Message ID: 309     Entry time: Monday, January 16, 2023, 09:54
Author: Adam Newsome 
Category: Standard Operation 
Type: Other 
Specific: Cooling 
Subject: T1 and T2 - Cooling Package Drained 

On Jan. 13, the T1 and T2 cooling package water reservoirs were drained to the BL1A holding tank. Water samples were obtained for each system and provided to RPG for analysis.

Prior to starting draining, the BL1A holding tank water level was approximately 330L. After draining, the water level was approximately 550L (checked Jan. 16).