99
|
Friday, February 10, 2017, 15:53 |
Keith C Ng | M9 | Development | t2 m9 job | Installed all jigs and Alignment group
did their shoots successfully. Used individual
pins on the 15" target jig and worked |
|
100
|
Tuesday, February 14, 2017, 16:08 |
Keith C Ng | M9 | Development | T2 M9 2015 vs 2017 comparison | Attached a quick comparison of M9 exit
port flanges WRT indium remnants: looks roughly
the same. Will attempt to install blanking |
|
101
|
Wednesday, February 15, 2017, 15:36 |
Keith C Ng | M9 | Development | t2 m9 blank off | Installed the blank off on the T2
M9 exit port: |
|
102
|
Friday, February 17, 2017, 13:33 |
Keith C Ng | M9 | Development | T2 M9 vacuum | Leak checked the blank off at T2 M9 exit
port with Dimo Y. and Edi D.V. (Vac Group)
and they confirm it is leak tight. Blank |
|
103
|
Monday, February 20, 2017, 15:58 |
Keith C Ng | M9 | Development | t2 m9 job wrap up | Restored shielding to T2 M9 void, blocks
seem more crooked compared to previous years. |
|
106
|
Thursday, July 27, 2017, 09:02 |
Keith C Ng | Primary Beamlines | Development | test | test |
|
121
|
Tuesday, June 11, 2019, 14:56 |
Keith C Ng | M9 | Development | M9 B1 seal notes from 1988 | Found original installation notes
for the initial installation of M9 Q1Q2 generation
2 in 1988. |
|
126
|
Thursday, March 19, 2020, 15:42 |
Keith C Ng | Primary Beamlines | Development | Vault beamline beam position monitor | The Beam Position Monitor between 1VB1
and 1VM3 has been installed. The indium joints
are leak tight, however the V flanges are |
|
128
|
Monday, August 10, 2020, 16:08 |
Keith C Ng | M9 | Development | M9 Q1Q2 magnet assembly installed in pit | The M9 Q1Q2 magnet assembly was installed
in the M9 beam line today.
Attached to elog is an inspection |
|