  RH-Cyclotron  Not logged in ELOG logo
Message ID: 44     Entry time: Wednesday, July 02, 2014, 16:46
Author: Grant Minor 
Category: Elevation Jack 
Type: Standard Operation 
Subject: Cyclotron Lid-Up Report for 27 June 2014 

The cyclotron lid was raised on June 27th, 2014.  Start time was 1:05pm end time was 2:17pm (good!) Dan McDonald collected and recorded numbers from the mechanical counters for the lid up sequence, I am entering the data into the e-Log on his behalf.

Below are the mechanical counter values from the start and finish of the lid-up job:

Mech. Counter Values
Jack Start Finish
1 32 47366
2 33 47399
3 28 47354
4 32 47398
5 32 47372
6 32 47395
7 33 47372
8 30 47390
9 33 47390
10 35 47397
11 34 47370
12 32 47396

There were 5 local jogs made to the jacks during the lid up process: 

Jog #1
Station Before Jog After Jog
8 1403 -
9 1387 1407
10 1408 -

 

Jog #2
Station Before Jog After Jog
2 - -
3 2769 2808
4 2808 -
8 - -
9 2766 2799
10 2798 -

 

Jog #3
Station Before Jog After Jog
8 6766 -
9 6759 6772
10 6772 -

 

Jog #4
Station Before Jog After Jog
8 22771 -
9 22764 22770
10 22770 -

 

Jog #5
Station Before Jog After Jog
8 - -
9 46764 46800
10 46800 -

 