Entry  Thursday, January 16, 2014, 08:46, maicodallavalle, Trolleys serviced, Maintenance, Pre Cyclotron work servicing and checking 
Entry  Friday, January 17, 2014, 07:53, Travis Cave, Trolleys serviced, Standard Operation, Trolley checks 
Entry  Tuesday, February 17, 2015, 07:10, Dan McDonald, Trolleys serviced, Maintenance, Pre shut down trolley service 
Entry  Friday, February 26, 2021, 08:29, Adam Newsome, Trolleys serviced, Maintenance, First Turn Radial Flag (FTRF) Jig - Pneumatic Upgrade PXL_20210216_202019350.jpg
Entry  Friday, February 26, 2021, 13:00, Adam Newsome, Trolleys serviced, Maintenance, Lower Resonator Trolley - Radial Drive Failure Issue 
Entry  Tuesday, August 31, 2021, 14:28, Adam Newsome, Trolleys serviced, Development, Upper Resonator Trolley - Finger Cylinders Replaced new_fingers.PNG
Entry  Friday, May 31, 2024, 12:47, Riley Sykes, Trolleys serviced, Maintenance, Tool Trolley Scheduled Maintenance Tool_Trolley_Drive_Motor.jpg
Entry  Monday, June 03, 2024, 14:29, Riley Sykes, Trolleys serviced, Maintenance, Upper Resonator Trolley 
Entry  Tuesday, June 04, 2024, 14:29, Riley Sykes, Trolleys serviced, Maintenance, Lower Resonator Trolley 
Entry  Wednesday, June 12, 2024, 10:35, Riley Sykes, Trolleys serviced, Maintenance, Outriggers 1 and 2 Service 
Entry  Tuesday, February 14, 2012, 15:40, Grant Minor, Trolley, Standard Operation, 2C Removal - all 4 QDLs were actuated remotely this year! 2C_probe_Feb_14_2012_labelled.JPG2C_probe_solenoid_5_Feb_14_2012_labelled.JPG
Entry  Friday, February 17, 2012, 15:07, Don Jackson, Trolley, Repair, Video Trolley Failed in Cyclotron Tank Stuck_Video_Trolley_Feb_17_2012_005.jpgStuck_Video_Trolley_Feb_17_2012_001.jpg
Entry  Tuesday, July 28, 2015, 11:47, Dan McDonald, Trolley, Maintenance, Camera trolley service 
Entry  Thursday, June 30, 2016, 13:47, Dan McDonald, Trolley, Maintenance, Lift trolley 
Entry  Friday, February 02, 2018, 14:14, Don Jackson, Trolley, Repair, Overcurrent on radial drive motor 
Entry  Monday, February 19, 2018, 12:58, maicodallavalle, Trolley, Repair, Lift Trolley Repair 
Entry  Wednesday, September 04, 2019, 15:29, Adam Newsome, Trolley, Maintenance, Connector faceplate and tubing upgrade 
Entry  Wednesday, February 05, 2020, 15:04, Adam Newsome, Trolley, Repair, Upper resonator trolley: cylinders for Ex 2C tasks 
Entry  Saturday, April 04, 2020, 10:03, Dan McDonald, Trolley, Development, Addition of DC motor controller mounts 
Entry  Monday, March 21, 2022, 13:14, Adam Newsome, Trolley, Repair, Video Trolley Mk 1 - Radial Limit Switch Replacement 
Entry  Wednesday, May 04, 2022, 12:07, Adam Newsome, Trolley, Development, Tool Trolley: Brass air fittings replacement complete 
Entry  Thursday, August 03, 2023, 10:43, Adam Newsome, Trolley, Development, Previous generation video trolley decommissioned 
Entry  Thursday, September 14, 2023, 13:51, Adam Newsome, Trolley, Maintenance, Lift Trolley: upgrades to camera tilt mechanism PXL_20230914_193143524.jpg
Entry  Friday, September 15, 2023, 10:15, Adam Newsome, Trolley, Maintenance, Lift Trolley: mirror actuation mechanism repair/upgrade PXL_20230915_164811247.jpg
Entry  Friday, February 16, 2024, 11:11, Adam Newsome, Trolley, Repair, Lift Trolley: vertical motion failure, motor relays replaced 
