Subject: M9 project post shutdown summary 

 Completed work at m9 beam line:

- Removed existing service stand and associated cable and water services. Legacy b1 water services still need to be removed for future magnet installation. Old service stand is currently in warm cell waiting for disposal.

- M9 Q345 and vacuum roughing line were cleaned by CMMS group.

- M9 B1 is disconnected but remains in beam line ready for removal and refurbishment for 2020 shut down. Relevant ports have been sealed off.

- New Q1 Q2 baseplate was test fit and did not fit with guide post bolted in place, interferes with T2 port blank off plate.

- 3d lidar scans of magnet space were done.

- Leica tracker data was taken of the holes in the poured in place concrete pad.


Photos from shutdown are on remote handling group folder, under "\\trwindata\groups\remote handling\Photos\2019\2019 m9 project"