Message ID: 98     Entry time: Tuesday, March 14, 2017, 11:23
Author: Jason Kapalka 
Category: Cyclotron 
Type: Standard Operation 
Subject: Start/end of shutdown photo and video survey 
The start of shutdown photo and video survey was performed in the Cyclotron tank by the RH group using the 
service bridge and video trolley on 2017-01-27 (see attached pictures).
 
The end of shutdown photo and video survey was performed in the Cyclotron tank by the RH, Probes, and 
Operations group using the service bridge and video trolley on 2017-03-08 and observed the following:
- Observed a small piece of melted plastic and wire near the 180° lower tank D-gap; this item has been present 
since the 2016 shutdown based on photographic evidence (see attached picture).
- Observed a large strip of paper on Q2L2, close to where the ladders were placed beside the CP (see attached 
picture). 
- Observed a bent periscope alignment target near Q4U7 (see attached picture).

A proposed guideline for conducting future video surveys is attached (via djacks@triumf.ca and genge@triumf.ca).
Attachment 1: Cyclotron_Video_Inspecting_Guidelines_(RevX_20170314).xlsx  14 kB