Entry  Monday, January 27, 2014, 14:42, Travis Cave, Shielding, Standard Operation, shields and radiation survey  Meeting_Orbital_Counter_Problem_Jan_2014.pdf
Entry  Tuesday, January 28, 2014, 14:59, Travis Cave, Shielding, Standard Operation, shields  
Entry  Tuesday, February 25, 2014, 15:00, Travis Cave, Shielding, Standard Operation, shields 
Entry  Wednesday, February 26, 2014, 14:55, Travis Cave, Shielding, Standard Operation, shields 
Entry  Tuesday, April 08, 2014, 10:45, Travis Cave, Shielding, Standard Operation, Large shield door on the RH B2 level 
Entry  Thursday, March 19, 2015, 13:14, maicodallavalle, Shielding, Standard Operation, Remote Handling B2 level Shielding door 
Entry  Friday, February 05, 2016, 14:55, Travis Cave, Shielding, Standard Operation, shadow shields 
Entry  Tuesday, March 07, 2017, 09:31, Jason Kapalka, Shielding, Standard Operation, Blockers/Shields/Covers/Ladders Checklist_for_Cyclotron_Shields_and_Blocks_and_Porthole_Covers_(Rev4_As_Run_2017).pdf
Entry  Wednesday, January 13, 2021, 11:35, Adam Newsome, Shielding, Maintenance, Shadow Shields Inspection - 2021 Shutdown 
Entry  Wednesday, January 19, 2022, 09:50, Travis Cave, Shielding, Standard Operation, Shield door is now open 
Entry  Tuesday, February 07, 2012, 18:09, Grant Minor, Service Bridge, Repair, Service Bridge Center Post Bearing Maintenance and Orbit Counter (2011/2012) Stripped_Orbit_Limit_Belt_Sept_23_2011.JPGBridge_Belt_Repair_Fall_2011.JPGOrbit_Counter_Wheel_Just_Before_Skip_Point.JPGD7900_detail_Feb_7_2012.JPGCyclotron_Orbit_Counter_Wheel_emails_Mar-Sep_2011.pdf
Entry  Thursday, October 25, 2012, 13:58, maicodallavalle, Service Bridge, Maintenance, Orbit Drive 
Entry  Monday, February 04, 2013, 13:52, Grant Minor, Service Bridge, Repair, Hydraulic cylinder failure on service bridge 6x
Entry  Wednesday, February 13, 2013, 08:55, maicodallavalle, Service Bridge, Repair, Service Bridge/Carrier Hydraulic Jacks Hydraulic_Jack_RC-254.pdf
Entry  Monday, September 30, 2013, 14:02, Travis Cave, Service Bridge, Maintenance, new festooning 
Entry  Monday, April 28, 2014, 10:20, Dan McDonald, Service Bridge, Maintenance, Bridge orbit reduction box 
Entry  Friday, February 05, 2016, 14:57, Travis Cave, Service Bridge, Maintenance, outrigger problem 
Entry  Thursday, October 31, 2019, 14:31, Adam Newsome, Service Bridge, Repair, Outrigger 2 Vertical Drive Repair 
Entry  Wednesday, June 16, 2021, 09:59, Adam Newsome, Service Bridge, Development, Bridge Lift Mechanism Refurbishment (Phase 1 of 2) - Complete PXL_20210519_210527283_-_Copy.jpgPXL_20210216_175228151_-_cylinder_air_tubing_replaced.jpgPXL_20210615_171909579.jpg
Entry  Thursday, February 02, 2023, 07:05, maicodallavalle, Service Bridge, Repair, Hinged Festoon Rail at Cyclotron  
Entry  Tuesday, March 28, 2023, 12:02, Nadia Jorgenson, Service Bridge, Repair, Outrigger 1 Failure and Repair Outrigger_1_Repair_2023.png
Entry  Thursday, September 07, 2023, 13:21, Jason Zhang, Service Bridge, Development, Outrigger #1 and #2 individual testing complete 
Entry  Wednesday, October 18, 2023, 12:35, Jason Zhang, Service Bridge, Development, O503 Bridge and Outrigger integration testing 
