ID Date Author Category Typedown Subject Text Attachments
  34   Wednesday, February 06, 2013, 16:33 Keith C NgPrimary BeamlinesMaintenancet2 monolith measurementsBeam lines took measurements of top of
T2 using Leica Total Station. Required no
crane activities over 1A blocks.
 20130206_t2alignmeas_IMG_0140.JPG20130206_t2alignmeas_IMG_0139.JPG 
  37   Wednesday, February 13, 2013, 15:49 Keith C NgM9MaintenanceM9 Q1 Q2 removal, preparationLocal and remote leak checks on M9 T2 area
were done today to confirm leak; Leak was
still present at T2 M9 joint. M9 Q1 and Q2
  
  38   Thursday, February 14, 2013, 15:43 Keith C NgM9MaintenanceM9 Q1 Q2 removal, preparationRemoved 8" rubber test rings from
M9 T2 joint. Rings moved to RH warm cell.
Radiation levels were 70 µSv on contact
 20130214_m9q1q2remove_IMG_0179.JPG20130214_m9q1q2remove_IMG_0177.JPG20130214_m9q1q2remove_IMG_0187.JPG20130214_m9q1q2remove_IMG_0181.JPG20130214_m9q1q2remove_IMG_0185.JPG 
  39   Friday, February 15, 2013, 14:29 Keith C NgM9MaintenanceM9 Q1 Q2 removal, preparationBeam lines group purged M9 Q1 Q2 magnets
and water lines in preparation of disconnecting
water services to those magnets, done in
 20130215_m9q1q2remove_P1020780.JPG20130215_m9q1q2remove_P1020778.JPG20130215_m9q1q2remove_P1020781.JPG 
  41   Tuesday, February 19, 2013, 16:46 Keith C NgM9MaintenanceM9 Q1 Q2 removal, preparationDetermined M9 Q2 service stand supply connector
was slowly leaking.
- Ball valve to the supply was leaking
 20130219_m9q1q2remove_IMG_0206.JPG 
  42   Thursday, February 21, 2013, 17:02 Keith C NgM9MaintenanceM9 Q1 Q2 removal, joint dissassemblyCUALCW system water loss was not from 1A
triplet. Q15 Q16 held static  pressure at
90 psi since 9 am until 17:00. Holding with
  
  44   Monday, February 25, 2013, 16:37 Keith C NgM9MaintenanceM9 Q1 Q2 removal, Q2 seal disassemblyRemoved Q2 15" indium seal ring, discovered
seal contained rubber on both sides instead
of indium.
 7x 
  45   Wednesday, February 27, 2013, 16:15 Keith C NgM9MaintenanceM9 Q1 Q2 removal, rad waste pit prepRadioactive waste pit uncovered, red barrel
with unknown contents taken out for assessment.
R. Ralea from RPG determined barrel was too
  
  46   Friday, March 01, 2013, 15:28 Keith C NgM9MaintenanceRadadioactive Waste Pit OrganizingSuccessfully stacked old m20 q2 q2 magnet
assembly on top of old M9 Q1 Q2 magnet and
M11 septum magnet. See photos.
 20130301_radwastepit_P1020865.JPG20130301_radwastepit_P1020869.JPG20130301_radwastepit_P1020873.JPG 
  47   Monday, March 04, 2013, 16:48 Keith C NgM9MaintenanceM9 Q1 Q2 removal, preparationPreparing for M9 Q1,2 move:
1. Re-arranged/organized cables on
top of magnet.
 6x 
  48   Tuesday, March 05, 2013, 14:15 Keith C NgM9MaintenanceM9 Q1, 2 removalRemoved M9 Q1 Q2 from beam line 1A via
crane and transferred from beam line to radiation
waste storage.
 7x 
  50   Tuesday, March 12, 2013, 16:33 Keith C NgM9MaintenanceM9 T2 flange blank off, preparation Scraped M9 T2 flange, removed what little
indium was left on flange.
- Completed two passes, some indium
  
  51   Wednesday, March 13, 2013, 16:21 Keith C NgM9MaintenanceM9 T2 blanking off preparation 1. Re-scraped M9 T2 flange after reviewing
video of flange.
- Some indium remains on inside of
  
  54   Tuesday, April 09, 2013, 16:41 Keith C NgM9MaintenanceT2 M9 exit port blank offBlanked off T2 M9 exit port with indium
seal blank off.
 
 20130409_t2m9blankoff_RHB_5782.JPG20130409_t2m9blankoff_RHB_5783.JPG20130409_t2m9blankoff_RHB_5784.JPG20130409_t2m9blankoff_RHB_5785.JPG 
  59   Wednesday, January 14, 2015, 11:00 Keith C NgPrimary BeamlinesMaintenance1VQ4 & 1VQ6 beamtube removal (WR #2686)Disconnected and removed beam tube from
1VQ4, 5, 6.  
  
  60   Friday, January 23, 2015, 15:21 Keith C NgPrimary BeamlinesMaintenance1VQ4 joint section (WR #2686) 1VQ4 & 1VQ6 beamtube was installed
by UCN group. RH provisonally installed aluminum
indium carrier ring with no indium into joint
 20150123_ucnbuild_IMG_1197.JPG20150123_ucnbuild_IMG_1202.JPG20150123_ucnbuild_IMG_1205.JPG20150123_ucnbuild_IMG_1207.JPG20150123_ucnbuild_IMG_1209.JPG 
  76   Wednesday, April 01, 2015, 16:07 Keith C NgM9MaintenanceT2 M9 area work1) Block and bridge setup is mostly complete
for T2 M9 sighting job. Waiting on approving
drawing TB22322 in order to continue with
  
  85   Friday, January 29, 2016, 17:08 Keith C NgPrimary BeamlinesMaintenance4VVR1 RemovalToday:
Disconnected and removed 4VVR1 gate
valve and removed from beamline.
  
  86   Friday, February 05, 2016, 08:48 Keith C NgPrimary BeamlinesMaintenance4VVR1 RemovalReturned work permit C2016-01-27-2 due
to tank lid being raised and elevated fields
make the work area un-favourable to work
  
  113   Thursday, March 15, 2018, 15:48 Keith C NgM9Maintenancem9 t2 alignment jobBlank off removed this morning, video recorded
the T2 flange,B1 flange and B1 vacuum box
interior. Blank off is 150 uSv/h @ .5m, 3
  