Entry  Monday, September 25, 2023, 16:31, Aaron Schmidt, Ta#66, LP-SIS, ITW, TM2, 45220-5, 45235-9, Done, Conditioning Ta#66 & HV Tests. Ta#66_HV_Test_1.docxTa#66_HV_test_2.docxTa#66_Conditioning.docx
Thermocouples installed on the left end plate x 2.
Monday, September 25, 2023, 16:23: Roughing.
Monday, September 25, 2023, 16:51: TP1B on.
Entry  Tuesday, October 10, 2023, 15:46, Aaron Schmidt, Ta#68 (Spare), LP-SIS, , , 45220-3, 45235-11, In progress, Conditioning Ta#68 (Spare) Ta#68-Spare_Conditioning.docx
Tuesday, October 10, 2023, 15:18: Roughing.
Tuesday, October 10, 2023, 15:46: TP1B on.
Tuesday, October 10, 2023, 15:52: TP1B at speed. CG1A @ 0.113T & dropping.
Entry  Wednesday, October 18, 2023, 15:43, Aaron Schmidt, , LP-SIS, , , 45447-12, 45235-17, In progress, Conditioning UC#43 (empty) w/ gas line UC#43_Conditioning_empty_with_Gas_mod.docxUC#43_HS_with_gas_line_mod_-_Test_2.docxUC#43_HS_with_gas_line_mod_-_HV_Test.docx
Thermocouples attached on end plate
Indium salt @ 10 µl
3 wraps of Ta HS on oven. Gas line on center block. Empty oven.
Entry  Monday, October 30, 2023, 16:01, Aaron Schmidt, , LP-SIS, , , 45220-2, 45235-13, In progress, HV power surge test plus mass scans 
 Monday, October 30, 2023, 16:00  Roughing

Tuesday, October 31, 2023, 08:58 Turbos on the afternoon before, TP1A timed out which delayed for another 30min turning on both TP. Now
3e-6 Torr in IG1. - FBP
Entry  Thursday, November 16, 2023, 09:43, Aaron Schmidt, , LP-SIS, , , , , In progress, Thermal tests 
Aurelia has been testing on the ISAC TS since last week. Thermocouples are installed in the end cap, left side & the ionizer.
No elog was initiated, but much has happened.
Site wide power outage on Friday/Saturday caused problems. The TS was running at that time & was also affected. Reboots occurred on the weekend
Entry  Monday, November 27, 2023, 16:09, Ferran Boix Pamies, , LP-SIS, , , 45220-2, 45235-13, In progress, HV power surge test plus mass scans 
Monday, November 27, 2023, 16:09  Roughing
Monday, November 27, 2023, 17:22 Both turbos are on, leaving vacuum over night.
Tuesday, November 28, 2023, 09:28  after pumping over night IG1 is at .15e-6 T. Water cooling on.
Entry  Thursday, January 18, 2024, 10:49, Aaron Schmidt, , LP-SIS, , , 44139-2, 45235-22, In progress, Conditioning UCx HS  
Straight/closed TGHT tube oven installed. SIS Assembly.
Thursday, January 18, 2024, 10:32: Roughing.
Thursday, January 18, 2024, 10:57: TP1B on.
Entry  Monday, January 22, 2024, 13:55, Aaron Schmidt, , LP-SIS, , , 45447-19, 45235-22, In progress, Conditioning UCx HS - 2 
Conditioning HS for UCx. LP-SIS oven / end caps installed
Monday, January 22, 2024, 13:53: Roughing.
Monday, January 22, 2024, 14:21: TP1B On.
Entry  Thursday, April 04, 2024, 10:38, Dave Neilson, , LP-SIS, , , 44691-8, 45235-26, Done, Mass marker testing 
 Thursday, April 04, 2024, 09:49: Target inserted yesterday, April 3. mass marker tube connections carefully confirmed. Vacuum roughed, turbo pumps
switched on at end of day. Water cooling turned on this morning. 
Thursday, April 04, 2024, 09:52 : Vacuum at 6.4e-6.  Not low enough to bypass lockout for TGHT TBHT ramp.
Entry  Wednesday, April 24, 2024, 16:21, Dave Neilson, , LP-SIS, , , 44691-8, 45235-26, ,  
 Wednesday, April 24, 2024, 16:20:     Target assembly installed.
Wednesday, April 24, 2024, 16:20:  VV1 closed. Pumping down to rough vacuum 
Wednesday, April 24, 2024, 16:21:   Water cooling on. Seal on lines confirmed.
Entry  Thursday, May 02, 2024, 13:45, Dave Neilson, -, LP-SIS, , , 44691-8, 45235-26, In progress, Mass marker testing 
 Wednesday, May 01, 2024, 12:44:  pumped down to rough vacuum, TP1B now on.