Entry  Tuesday, November 14, 2023, 12:13, Nadia Jorgenson, Service Bridge, Repair, First Festooning Car "H" channel replacement  Festooning_car_H_channel_deformation.pngFestooning_car_H_channel_bottom_face.png
Entry  Tuesday, November 14, 2023, 12:38, Nadia Jorgenson, Service Bridge, Maintenance, Bridge Orbit Counter Work in 2023 
Entry  Thursday, May 16, 2024, 12:33, Riley Sykes, Service Bridge, Maintenance, Center Post Bearing 
Entry  Friday, May 31, 2024, 11:28, Riley Sykes, Service Bridge, Maintenance, Outrigger mechanical inspection 
Entry  Friday, June 14, 2024, 10:04, Riley Sykes, Service Bridge, Maintenance, Service/ Bridge inspection 
Entry  Wednesday, October 16, 2024, 11:37, Adam Newsome, Service Bridge, Development, Bridge Lift Mechanism Refurbishment (Phase 2 of 2) - Complete  6x
Entry  Tuesday, March 14, 2017, 17:07, Jason Kapalka, Probe, Maintenance, LE probe removal simulation exercise 
Entry  Wednesday, June 29, 2022, 12:12, Adam Newsome, Probe, Development, LE1/LE2 Probe Frame - Updates PXL_20220629_175832571.jpg
Entry  Thursday, November 05, 2020, 15:38, Adam Newsome, Infrastructure, Development, New crane pendant: B1 level crane 
Entry  Monday, November 09, 2020, 09:17, Adam Newsome, Infrastructure, Development, New crane pendant: B2 level crane 
Entry  Wednesday, May 05, 2021, 12:20, Adam Newsome, Infrastructure, Development, Cyclotron RH Control Room: Outlets Installed 
Entry  Friday, January 27, 2023, 12:12, Adam Newsome, Infrastructure, Development, Vault crane - inspection, remote pendant installation 
Entry  Wednesday, July 17, 2024, 15:02, Adam Newsome, Infrastructure, Standard Operation, Safety Walkaround Complete - RH Shop, Back Shop, B1, and B2 levels 
Entry  Thursday, October 10, 2024, 12:30, Adam Newsome, Infrastructure, Standard Operation, Safety Walkaround Complete - RH Shop, Back Shop, B1, and B2 levels 
Entry  Friday, January 03, 2025, 10:20, Adam Newsome, Infrastructure, Standard Operation, Safety Walkaround Complete - RH Building B1 and B2 Level 
Entry  Monday, January 06, 2025, 13:57, Adam Newsome, Infrastructure, Standard Operation, Safety Walkaround Complete - RH Building Shop and Back Shop 
Entry  Monday, June 27, 2011, 10:38, John Wong, General, Routine, Testing RH elog 
Entry  Tuesday, September 25, 2012, 08:57, maicodallavalle, Elevation Jack, Maintenance, 2012 Service Maintance of #4 Station Jacking System  
Entry  Tuesday, January 29, 2013, 18:49, Grant Minor, Elevation Jack, Standard Operation, Lid-up complete - summary notes Jacks_Station_6_and_4_Procedure_Jan_12_2012_122.jpg
Entry  Wednesday, January 30, 2013, 14:44, Grant Minor, Elevation Jack, Standard Operation, Further lid-up notes from Dan Louie Dan_Louie_Lid-Up_e-mail_30Jan2013.pdf
Entry  Wednesday, February 06, 2013, 17:42, Grant Minor, Elevation Jack, Maintenance, In-situ jack power screw lubrication inspection - Stations 9, 10, 11, and 6 16x
Entry  Wednesday, February 06, 2013, 17:50, Grant Minor, Elevation Jack, Maintenance, Service records compiled by G. Minor Cyclotron_Elevation_Maintenance_Rotation_Record_17Dec2012.pdf
Entry  Wednesday, February 06, 2013, 18:07, Grant Minor, Elevation Jack, Maintenance, Lid-down yoke gap measurements from 1994 Elevation_Yoke_Measurements_1994.pdf
