Message ID: 31     Entry time: Thursday, April 12, 2012, 15:19
Author: Isaac Earle 
Category: Maintenance 
Type: Target 2 
Specific: Target 
Subject: T2 Target Water Drained 

 In preparation for extended periods of the T2 volume being vented during the M20 repair, the T2 water package was shut-off, the water lines were disconnected from the target, and the cooling water was removed from the target using compressed air.