74
|
Thursday, March 05, 2015, 08:42 |
Keith C Ng | Primary Beamlines | Repair | 1AT1 area water leak fixes | 1) Quick connect fittings on the rotary
collimator were leaking (the two red collared
fittings in photo below). |
11x |
75
|
Monday, March 30, 2015, 16:10 |
Keith C Ng | M9 | Repair | T2 area uncovering | Started to uncover and create work space
around T2 M9 area, setup is mostly complete.
Some misc items to be craned into position. |
|
104
|
Wednesday, March 08, 2017, 16:05 |
Keith C Ng | Primary Beamlines | Repair | collimator joint repair | Started uncovering the area above the T2
to Q13 joint:
|
|
105
|
Thursday, March 16, 2017, 15:50 |
Keith C Ng | Primary Beamlines | Repair | collimator b transition to t2 | On Monday found leaking joint was the ring
directly downstream of T2. Vacuum group has
been spraying Vacseal (http://www.vacseal.net/Pages/default.aspx) |
|
107
|
Tuesday, January 23, 2018, 15:44 |
Keith C Ng | Primary Beamlines | Repair | 1AQ15 insulator repair | Assisted beamlines in replacing 2 insulators
on 1A Q15 magnet. #10 and #14 insulators
were found to be leaking at the ceramic, |
|
108
|
Wednesday, January 31, 2018, 15:28 |
Keith C Ng | Primary Beamlines | Repair | Q15 repair | Beamlines has changed out another 2 insulators
on Q15 after discovering two additional leaks.
Insulators #2 & #4 were replaced. One |
|
109
|
Thursday, February 01, 2018, 15:44 |
Keith C Ng | Primary Beamlines | Repair | q15 repair | Correction that all supply side (even numbered
insulators) ceramic insulators on Q15 have
been replaced with new old stock insulators |
|
110
|
Monday, February 05, 2018, 15:40 |
Keith C Ng | Primary Beamlines | Repair | 1A Q15 repair. | 1.) Completed covering up 1A Q15.
2.) RH flask currently contains the
8 insulators removed from Q15. 3.6 mSv/h |
|
111
|
Wednesday, February 14, 2018, 10:36 |
Keith C Ng | Primary Beamlines | Repair | 1a q12 q13 | Uncovered and placed bridges for 1a q12
q13 for doug's re cabling work. See WP C2018-02-13-2:
work |
|
115
|
Wednesday, March 21, 2018, 15:22 |
Keith C Ng | M9 | Repair | t2 m9 laser tracker jigs | Installed the remaining laser tracker jigs
for beam lines. No issues. Made sure 8"
target the mounting poles did not interfere |
|
119
|
Tuesday, April 16, 2019, 11:19 |
Ron Kuramoto | Primary Beamlines | Repair | 1AQ14 B/L Flange Broken Thermocouple | On March 7,2019 the Thermocouple (TC) cable
which monitors the temperature of the 1AQ14
B/L vacuum joint was broken when the iron |
|
120
|
Thursday, April 25, 2019, 11:13 |
Keith C Ng | M20 | Repair | M20 Q2 repair notes | See attached scan for repair notes regarding
M20 Q2 during the 2019 winter shutdown. The
repair method for M20 Q2 was instigated by |
|
124
|
Monday, February 24, 2020, 15:13 |
Keith C Ng | M9 | Repair | m9 q1q2 repair laser tracker shoot | Beamlines
shot the position of the M9 T2 port and B1
flange for setting the M9 test stand flanges |
|
125
|
Friday, March 06, 2020, 13:36 |
Keith C Ng | M9 | Repair | M9 B1 moved to warm cell | The M9 B1 was removed from the M9
channel surveyed and moved to the remote
handling warm cell for refurbishment. |
|
129
|
Friday, March 18, 2022, 12:12 |
Keith C Ng | Primary Beamlines | Repair | q15 repair | beamlines replaced leaking insulator
on q15, circuit #4. See updated pdf for replacement
part and location. |
|
19
|
Friday, January 11, 2013, 15:44 |
Keith C Ng | Primary Beamlines | Maintenance | 1AVA8 valve o ring replacement | Assisted vacuum group with removing 1AVA8:
- uncovered valve area and set up
remote handling bridge over valve. |
|
20
|
Monday, January 14, 2013, 16:36 |
Keith C Ng | Primary Beamlines | Maintenance | 1AVA8 valve o ring replacement | continued with o ring replacement, replaced
all relevant o ring seals on valve (valve
body seal and actuator arm dynamic seals). |
|
21
|
Tuesday, January 15, 2013, 16:37 |
Keith C Ng | Primary Beamlines | Maintenance | 1AVA8 valve o ring replacement | Job completed today and shielding block
over valve restored.
- He leak checked valve and accessible |
|
31
|
Friday, February 01, 2013, 14:15 |
Keith C Ng | Primary Beamlines | Maintenance | M9 Q1 Q2; storage pit assessment | Uncovered radioactive waste storage pit
to see contents. Assessing viability of moving
contents inside to facilitate storage of |
|
33
|
Tuesday, February 05, 2013, 16:12 |
Keith C Ng | Primary Beamlines | Maintenance | 1A triplet repair (ground fault) (Completed) | Today: D. Preddy completed another power
test on 1A Q14, 15, 16 after all iron/steel
shielding was restored. Magnet power and |
|