Entry  Tuesday, March 19, 2013, 19:17, Grant Minor, Elevation Jack, Standard Operation, Re-indexing of all jack station "zero" yoke elevations Jacks_Station_6_and_4_Procedure_Jan_12_2012_122.jpg
Entry  Thursday, April 11, 2013, 19:00, Grant Minor, Elevation Jack, Maintenance, Upper Bearing at Jack Station 9 + Fall Protection Upgrades station_9_ceiling_anchors_SRLs_10april2013-002.JPGstation_9_ceiling_anchors_SRLs_10april2013-003.JPGstation_9_ceiling_anchors_SRLs_10april2013-004.JPGstation_9_ceiling_anchors_SRLs_10april2013-006.JPG
Entry  Monday, January 20, 2014, 12:00, Grant Minor, Elevation Jack, Standard Operation, Indexing Check of Cyclotron Jack Stations 
Entry  Thursday, January 23, 2014, 18:47, Grant Minor, Elevation Jack, Standard Operation, Cyclotron Lid-Up Report - 22 Jan 2014 6x
Entry  Monday, March 03, 2014, 15:07, Grant Minor, Elevation Jack, Standard Operation, Cyclotron Lid-Down Report Monday 3-March-2014 
Entry  Wednesday, July 02, 2014, 16:46, Grant Minor, Elevation Jack, Standard Operation, Cyclotron Lid-Up Report for 27 June 2014 
Entry  Friday, July 04, 2014, 07:21, Dan McDonald, Elevation Jack, Standard Operation, Cyclotron lid down July-2- 2014 
Entry  Tuesday, January 13, 2015, 16:46, Grant Minor, Elevation Jack, Development, Upper Bearing Fall Protect Guardrails TRH1217 Installed on Stns 8,10, 3, 4 & 5 9x
Entry  Friday, January 23, 2015, 10:27, maicodallavalle, Elevation Jack, Maintenance, 2015 Jack Maintenance - Stations #4 and Station #9 
Entry  Monday, January 26, 2015, 07:57, maicodallavalle, Elevation Jack, Maintenance, Fall arrest Platform Railing 
Entry  Tuesday, January 27, 2015, 11:39, Grant Minor, Elevation Jack, Standard Operation, Lid-Up Report 26 Jan 2015 Station_8_Interference_Measurment_26Jan2015.JPGStation_8_Lid_Up_without_platform_26Jan2015.JPG
Entry  Friday, March 06, 2015, 16:42, Grant Minor, Elevation Jack, Standard Operation, Lid-Down Report 6-March-2015 Electrical_Cover_Knocked_Off_6March2015.JPG
Entry  Monday, March 09, 2015, 11:55, chad fisher, Elevation Jack, Maintenance, Checking for contamination on fall arrest equip. 
Entry  Tuesday, March 10, 2015, 10:24, chad fisher, Elevation Jack, Maintenance, Contaminated equipment update 
Entry  Thursday, March 26, 2015, 15:48, Grant Minor, Elevation Jack, Standard Operation, Cyclotron Lid-Up 26 March 2015 
Entry  Thursday, April 16, 2015, 15:26, Grant Minor, Elevation Jack, Maintenance, Cyclotron Elevating System Maintenance Rotation Record - Updated 16 Apr 2015 Cyclotron_Elevating_System_Maintenance_Rotation_Record_16Apr2015.pdf
Entry  Thursday, September 17, 2015, 18:38, Grant Minor, Elevation Jack, Maintenance, Station 9 Jack Worm Gear Inspection - unusual wear markings 16Sept2015 8x
Entry  Wednesday, September 30, 2015, 11:26, Isaac Earle, Elevation Jack, Standard Operation, Station 9 Jack Right Side - Unusual Wear Investigation 7x
Entry  Wednesday, September 30, 2015, 11:52, Isaac Earle, Elevation Jack, Standard Operation, Station 9 Jack Left Side - Inspection & Service Status 15x
Entry  Tuesday, October 27, 2015, 07:50, maicodallavalle, Elevation Jack, Standard Operation, Service to Station # 9 Right side 9x
Entry  Tuesday, January 19, 2016, 17:59, Grant Minor, Elevation Jack, Development, Upper Bearing Fall Protection Installation - Stations 1, 2, 6, 7, 8, 11, & 12 22x
