Message ID: 113     Entry time: Thursday, March 15, 2018, 15:48
Author: Keith C Ng 
Category: M9 
Type: Maintenance 
Subject: m9 t2 alignment job 

Blank off removed this morning, video recorded the T2 flange,B1 flange and B1 vacuum box interior. Blank off is 150 uSv/h @ .5m, 3 mSv/h on contact at the spring eye ears. Not swiped yet, not tagged. Currently tucked between an 18' shield block and the ME27 block.

Waiting for beam lines to install the target spheres on the target jigs, expecting to install them tomorrow.