A safety walkaround was completed for the RH building shop and back shop.

The resulting spreadsheet can be found on DocuShare as Document-242733.

Main deficiencies identified:

  • Main shop, ground level:
    • Lighting still needs to be replaced (this was previously requested of electrical services and they are aware of it)
    • Unpainted lead bricks still need to be picked up (this was previously requested of mechanical services and they are aware of it)
    • Rad waste needs to be picked up (will do soon)