Entry  Wednesday, January 27, 2016, 10:51, maicodallavalle, Elevation Jack, Maintenance, 2016 Cyclotron Elevation System Maintenance  
Entry  Wednesday, September 14, 2016, 11:30, Dan McDonald, Elevation Jack, Maintenance, Jack station 10B 14x
Entry  Monday, February 06, 2017, 20:32, Jason Kapalka, Elevation Jack, Maintenance, 2017 Cyclotron Elevating System Maintenance  Cyclotron_Elevation_Maintenance_Rotation_Record_20170829.xlsx
Entry  Friday, February 23, 2018, 15:44, Jason Kapalka, Elevation Jack, Repair, Replacement of Elevating System wiring 
Entry  Tuesday, January 22, 2019, 07:18, Dan McDonald, Elevation Jack, Maintenance, Station 11-12 jack swap and hoist plate instal 
Entry  Sunday, April 05, 2020, 13:24, Dan McDonald, Elevation Jack, Maintenance, Elevating system station swap 2019-2020 
Entry  Thursday, October 06, 2022, 17:15, Adam Newsome, Elevation Jack, Maintenance, Preventative Maintenance: MCC-E elevating system motor contactors Elevating_System_Motor_Contactors_2022-10-06.png
Entry  Friday, February 03, 2023, 08:27, Eric Lahe, Elevation Jack, Maintenance, Elevating System Jack Inspection  Elevation_System_Checklist_-_Jan312023.xlsx
Entry  Tuesday, January 23, 2024, 14:03, Adam Newsome, Elevation Jack, Maintenance, Inspection of elevating system motor contacts Elev_Motor_1.jpgElev_Motor_2.jpg
Entry  Wednesday, January 31, 2024, 11:39, Adam Newsome, Elevation Jack, Maintenance, Jack station 11: synchro replaced 
Entry  Wednesday, January 31, 2024, 15:06, Eric Lahe, Elevation Jack, Maintenance, Elevating System - Annual Station Swap 2023-2024 
Entry  Wednesday, February 07, 2024, 12:04, Adam Newsome, Elevation Jack, Repair, Elevating system - brake master relay fuse issue 
Entry  Thursday, February 08, 2024, 08:50, Adam Newsome, Elevation Jack, Maintenance, Elevating system - station 10 motor contactor issue 
Entry  Friday, February 09, 2024, 15:43, Adam Newsome, Elevation Jack, Standard Operation, Lid up operation - 2024 Elevation_System_Checklist_-_February_2024.xlsxElevation_System_Thermal_Imaging_Report_-_Lid_Up_Feb_2024.pdf
Entry  Wednesday, April 24, 2024, 14:26, Adam Newsome, Elevation Jack, Standard Operation, Lid up operation (second) - 2024 Elevation_System_Checklist_-_2024_-_Second_Lid_Up.pdf
Entry  Thursday, May 02, 2024, 12:42, Adam Newsome, Elevation Jack, Standard Operation, Lid up operation (third) - 2024 Elevation_System_Checklist_-_2024_-_May.pdf
Entry  Tuesday, May 07, 2024, 09:35, Adam Newsome, Elevation Jack, Standard Operation, Lid down operation (third) - 2024  Motor_Contactor_6_-_2024.PNGElevation_System_Checklist_-_2024_Lid_down_-_third.pdf
Entry  Monday, June 24, 2024, 12:53, Riley Sykes, Elevation Jack, Maintenance, Highfield Service 
Entry  Wednesday, July 24, 2024, 14:26, Riley Sykes, Elevation Jack, Maintenance, Service inspection and relubrication 
Entry  Wednesday, August 07, 2024, 14:24, Riley Sykes, Elevation Jack, Maintenance, Service inspection and relubrication 
Entry  Wednesday, February 27, 2013, 12:08, Travis Cave, Cyclotron, Standard Operation, Installation of 2C 
Entry  Tuesday, March 05, 2013, 14:11, Travis Cave, Cyclotron, Standard Operation, Setup and the Installation of the HE 1 probe. 
