244
|
Thursday, September 06, 2018, 13:49 |
Isaac Earle | Repair | Target 1 | Cooling | T1 cooling package secondary side solenoid failed | On Friday Aug 31 at approximately
3am T1CS:FGSEC dropped to 0gpm flow.
This was confirmed to be a real reading when |
|
247
|
Thursday, January 10, 2019, 13:51 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 and T2 cooling packages inspected | The T1 and T2 cooling packages were inspected
today while running. No water leaks
were observed at either package including |
|
249
|
Tuesday, February 26, 2019, 10:55 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 and T2 MRO work and solenoid valve change summary | The following work was completed between
Jan 16 - Feb 19, 2019:
T1 and T2 cooling packages |
|
251
|
Wednesday, May 22, 2019, 14:25 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 target moved to HC; T1-MK1 target moved to BL | After extensive
testing over the last 2 weeks it was determined |
|
252
|
Monday, June 24, 2019, 14:29 |
Isaac Earle | Development | Target 1 | Target | T1 and T2 target alignment frames overhauled | The following work was completed on both
the T1 and T2 target alignment frames
One of the short taper |
8x |
255
|
Thursday, January 30, 2020, 17:55 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 target assembly repair completed in hot cell | The following work was done to the T1-MK2
target in the hotcell between the dates of
May 24, 2019 - Jan 30, 2020 (See E-Log #251 |
    |
256
|
Wednesday, February 05, 2020, 14:53 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 & T2 cooling package MRO work completed | Annual MRO work on the T1 and T2
cooling packages is now complete. The
following tasks were performed: |
|
269
|
Wednesday, August 19, 2020, 12:57 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1/T2 MRO summary for 2020 shutdown | The following work was completed during
the 2020 shutdown period for BL1A (Jan-Aug
2020): |
|
273
|
Wednesday, March 31, 2021, 16:15 |
Matthew Gareau | Standard Operation | Target 1 | Target | T1-MK1 target exchange | March 29 Monday
- moved T1-MK1 target from beamline
to hotcell (field from target 15mSv/hr |
   |
276
|
Thursday, February 17, 2022, 13:03 |
Matthew Gareau | Maintenance | Target 1 | Target | T1 MK2 wire scanner and protect monitor test removal and reattachment with pin straightening | this Work was done on 09 Dec 2021.
Since Isaac Earle was leaving Triumf
he was giving us (maico, chad, adam, and |
    |
278
|
Thursday, March 10, 2022, 13:57 |
Adam Newsome | Maintenance | Target 1 | Cooling | Changed paddle wheel, o-ring, and shaft in flow sensors at T1 cooling package | The paddle wheels, o-rings, and shafts
were changed at the T1 cooling package for
the following sensors: |
|
279
|
Friday, March 11, 2022, 15:05 |
Adam Newsome | Maintenance | Target 1 | Cooling | O-rings on T1 cooling package water reservoir changed | The four o-rings on top of the T1 cooling
package water reservoir were changed as per
the recommended 5 year replacement schedule. |
|
281
|
Friday, March 11, 2022, 15:08 |
Adam Newsome | Maintenance | Target 1 | Cooling | Filters replaced: T1 cooling system | All filters were replaced for the T1 cooling
system: demineralizing resin circuit, target
water system, and M15. |
|
283
|
Monday, March 14, 2022, 14:08 |
Adam Newsome | Maintenance | Target 1 | Cooling | T1 cooling system: filled, tuned, leak-checked | The T1 cooling system was refilled with
water via the expansion tank until the tank
level read approximately 38 cm. |
|
291
|
Thursday, May 05, 2022, 14:39 |
Adam Newsome | Standard Operation | Target 1 | Target | T1-MK1 and T2-MK1 profile monitor actuation test | The profile monitor actuation tests were
completed for T1 and T2. No abnormalities
were noticed in vacuum during either test. |
|
292
|
Wednesday, May 25, 2022, 10:15 |
Adam Newsome | Standard Operation | Target 1 | Target | T1-MK2 moved from hot cell to storage area | The T1-MK2 target was moved from the hot
cell to the storage area, in position 5.
Note: manual nudging of the flask was required |
|
305
|
Tuesday, October 11, 2022, 11:27 |
Adam Newsome | Maintenance | Target 1 | Cooling | T1 inlet pressure transducer replacement | A fault was reported June 21, 2022 (Fault
15033) regarding T1 inlet pressure warnings... |
|
308
|
Thursday, January 12, 2023, 10:36 |
Adam Newsome | Maintenance | Target 1 | Water Leak | T1 and T2 - Cooling Package Water Leaks - Ball Valves | Upon uncovering the T1 and T2 areas to
prepare for regular cooling package maintenance,
it was discovered that multiple ball valves |
|
310
|
Monday, January 16, 2023, 15:01 |
Adam Newsome | Maintenance | Target 1 | Cooling | T1 Cooling Package MRO - 2023 Shutdown | T1 Cooling Package MRO began Jan. 16, 2023.
The following maintenance tasks have |
|
315
|
Wednesday, February 01, 2023, 14:23 |
Albert Kong | Maintenance | Target 1 | Cooling | T1 Cooling Package: flow test after resin exchange / valve leak check / faulty(?) dial pressure gauge | Maico/Eric/Albert:
The expansion tank in T1 was filled
to ~36cm in the morning. |
|