Message ID: 47     Entry time: Monday, March 04, 2013, 16:48
Author: Keith C Ng 
Category: M9 
Type: Maintenance 
Subject: M9 Q1 Q2 removal, preparation 

Preparing for M9 Q1,2 move:

1. Re-arranged/organized cables on top of magnet.

20130304_m9q1q2remove_IMG_0299.JPG20130304_m9q1q2remove_IMG_0300.JPG20130304_m9q1q2remove_IMG_0303.JPG

 

2. Re-configured bagging bunker for walk around access.

 

3. M. Kinakin replaced bullet bolt that was used for assaying.

- Removed new bullet bolt from magnet and decontaminated

 

4. Fully collapsed M9 Q1,2 vacuum box

- Q1 front flange up against T2 flange, appx .25" clearance between Q2 spring eyes and B1 vacuum box.

- Helium line appears to be sticking out under B2

- See above and below photos.

20130304_m9q1q2remove_IMG_0294.JPG

 

5. Disconnected some kind of electrical line from M9 Q2.

- Was secured and pulled off from magnet; see photos below, before & after.

20130304_m9q1q2remove_IMG_0306.JPG20130304_m9q1q2remove_IMG_0309.JPG