Entry  Friday, March 08, 2013, 18:42, Grant Minor, Cyclotron, Repair, Tank lid not at upper limit and resulting effects Contact_btwn_cable_tray_and_upper_equip_8Mar2013.PNGJack_upper_limit_switch_not_engaged_8Mar2013.pngJack_upper_limit_switch_engaged_8Mar2013.pngCyclotron_height_stick_half_inch_from_roof_8Mar2013.JPGCyclotron_height_stick_final_position_8Mar2013.jpg
Entry  Monday, March 11, 2013, 19:43, Grant Minor, Cyclotron, Repair, Adjustment of tank lid upper limit by 1/4" upwards cyclotron_upper_limit_station_10_before_adjustment_11Mar2013_002.jpgcyclotron_upper_limit_station_10_after_adjustment_11Mar2013_004.jpgcyclotron_upper_limit_station_1_before_adjustment_11Mar2013_005.jpgcyclotron_upper_limit_station_1_after_adjustment_11Mar2013_006.jpgcyclotron_upper_limit_lamp_on_11Mar2013_008.jpg
Entry  Thursday, March 14, 2013, 19:57, Grant Minor, Cyclotron, Repair, Tank lid upper / over travel limit check cyclotron_over_travel_limit_check_Station10_14Mar2013_003.JPGcyclotron_over_travel_limit_check_Station1_14Mar2013_001.jpg
Entry  Friday, March 15, 2013, 08:39, Don Jackson, Cyclotron, Standard Operation, Pre Lid Down In Tank Video Survey Pre_Lid_Down_Survey_2013.pdf
Entry  Friday, March 15, 2013, 15:18, Grant Minor, Cyclotron, Standard Operation, Lid Down Successful - Mechanical Counter Readings 
Entry  Monday, March 18, 2013, 15:12, Isaac Earle, Cyclotron, Maintenance, Cyclotron Magnet Face Gap Measurements 8x
Entry  Friday, January 24, 2014, 14:10, Travis Cave, Cyclotron, Standard Operation, Copper blockers 
Entry  Wednesday, January 29, 2014, 15:08, Bevan Moss, Cyclotron, Standard Operation, Shielding and Port Hole Covers 
Entry  Thursday, January 30, 2014, 13:47, Travis Cave, Cyclotron, Standard Operation, shields 
Entry  Friday, January 31, 2014, 10:07, Travis Cave, Cyclotron, Standard Operation, 2C removal 
Entry  Friday, February 07, 2014, 10:50, Travis Cave, Cyclotron, Standard Operation, 2C install 
Entry  Friday, February 21, 2014, 11:05, Bevan Moss, Cyclotron, Standard Operation, Old Monitor Box Removed, New installed 7x
    Reply  Friday, February 21, 2014, 15:58, Bevan Moss, Cyclotron, Standard Operation, Old Monitor Box Removed, New installed 
Entry  Monday, March 03, 2014, 13:09, Travis Cave, Cyclotron, Standard Operation, shields 
Entry  Tuesday, January 27, 2015, 14:40, Travis Cave, Cyclotron, Standard Operation, Day one of in tank work 
Entry  Wednesday, January 28, 2015, 14:33, Travis Cave, Cyclotron, Standard Operation, Day two of in tank work 
Entry  Thursday, January 29, 2015, 14:53, Travis Cave, Cyclotron, Standard Operation, Day three of in tank work 
Entry  Friday, January 30, 2015, 15:02, Travis Cave, Cyclotron, Standard Operation, Day four of in tank work 
Entry  Monday, February 02, 2015, 14:28, Travis Cave, Cyclotron, Standard Operation, Day five of in tank work 
Entry  Wednesday, February 04, 2015, 13:57, Travis Cave, Cyclotron, Standard Operation, 2C removal 
Entry  Tuesday, February 17, 2015, 11:28, Travis Cave, Cyclotron, Standard Operation, 2C Installation 
Entry  Friday, March 06, 2015, 14:38, Travis Cave, Cyclotron, Standard Operation, Shield Removal 
Entry  Tuesday, March 17, 2015, 13:04, maicodallavalle, Cyclotron, Maintenance, Upper Bearings Station #5 and #10 
Entry  Friday, March 27, 2015, 07:31, Dan McDonald, Cyclotron, Repair, Lid up operations 
Entry  Friday, March 27, 2015, 11:25, Travis Cave, Cyclotron, Standard Operation, Copper Blockers 
