  18   Wednesday, October 24, 2012, 11:53 Keith C NgM9RepairM9 T2 blank off completeShielding around m9 t2 restored as of 11:45,
vacuum levels still the same since 19 October.
- Work permit returned.
 201211_m9t2repair.xlsx 
  22   Wednesday, January 16, 2013, 17:03 Keith C NgPrimary BeamlinesRepair1A triplet repairMoved 18' blocks away from triplet area
in preparation for uncovering triplet. Plastic
laid down up stream of t2 target station
  
  23   Friday, January 18, 2013, 14:40 Keith C NgPrimary BeamlinesRepair1A triplet repairCompleted uncovering
shielding and RH setup over 1A Q14 triplet
area, see photo for RH setup.
 20130118_tripletrepair_RHB_5431-web_m.jpg 
  24   Tuesday, January 22, 2013, 16:02 Keith C NgPrimary BeamlinesRepair1A triplet repair1.5 day work delay due to plant group unavailable
on the 21st of January. Gardner air compressor
was being moved.
 20130122_tripletrepair_IMG_0018_webm.jpg 
  25   Wednesday, January 23, 2013, 15:51 Keith C NgPrimary BeamlinesRepair1A triplet repair (ground fault)Continued work on finding ground fault
in 1A triplet magnets;
 
 20130123_tripletrepair_P1020666.JPG20130123_tripletrepair_P1020664.JPG20130123_tripletrepair_P1020669.JPG 
  26   Thursday, January 24, 2013, 17:05 Keith C NgPrimary BeamlinesRepair1A triplet repair (ground fault)Continued with work on finding ground fault
on 1A triplet;
 
 20130124_tripletrepair_IMG_0047.JPG20130122_tripletrepair_IMG_0011.JPG20130124_tripletrepair_IMG_0040.JPG 
  27   Friday, January 25, 2013, 15:15 Keith C NgPrimary BeamlinesRepair1A triplet repair (ground fault)Today: Uncovered 1A triplet cable chase
and reconfigured shielding. D. Preddy will
continue with diagnosing ground fault on
 20130125_tripletrepair_IMG_0071.JPG20130125_tripletrepair_IMG_0067.JPG 
  28   Monday, January 28, 2013, 16:28 Keith C NgPrimary BeamlinesRepair1A triplet repair (ground fault)Rad survey map from last Friday (25 January)
here.
 
 6x 
  29   Tuesday, January 29, 2013, 16:28 Keith C NgPrimary BeamlinesRepair1A triplet repair (ground fault)Restored shielding over 1A triplet chase.
 
Uncovered Q16 and set up RH bridge
  
  30   Wednesday, January 30, 2013, 16:46 Keith C NgPrimary BeamlinesRepair1A triplet repair (ground fault)Cut and removed asymmetric steering cables
from Q14 and 16, cables are no longer resting
on magnet power bus bars.
 20130130_tripletrepair_P1020683.JPG20130130_tripletrepair_IMG_0123.JPG20130130_tripletrepair_P1020686.JPG20130130_tripletrepair_IMG_0118.JPG20130130_tripletrepair_P1020697.JPG 
  32   Monday, February 04, 2013, 16:04 Keith C NgPrimary BeamlinesRepair1A triplet repair (ground fault)Restored 1A triplet shielding and removed
RH shielding.
 
 20130204_tripletrepair_IMG_0129.JPG20130204_tripletrepair_IMG_0130.JPG20130204_tripletrepair_IMG_0132.JPG20130204_tripletrepair_IMG_0134.JPG20130204_tripletrepair_IMG_0133.JPG 
  35   Thursday, February 07, 2013, 16:02 Keith C NgM9RepairM9 Q1 Q2 removal, site preprationStarted work on removing M9 Q1 Q2 magnets;
area clean up and preparation, removing shielding
above Q1 and Q2 and remote handling setup
 20130207_m9q1q2remove_IMG_0155.JPG20130207_m9q1q2remove_IMG_0162.JPG20130207_m9q1q2remove_IMG_0165.JPG20130207_m9q1q2remove_IMG_0154.JPG20130207_m9q1q2remove_IMG_0157.JPG 
  36   Friday, February 08, 2013, 15:31 Keith C NgM9RepairM9 Q1 Q2 removal, site preprationCompleted remote handling/shielding setup
over T2 M9, see photos for setup.
- Rad levels at 16' above Q2 were
 20130208_m9q1q2remove_IMG_0172.JPG20130208_m9q1q2remove_IMG_0174.JPG20130208_m9q1q2remove_IMG_0175.JPG 
  40   Monday, February 18, 2013, 16:24 Keith C NgM9RepairM9 Q1 Q2 removal, electrical and water disconnectedToday, re-arranged electrical wiring on
Q1 Q2 magnet away from Q2 indium joint. Cable
bundles were bundled as neatly as possible.
 20130218_m9q1q2remove_P1020787.JPG20130218_m9q1q2remove_P1020786.JPG20130218_m9q1q2remove_P1020788.JPG 
  43   Friday, February 22, 2013, 17:27 Keith C NgM9RepairM9 Q1 Q2 removal, Q2 joint dissassemblyM9 Q2 15" pin drive was removed and
disconnected.
- Pin drive retention screw had to
 20130222_m9q1q2remove_P1020840.JPG20130222_m9q1q2remove_P1020832.JPG20130222_m9q1q2remove_P1020831.JPG 
  49   Thursday, March 07, 2013, 08:35 Keith C NgM9RepairM9 T2 flange blank offWork on blank off of M9 T2 started: Cleared
away blocks making up bagging bunker. R.
Kuramoto took some initial photos of the
  
  53   Tuesday, March 26, 2013, 09:04 Keith C NgM9RepairM9 Q1Q2 void inspectionYesterday: did visual, video inspection
and still imaging of T2 M9 Q1Q2 void. G.
Morris came down to work site for visual
 20130325_t2m9q1q2void_RHB_5726.JPG20130325_t2m9q1q2void_RHB_5728.JPG20130325_t2m9q1q2void_RHB_5742.JPG 
  55   Wednesday, April 10, 2013, 16:20 Keith C NgM9RepairM9 T2 flange blank offContinued with work on T2 M9 exit port
and area; Vacuum started after 13:00 hours
(due to vacuum pump issues at T2). He leak
  
  56   Thursday, April 11, 2013, 15:43 Keith C NgM9RepairT2 M9 exit port temporary shieldingInstalled shielding stand (TSH0094) for
T2 M9 exit port as per drawing TSH0095; three
steel blocks in total were lowered into the
 10x 
  57   Thursday, December 12, 2013, 14:21 Keith C NgPrimary BeamlinesRepairT2 suck tube active/contaminated water removalRemoved "suck tube" filled with
active/contaminated water from top of 1A
beam line blocks to meson extension hall
  