Message ID: 190     Entry time: Thursday, October 10, 2024, 12:30
Author: Adam Newsome 
Category: Infrastructure 
Type: Standard Operation 
Subject: Safety Walkaround Complete - RH Shop, Back Shop, B1, and B2 levels 

A safety walkaround was completed for the RH Shop, Back Shop, B1, and B2 levels.

The resulting spreadsheet can be found on DocuShare as Document-242733.

Main deficiencies identified:

  • Main Shop:
    • Lifting equipment has overdue inspection
    • Light bulbs burnt out
    • Unpainted lead has not been removed
  • B1:
    • Crane has overdue inspection
    • Lifting equipment has overdue inspection
  • B2:
    • Crane has overdue inspection
    • Lifting equipment has overdue inspection

Action has been taken on all deficiencies.

 