Entry  Thursday, April 02, 2015, 12:09, Dan McDonald, Cyclotron, Standard Operation, Lid Down operations April, 2, 2015 
Entry  Tuesday, January 05, 2016, 09:58, Travis Cave, Cyclotron, Standard Operation, Opened the shield door 
Entry  Wednesday, February 03, 2016, 08:16, Dan McDonald, Cyclotron, Standard Operation, Cyclotron lid up  lid_up_2016.pdf
Entry  Tuesday, February 09, 2016, 14:48, Travis Cave, Cyclotron, Standard Operation, shadow shields 
Entry  Wednesday, February 10, 2016, 14:53, Travis Cave, Cyclotron, Standard Operation, shadow shields 
Entry  Tuesday, February 16, 2016, 16:32, Isaac Earle, Cyclotron, Standard Operation, HE1 Probe Removed from Cyclotron 
Entry  Friday, February 19, 2016, 10:17, Isaac Earle, Cyclotron, Standard Operation, HE1 Probe Installed in Cyclotron 
Entry  Thursday, February 25, 2016, 11:41, Travis Cave, Cyclotron, Standard Operation, Ex 2C removal 
Entry  Tuesday, March 01, 2016, 13:27, Travis Cave, Cyclotron, Standard Operation, Ex 2C install 
Entry  Wednesday, March 09, 2016, 17:09, Ron Kuramoto, Cyclotron, Development, EX4N new housing installation dspage07994143927104268192.pdfExtr_4N_Final_instalation_-_gimbal-pipe-valve.docxIMG_1886.JPG
Entry  Tuesday, March 15, 2016, 13:56, Dan McDonald, Cyclotron, Standard Operation, Lid Down 2016 
Entry  Thursday, April 07, 2016, 11:04, Travis Cave, Cyclotron, Standard Operation, Closed the shield door 
Entry  Tuesday, January 31, 2017, 14:41, Travis Cave, Cyclotron, Standard Operation, Shield installation 
Entry  Thursday, February 09, 2017, 15:21, Isaac Earle, Cyclotron, Standard Operation, HE2 Probe Removed 
Entry  Tuesday, February 21, 2017, 13:40, Isaac Earle, Cyclotron, Standard Operation, HE2 Probe Returned to Cyclotron 
Entry  Tuesday, February 28, 2017, 15:45, Jason Kapalka, Cyclotron, Standard Operation, 2C extraction probe removal and reinstallation 
Entry  Friday, March 03, 2017, 13:30, Jason Kapalka, Cyclotron, Standard Operation, CP continuity test 
Entry  Tuesday, March 14, 2017, 11:23, Jason Kapalka, Cyclotron, Standard Operation, Start/end of shutdown photo and video survey Cyclotron_Video_Inspecting_Guidelines_(RevX_20170314).xlsx
Entry  Tuesday, March 14, 2017, 12:02, Jason Kapalka, Cyclotron, Standard Operation, Radiation survey Procedure_for_Cyclotron_Tank_Radiation_Survey_by_Don_Jackson_(20000106_Obsolete).doctankworkssubplot.m2017_01_30_shields_out_tank_superimposed.png2017_02_02_shields_in.png
Entry  Tuesday, March 14, 2017, 17:28, Jason Kapalka, Cyclotron, Maintenance, Lower resonator removal simulation exercice 
Entry  Tuesday, March 14, 2017, 17:57, Jason Kapalka, Cyclotron, Standard Operation, Lid raising and lowering operations 
Entry  Monday, January 08, 2018, 09:04, Maico Dalla Valle / Jason Kapalka, Cyclotron, Standard Operation, Cyclotron Lid Up Cyclotron_Elevation_Maintenance_Rotation_Record_20180223.xlsx
Entry  Tuesday, January 09, 2018, 15:54, Jason Kapalka, Cyclotron, Standard Operation, Lid-up sequence (in-tank work) 
Entry  Tuesday, January 16, 2018, 13:43, Travis Cave, Cyclotron, Standard Operation, Cyclotron in tank work 
Entry  Thursday, January 25, 2018, 17:16, Isaac Earle, Cyclotron, Standard Operation, HE1 probe removed 
Entry  Wednesday, January 31, 2018, 11:20, Isaac Earle, Cyclotron, Standard Operation, HE1 probe reinstalled 
Entry  Tuesday, April 03, 2018, 11:57, Travis Cave, Cyclotron, Standard Operation, Blue Shield Door Shut. 
