips were installed around
the T1 and T2 areas today with Doug Preddy
and contractors from SMT Research. Four |
9x |
|
116
|
Wednesday, May 14, 2014, 20:36 |
Grant Minor | Development | Target 2 | Target | Target exercised to position 0, then back to 2.0 mm above position 4 | The T2 target was exercised to position
0 around 6:15pm so that the T2 profile monitor
could be used by operations. The T2 |
|
|
126
|
Monday, November 17, 2014, 10:14 |
Isaac Earle | Development | Target 1 | Active Sump | Filter Installed Downstream of RH HC Lab Active Sump | A filter housing and filter were installed
by Dan McDonald on November 14 in the piping
section between the Remote Handling Hot Cell |
|
|
143
|
Friday, February 27, 2015, 18:06 |
Isaac Earle | Development | Target 1 | Target | T1 Rotary Collimator Water and Air Line Investigation | Ron Kuramoto, Keith Ng, John McKinnon,
and myself spent some time today investigating
water and air lines related to the T1 Rotary |
|
|
147
|
Thursday, April 09, 2015, 13:56 |
Isaac Earle | Development | Target 2 | Target | T2-MK2 target wired for version identification, cable ties replaced, ready for use | The "POT/CAM" MS connector on
the T2-MK2 has been wired to allow automatic
target version number identification by the |
|
|
151
|
Wednesday, April 22, 2015, 09:46 |
Isaac Earle | Development | Target 1 | Target | Water Sensors Installed on T1 Monolith | Four water sensors have been installed
on top of the T1 monolith. These water
sensors were wired and brought to the area |
|
|
153
|
Wednesday, April 22, 2015, 15:17 |
Isaac Earle | Development | Target 1 | Target | T1-MK2 wired for version identification | The T1-MK2 target was wired for automatic
target version detection by the new PLC control
system (A to C jumper in POT/CAM MS |
|
|
154
|
Thursday, April 23, 2015, 13:40 |
Isaac Earle | Development | Target 2 | Other | T2 Protect Monitor Elevation Adjustment | - T2 Protect Monitor moved from the beam
line to the hot cell on Monday April 20th
- Elevation of the plate center measured |
|
|
157
|
Tuesday, April 28, 2015, 15:55 |
Isaac Earle | Development | Target 1 | Target | Target Version Jumper Wires Installed for T1-MK1 and T2-MK1 | The T1-MK1 and T2-MK1 targets have
been re-wired to allow version identification.
Work was performed in the target storage |
|
|
162
|
Thursday, June 11, 2015, 16:59 |
Isaac Earle | Development | Other | Controls | Lab Test of New T1/T2 Level Sensors | The new T1/T2 level sensors (Omega LVCN414)
were tested in the RH HC lab today using
the Omega software on a laptop and positioning |
|
|
163
|
Friday, June 19, 2015, 17:11 |
Isaac Earle | Development | Other | Controls | PLC Test of Ultrasonic Level Sensor | The new T1/T2 level sensors
(Omega LVCN414) were hooked up to the PLC |
|
|
165
|
Wednesday, July 08, 2015, 16:21 |
Isaac Earle | Development | Target 1 | Target | 0.003" 347 SS Sheet for T1/T2 Targets Received | A 5lb roll of 347SS sheet was received
today. This alloy is to be used for
the target windows of the new T1 and T2 beryllium |
|
|
166
|
Thursday, July 09, 2015, 13:51 |
Isaac Earle | Development | Other | Target | New T1 and T2 Beryllium Targets Ordered | An order for new T1 and T2 beryllium
targets was submitted to the TRIUMF machine
shop today. A total of seven T2 targets |
|
|
168
|
Friday, July 17, 2015, 10:14 |
Isaac Earle | Development | Target 1 | Target | T1/T2 Be Target Failure History & Replacement Plan | T1 and T2 beryllium target failure history
was investigated back to 2000 (as far as
XSTRIP records were readily available). For |
|
|
169
|
Thursday, August 13, 2015, 09:47 |
Isaac Earle | Development | Other | Other | "Clamp A" disassembled and used to build clamp "TRH1257-#01" | The 4" Marman flange clamp (IRH0001)
labeled "Clamp A", as used
in the testing detailed in Document-114623 |
|
|
184
|
Thursday, December 17, 2015, 13:31 |
Grant Minor | Development | Other | Target | T1/T2 Target Cassette - window / end cap manufacturing change (WO 41527) | Isaac Earle has recently been managing
the fabrication of some new Be target cassettes
for the T1 / T2 Meson Hall target ladders |
|
|
189
|
Monday, March 07, 2016, 18:22 |
Isaac Earle | Development | Target 1 | Controls | Preliminary Testing of T1 Control System Complete | Preliminary testing of the new PLC
control system and EPICS interface was completed
today for the T1 target, T1 cooling package, |
|
|
190
|
Wednesday, March 16, 2016, 16:50 |
Isaac Earle | Development | Target 2 | Controls | Preliminary Testing of T2 Control System Complete | Preliminary testing of the new
PLC control system and EPICS interface was |
|
|
192
|
Thursday, March 24, 2016, 15:38 |
Isaac Earle | Development | Target 1 | Target | T1/T2 Beryllium Target Test Jig Fabrication Complete | Fabrication of the T1/T2 beryllium target
testing jig (TBP1721) was completed today
by Dan MacDonald. With a target installed |
|
|
194
|
Thursday, April 07, 2016, 16:44 |
Isaac Earle | Development | Other | Controls | T1/T2 Controls "Assembly Tests" Completed | The T1/T2 Control System "Assembly
Tests" (Document 118467 Release
#1, Section 5) have been completed. The |
|
|
195
|
Monday, April 11, 2016, 13:51 |
