Message ID: 266     Entry time: Tuesday, July 07, 2020, 13:22
Author: Isaac Earle 
Category: Development 
Type: Other 
Specific: M9 
Subject: M9 Q1Q2 

 The M9 Q1Q2 magnet assembly lift beam has been installed according to drawing TB23401.  The side-to-side as well as beam-axis direction adjustment features were tuned so that the assembly is level when lifted.

 

Aug 5, 2020 update:  All fasteners on the lift beam assembly have been torqued according to the specification on drawing TB23401

 

 