Entry  Thursday, January 30, 2020, 06:55, Dan McDonald, Cyclotron, Standard Operation, Lid up operations lid_up_2020.xlsx
Entry  Monday, February 03, 2020, 11:06, Adam Newsome, Cyclotron, Development, Porthole Cover Handling Tool - Initial Test Report IMG_20200128_114901.jpg
Entry  Wednesday, February 05, 2020, 12:37, Adam Newsome, Cyclotron, Development, Cyclotron Vacuum Cleaning Tool - Initial Test IMG_20200205_093927.jpg
Entry  Wednesday, February 05, 2020, 12:44, Adam Newsome, Cyclotron, Development, Cyclotron Small Object Retrival Tool - Intial Test IMG_20200205_112703.jpg
Entry  Saturday, April 04, 2020, 09:47, Dan McDonald, Cyclotron, Standard Operation, Lid down operations lid_down_2020.xlsx
Entry  Thursday, July 16, 2020, 11:57, Adam Newsome, Cyclotron, Development, Cyclotron Mockup: Orbital Position Pendant Upgrade Before.jpgAfter.jpg
Entry  Friday, January 22, 2021, 14:30, Adam Newsome, Cyclotron, Standard Operation, Lid up operation - 2021 
Entry  Wednesday, February 03, 2021, 12:37, Adam Newsome, Cyclotron, Development, Ladder Handling Tool - First In-Tank Test (SAS0824) Capture.PNGCapture5.PNGCapture14.PNG
Entry  Thursday, April 01, 2021, 13:47, Adam Newsome, Cyclotron, Standard Operation, Vault Shield Door Closed 
Entry  Friday, February 04, 2022, 11:52, Adam Newsome, Cyclotron, Standard Operation, Lid up operation - 2022 
Entry  Tuesday, February 08, 2022, 11:39, Adam Newsome, Cyclotron, Development, Radiation Survey - sampling rate error 
Entry  Wednesday, April 27, 2022, 16:05, Adam Newsome, Cyclotron, Standard Operation, Lid down operation - 2022 
Entry  Tuesday, May 10, 2022, 11:26, Nadia Jorgenson, Cyclotron, Repair, Festooning rail rope and pulley system re-routed 
Entry  Tuesday, May 10, 2022, 11:30, Nadia Jorgenson, Cyclotron, Repair, Cracked Festooning Rail Bushing Removed Festooning_Bushing_Cracked.jpg
Entry  Tuesday, May 10, 2022, 11:31, Nadia Jorgenson, Cyclotron, Standard Operation, Vault Shield Door Closed 
Entry  Monday, January 30, 2023, 12:20, Adam Newsome, Cyclotron, Standard Operation, Lid up operation - 2023  2023_Synchro_Counts.xlsx2023_Jacks_Infrared_Data.xlsx
Entry  Friday, March 31, 2023, 13:22, Adam Newsome, Cyclotron, Standard Operation, Lid down operation - 2023 Elevation_System_Checklist_-_March_31_2023.pdf
Entry  Wednesday, April 26, 2023, 11:19, Adam Newsome, Cyclotron, Standard Operation, Vault Shield Door Closed 
Entry  Friday, July 28, 2023, 12:05, Adam Newsome, Cyclotron, Development, Maintenance ladders: end caps added PXL_20230728_184520962.jpg
Entry  Monday, February 26, 2024, 11:52, Adam Newsome, Cyclotron, Repair, Controls issue - CAMAC power supply 
Entry  Friday, April 19, 2024, 15:18, Adam Newsome, Cyclotron, Standard Operation, Lid down operation - 2024 Elevation_System_Checklist_-_2024.xlsx
Entry  Tuesday, April 30, 2024, 15:00, Adam Newsome, Cyclotron, Standard Operation, Lid down operation (second) - 2024  Elevation_System_Checklist_-_2024_-_Second_Lid_Down.pdf
Entry  Wednesday, July 24, 2024, 11:39, Adam Newsome, Cyclotron, Standard Operation, Investigation of faulty Al-ALCW signal 
Entry  Tuesday, April 20, 2021, 15:02, Adam Newsome, Carrier, Development, Emergency Trolley Rescue Winch: Installed and Tested PXL_20210420_185918486.MP.jpgPXL_20210420_190619179.jpg
Entry  Tuesday, May 14, 2024, 10:53, Riley Sykes, Carrier, Maintenance, Carrier underrail wheels maintenance 
Entry  Friday, May 31, 2024, 08:57, Riley Sykes, Carrier, Maintenance, Carrier Drive motor/gear reducer 
Entry  Tuesday, July 23, 2024, 13:27, Riley Sykes, Carrier, Maintenance, Service/Maintenance checks 