Message ID: 13     Entry time: Wednesday, February 13, 2013, 08:55
Author: maicodallavalle 
Category: Service Bridge 
Type: Repair 
Subject: Service Bridge/Carrier Hydraulic Jacks 

On Monday February 4TH  the Service Bridge was being lifted into  the Cyclotron with the Carrier. It was noticed that one of the two Hydraulic Jacks was leaking. All work stopped and the Service Bridge and Carrier were moved to the Remote Handling B2 level for repair. The Service Bridge and Carrier were separated and the Hydraulic Jacks were inspected. It was noticed that both Hydraulic Jacks were leaking. Two overhaul kits were ordered. Two other Hydraulic Jacks were found and replaced. Work continued in the Cyclotron with the Bridge and Carrier. The two  Leaking Hydraulic Jacks were overhauled. Once most of the work in the Cyclotron was done and there was time that the Service Bridge and Carrier were out of the Cyclotron and not in use the two overhauled Hydraulic Jacks  would be replaced. They were tested without the Service Bridge and then with the Service Bridge. There were no leaks and all operation was back to normal.   

Attachment 1: Hydraulic_Jack_RC-254.pdf  192 kB  | Show | Hide all
ELOG V2.9.2-2455