Wednesday, May 01, 2024, 12:49:  TP1A on.
Thursday, May 02, 2024, 9:10:  water cooling on. no effect on vacuum
Entry  Tuesday, July 23, 2024, 09:43, Dave Neilson, , LP-SIS, , , 44691-8, 45235-26, Done, mass marker - reservoir testing 
Wednesday, July 22, 2024, 11:41  - target installed
Wednesday, July 22, 2024, 13:31 - pumping down
Wednesday, July 22, 2024, 14:21 - turbo pumps on
Entry  Thursday, July 25, 2024, 14:26, Dave Neilson, Ta#67 Thin foil , LP-SIS, ITE, TM3, 45447-14, 45235-10, , Conditioning Ta#67 Thin foil 
Thursday, July 25, 2024, 14:25  - competing electrical checks prior to test stand installation
 Thursday, July 25, 2024, 17:07 - after target installation test stand roughed down, turbo pumps then turned on. vacuuming overnight
 Friday, July 26, 2024, 09:01  -  water cooling turned on, while monitoring vacuum level (~1.5e-6T).  No affect on vacuum.
Entry  Monday, July 29, 2024, 23:02, Aurelia Laxdal, Ta#67 Thin foils, LP-SIS, ITE, TM3, 45447-14, 45235-10, , Cooldown for removing the V wires  
 22:55 Cooldown completed to remove the voltage wires from inside the vacuum box. 
Entry  Friday, August 09, 2024, 21:08, Ferran Boix Pamies, Ta#67 Thin foils , LP-SIS, ITE, TM4, 45447-14 , 45235-10, In progress, Ta#67 thin foil retesting ITE-TM4-Ta#67-LP-SIS_Thin_Foil.docx
Friday, August 09, 2024, 21:07 Insulators, retainer and Re foil have been replaced, source cup machined so the ion source does not short against it.
Venting TS now.
Friday, August 09, 2024, 22:17 Roughing.
Entry  Friday, September 20, 2024, 14:22, Aaron Schmidt, Ta#, LP-SIS, ITE, TM2, 45447-18, 45235-13, , Conditioning Ta# 
 https://elog.triumf.ca/TIS/Target+Production/146
Has not run through EVAP2.
Friday, September 20, 2024, 14:04: Roughing.
Entry  Wednesday, November 13, 2024, 14:36, Aaron Schmidt, UC#(47) - Not included, LP-SIS, ITE, TM3, 44691-8, 45235-24, In progress, Conditioning UC#47 (Assembly only) UC#47_empty_conditioning_test_1_-_Failed.docxUC#47_empty_conditioning_test_2.docx
Gas line is attached. 
Wednesday, November 13, 2024, 14:18: Roughing.
Wednesday, November 13, 2024, 18:20: Closed backing valves. Vacuum @ 2.140 T? 
Entry  Wednesday, June 01, 2016, 10:02, Aaron Schmidt, UC#16, LP-IG-LIS, ITE, TM4, 39814-V2-1, , , Conditioning Heat shield for UC#16 OMEGA_OM-DAQPRO-5300_03-Jun-16_08.14.47.dlpTS-2016-06-02_UC#16.rgaTS-2016-06-02-13-46_UC#16.rgaUC#16.docx
Wednesday, June 01, 2016, 10:02: Begin roughing.
Wednesday, June 01, 2016, 10:44: Turbo pumps started.
Wednesday, June 01, 2016, 10:47: Ion Gauge IG1 ON.
Entry  Friday, September 02, 2016, 15:47, Aaron Schmidt, SiC#34, LP-IG-LIS, ITE, TM4, 39814-V2-1, 41751-9, , Conditioning SiC# 34 ER-580-270-m40.txtITE-TM4-SiC#34-LP-IG-LIS_Test_Stand.docxSiC#34.docxTS-2016-09-06-08-12.rga
Friday, September 02, 2016, 15:47: Roughing.
Friday, September 02, 2016, 16:18: Turbos started -AM
Friday, September 02, 2016, 16:28: Turbos at speed. Vacuum at 2.0E-5 T.
Entry  Thursday, May 04, 2017, 13:49, Aaron Schmidt, UC#20, LP-IG-LIS, , , , , , Conditioning Heat shield for UC#20 (1) UC#20_Heat_shield_conditioning-1.docxTS-2017-05-05-07-35.rga
Thursday, May 04, 2017, 13:48: Roughing.
Thursday, May 04, 2017, 14:09: Turbos on.

Friday, May 05, 2017, 07:35: RGA on. Vacuum @ 1.56e-06T