Removed 8" rubber test rings from M9 T2 joint. Rings moved to RH warm cell. Radiation levels were 70 µSv on contact 1.7 µSv @ 1/2 m.
Bagging bunker was setup west of the T2 M9 work area, see photos.
Began disconnecting M9 Q1 Q2 services: Electrical and thermal switch connectors disconnected from service stand, water service lines for Q1 and Q2 remain to be disconnected.
|