RH-Cyclotron |
Not logged in |
|
|
Message ID: 90
Entry time: Wednesday, September 14, 2016, 11:30
|
Author: |
Dan McDonald |
Category: |
Elevation Jack |
Type: |
Maintenance |
Subject: |
Jack station 10B |
|
|
Annual jack maintenance : Jack 10b upon inspection it was found that the output shaft seal on 10b was in need of replacement. In past years RH personal had to remove a LoveJoy coupling which required cutting of the coupler due to galling and possible interference tolerances being out. We sourced sample split seals from Motion Canada that can be installed with out coupling removal we will install and monitor to determine the effectiveness and the possibility of converting all jack stations to this seal design . Attached are pictures of old seal style, new style seal, worm, wheel housing, current coupling on shaft, old coupling that has been cut off and various components. The jack components appear to be in good working order, no extra ordinary maintenance needs to be performed besides seal replacement. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|