  ID Date Author Target/No.#down Source Station Module Target Oven W.O# Heat Shield W.O# Status Subject Text Attachments
  8   Tuesday, September 20, 2011, 19:00 Aurelia LaxdalTaC#1LP-SISITETM138634-636833-6DoneFinished testing TaC#1Tuesday, September 20, 2011:
Did another mass scan today at 5:40.
Saved as: plotdump-local-clean.txt Sept 20
  
  982   Tuesday, October 10, 2023, 15:46 Aaron SchmidtTa#68 (Spare)LP-SIS  45220-345235-11In progressConditioning Ta#68 (Spare)Tuesday, October 10, 2023, 15:18: Roughing.
Tuesday, October 10, 2023, 15:46:
TP1B on.
 Ta#68-Spare_Conditioning.docx 
  1023   Thursday, October 03, 2024, 16:26 Aaron SchmidtTa#68HP-SISITETM245447-2645235-16 * Conditioning Ta#68HS note:
Base# 45235-16
Lid# 39956-8
  
  1018   Friday, August 09, 2024, 21:08 Ferran Boix PamiesTa#67 Thin foils LP-SISITETM445447-14 45235-10In progressTa#67 thin foil retestingFriday, August 09, 2024, 21:07 Insulators,
retainer and Re foil have been replaced,
source cup machined so the ion source does
 ITE-TM4-Ta#67-LP-SIS_Thin_Foil.docx 
  1015   Monday, July 29, 2024, 23:02 Aurelia LaxdalTa#67 Thin foilsLP-SISITETM345447-1445235-10 Cooldown for removing the V wires  22:55 Cooldown completed to remove
the voltage wires from inside the vacuum
box. 
  
  1014   Thursday, July 25, 2024, 14:26 Dave NeilsonTa#67 Thin foil LP-SISITETM345447-1445235-10 Conditioning Ta#67 Thin foilThursday, July 25, 2024, 14:25  -
competing electrical checks prior to test
stand installation
  
  980   Monday, September 25, 2023, 16:31 Aaron SchmidtTa#66LP-SISITWTM245220-545235-9DoneConditioning Ta#66 & HV Tests.Thermocouples installed on the left end
plate x 2.
Monday, September 25, 2023, 16:23:
 Ta#66_HV_Test_1.docxTa#66_HV_test_2.docxTa#66_Conditioning.docx 
  967   Tuesday, May 16, 2023, 14:00 Aaron SchmidtTa#65LP-SISITETM445220-745235-2In progressConditioning Ta#65Calibrated window installed on the beam
line.
Tuesday, May 16, 2023, 13:45: Roughing
 Ta#65_conditioning_-_Mass_&_wire_scans.docx 
  931   Wednesday, June 08, 2022, 10:01 Aaron SchmidtTa#64LP-SISITETM444691-1244378-13In progressConditioning Ta#64 & HV Test.Thermocouples connected. Test HV
Wednesday, June 08, 2022, 09:33:
Roughing.
 7x 
  906   Friday, November 12, 2021, 13:01 Aaron SchmidtTa#63LP-SISITETM444691-1144378-12In progressConditioning Ta#63Friday, November 12, 2021, 13:01: BV1B
open. Roughing.
Friday, November 12, 2021, 13:05:
 Ta#63.docxER-580-230-30kV-m7.txtER-580-230-30kV-m23.txtER-580-230-30kV-m131.txt 
  876   Monday, June 07, 2021, 13:45 Aaron SchmidtTa#62LP-SISITETM444139-1044378-4In progressTa#62 ConditioningMonday, June 07, 2021, 13:44: Roughing.
Monday, June 07, 2021, 14:16: TP1B
on. (Tripped shortly after?)
 Ta#62_Conditioning_-_1.docx 
  879   Wednesday, June 09, 2021, 14:31 Aaron SchmidtTa#62LP-SISITETM444139-1044378-4In progressInstall MB1 window & 9 pin for V test.Installed a new window on MB1 as per Aurelia.
Connect modified 9 pin connector & voltage
meters for Ta#62 testing.
 Ta#62_voltage_tests.docx 
  880   Monday, June 21, 2021, 11:53 Aaron SchmidtTa#62LP-SISITETM444139-1044378-4FailedTa#62 Conditioning - 2Replace 9-pin back to normal grounded setup.
Re-salt Ta#62. (Cu Gaskets in-use on FS#5)
Monday, June 21, 2021, 11:30: Roughing
 Ta#62_Conditioning_-_2.docx 
  882   Friday, June 25, 2021, 11:18 Aaron SchmidtTa#62LP-SISITETM444691-444378-4DoneTa#62 Conditioning - NewReplacement Ta target for the previous
one (44139-10) https://elog.triumf.ca/TIS/Test-Stand/880
Friday, June 25, 2021, 11:16: Roughing.
 Ta#62_44691-4_Conditioning_-_R.docxTa#62_44691-4_Conditioning..docxITE-TM4-Ta#62-LP-SIS_Test_Stand.docx 
  816   Friday, October 16, 2020, 11:33 Aaron SchmidtTa#61LP-SISITETM444508-143515-1In progressConditioning Ta#61Friday, October 16, 2020, 11:11: Roughing.
Friday, October 16, 2020, 11:39:
TP1B on.
 Ta#61.docxITE-TM4-Ta#61-LP-SIS_Test_Stand.docxER-580-230-30kV-M133.txtER-580-230-30kV-M28.txt 
  785   Thursday, February 20, 2020, 11:41 Aaron SchmidtTa#60LP-SIS  44139-1343515-5In progressTa#60 w/ EE testing Ta#60 (Unconditioned) - Salts in.
Thursday, February 20, 2020, 14:04:
Roughing.
 20200221_134828.jpg20200221_134939.jpgTa#60_-_TS_Pre-condition_-_EE_test_-_1.docx 
  787   Monday, March 02, 2020, 14:42 Aaron SchmidtTa#60LP-SIS  44139-1343515-5In progressFull TS testing w/ HV using Ta#60Monday, March 02, 2020, 14:36: Roughing.
Monday, March 02, 2020, 15:08: Turbo
pumps on.
  
  789   Wednesday, March 11, 2020, 13:31 Aaron SchmidtTa#60LP-SIS  44139-1343515-5In progressTa#60 w/ EE testing - 2Thermocouples installed on EE. Double checked
continuity & used a heat gun.
Wednesday, March 11, 2020, 13:30:
 Ta#60_-_TS_Pre-condition_-_EE_Test_-_2.docx 
  795   Tuesday, June 16, 2020, 11:03 Aaron SchmidtTa#60LP-SISITWTM244139-1343515-5In progressConditioning Ta#60 Tuesday, June 16, 2020, 11:01: Turbo pumps
on.

Wednesday, June 17, 2020,
 Ta#60_Conditioning.docxITW-TM2-Ta#60-LP-SIS_Test_Stand.docxER-580-230-30kV-m8.txtER-580-230-30kV-m40.txt 
  758   Monday, September 23, 2019, 13:30 Aaron SchmidtTa#59LP-SISITETM244062-542752-10In progressConditioning Ta#59 AssyMonday, September 23, 2019, 13:28: Roughing.
Monday, September 23, 2019, 13:38:
Closed BV1A / Opened BV1 A & B to open
 9x 