Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-Cyclotron  Not logged in ELOG logo
Message ID: 45     Entry time: Friday, July 04, 2014, 07:21
Author: Dan McDonald 
Category: Elevation Jack 
Type: Standard Operation 
Subject: Cyclotron lid down July-2- 2014 

Cyclotron lid down was successfully completed on July 2 2014. Lid went partially down before jack nine had to be jogged to catch up to system. After thirty min of continual system trips Maico Dalla Valle and I Jogged all stations to 42745. Still encountering continual system trips Gord Roy and Dan Louie removed and reset all relays in system, lid proceeded to lower with out problem. Final jack position recording done at 19:45.

 

 

Jack   Start Finish  Jog 1   All jacks reset to 42745 from these positions    
1   47366 44     42755            
2   47399 46     42739   Lid down start 18:32      
3   47354 42     42746   Jack reset at 19:00      
4   47398 46     42738   Finished at 19:45      
5   47372 45     42754            
6   47395 44     42744            
7   47372 46     42751            
8   47390 42     42732            
9   47390 46 42755/42739 42739            
10   47397 48 42741   42741            
11   47370 48     42741            
12   47396 48     42743            
                         
ELOG V2.9.2-2455