Isaac Earle | Development | Other | Other | Target Transfer Flask Hoist Hook Lower Limit Adjusted | The lower limit of the flask hoist
hook has been adjusted. The travelling
nut for the lower limit was rotated 3 notches |
|
|
202
|
Tuesday, June 21, 2016, 09:25 |
Isaac Earle | Development | Other | Controls | T1/T2 EPICS System With-Beam Testing | With-beam commissioning tests were
completed today by Tony Tateyama and Isaac
Earle. The test results are attached |
|
|
206
|
Tuesday, August 30, 2016, 14:09 |
Isaac Earle | Development | Other | Controls | T1/T2 PLC Code Update | A new version of the T1/T2 PLC code
has been uploaded to the PLC CPU. The
main change in the new version is a fix to |
|
|
207
|
Thursday, September 08, 2016, 17:26 |
Isaac Earle | Development | Other | Active Sump | New Active Sump High Level Switch and Electronics Installed | To address the deficiencies identified
in E-Logs #204 and #205 the old active sump
high level switch was replaced with Omega |
|
|
210
|
Thursday, October 06, 2016, 12:16 |
Isaac Earle | Development | Target 1 | Controls | Expansion Tank High Level Warning Added | An expansion tank high level warning
has been added to the T1/T2 control system
under Work Request #4011. The purpose |
|
|
217
|
Thursday, March 30, 2017, 09:48 |
Isaac Earle | Development | Other | Controls | T1/T2 control system de-glitching & target ID changes | The following changes were made to
the T1/T2 PLC control system:
- De-glitching system investigated |
|
|
218
|
Wednesday, April 05, 2017, 17:55 |
Isaac Earle | Development | Other | Target | T2 area devices alignment strategy | A strategy for alignment of the T2 protect
monitor, T2 target, and T2 Collimator A was
discussed today and decided upon by Yuri |
|
|
220
|
Tuesday, April 11, 2017, 17:31 |
Isaac Earle | Development | Target 2 | Target | T2-MK2 target MRO and alignment of T2 devices | The following work was performed on
the T2-MK2 target assembly and the T2 Protect
assembly for maintenance purposes and to |
|
|
221
|
Friday, May 05, 2017, 15:09 |
Isaac Earle | Development | Target 2 | Target | T2-MK2 beam spot check in hot cell | On May 5th the T2-MK2 target was
moved to the hot cell for the purpose of
checking the beam spot on the Position 2 |
|
|
227
|
Thursday, July 27, 2017, 09:34 |
Keith C Ng | Development | Other | Other | test 2 | test 2 |
|
|
231
|
Thursday, December 07, 2017, 13:54 |
Isaac Earle | Development | Other | Other | Waste pails transferred from warm cell storage bunker to rad waste pit | Six 5 gallon pails were transferred this
morning from a temporary storage bunker in
the Warm Cell to the Rad Waste Pit for long |
|
|
252
|
Monday, June 24, 2019, 14:29 |
Isaac Earle | Development | Target 1 | Target | T1 and T2 target alignment frames overhauled | The following work was completed on both
the T1 and T2 target alignment frames
One of the short taper |
8x |
|
258
|
Friday, February 28, 2020, 09:06 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 service stand floor plate installed | The M9 service stand floor plate
(TB23351) was installed in the M9 pit yesterday.
Prior to installation all 5 threaded inserts |
|
|
260
|
Wednesday, March 11, 2020, 10:29 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 service stand foot plate installed | The M9 Q1Q2 "foot" plate
(TB23363) has been installed over the floor
plate. A nominal gap between the plates |
|
|
263
|
Tuesday, June 09, 2020, 17:01 |
Isaac Earle | Development | Other | M9 | Cables and helium leak check line installed to M9 service stand | The 10-pin thermal switch wire, 2-pin
steering wire for Q2, and a 1/4" copper
tube for remote helium leak check were installed |
|
|
264
|
Wednesday, June 10, 2020, 08:58 |
Isaac Earle | Development | Other | M9 | T2-M9 and M9-B1 flange scan data | Laser tracker scan data from 2017
and 2019 attached as a backup. Original
files from Beamlines Group who also keep |
|
|
265
|
Friday, June 12, 2020, 13:54 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 water header installed | The Q1Q2 water header (TB23481) was mounted
this morning as per installation drawing
TB23400. |
|
|
266
|
Tuesday, July 07, 2020, 13:22 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 | The M9 Q1Q2 magnet assembly lift
beam has been installed according to drawing
TB23401. The side-to-side as well as |
|
|
267
|
Tuesday, July 07, 2020, 15:13 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 service stand Lemo connector wiring | The diagram below shows the wiring for
the two connectors on the service stand (the
wires running from the stand to the power |
|
|
268
|
Thursday, July 09, 2020, 06:44 |
Isaac Earle | Development | Other | M9 | Alignment of M9 Q1Q2 magnets complete | Mike Vogel reported that alignment
of the Q1Q2 assembly w.r.t. the T2 and B1
flanges was completed on July 7. This |
|
|
272
|
Wednesday, February 17, 2021, 10:39 |
Isaac Earle | Development | Other | UCN | UCN Target Cask Testing | A trial run of remote removal of the UCN
target was performed using the shielded target
cask (TTA0335) developed in 2020. The |
8x |
|
1
|
Wednesday, June 29, 2011, 15:27 |
John Wong | | | | test | blah blah blah.... |
|