ID Date Author Category Typedown Specific Subject Text Attachments
  55   Friday, September 07, 2012, 16:35 Isaac EarleRepairTarget 2TargetT2-MK1 Target Repair Completed - Profile monitor wiring harness
checked by Bill Rawnsley using resistor pack
--> OK
  
  61   Wednesday, October 24, 2012, 17:38 Isaac EarleRepairTarget 2TargetT1 & T2 Target Ladder Control System Status During the recent shutdown for the
T2/M9 joint repair Graham Waters replaced
the corrupted application code on the controller
  
  65   Tuesday, January 08, 2013, 09:27 Isaac EarleStandard OperationTarget 2TargetBL1A Air Amplifier turned off for duration of shutdown. The BL1A air amplifier
has been shut down by closing the air supply
  
  66   Tuesday, January 08, 2013, 10:52 Isaac EarleMaintenanceTarget 2TargetT2-MK1 Target Maintenance- T2-MK1 target transported from storage
pit to hot cell
- Proximity sensor removed
  
  68   Monday, January 14, 2013, 16:55 Isaac EarleStandard OperationTarget 2TargetTarget Move & Damaged Profile MonitorThe T2-MK1 target (spare T2 target) was
transported from the hot cell to the storage
pit today.  
  
  69   Monday, January 21, 2013, 11:57 Isaac EarleRepairTarget 2TargetFlask Repair On January 15th, when attempting
to move the T2 target from the beam line
to the hot cell, the latch mechanism on the
 IMG_0818.JPGIMG_0824.JPGIMG_0836.JPGIMG_0838.JPG 
  70   Monday, January 21, 2013, 16:18 Isaac EarleStandard OperationTarget 2TargetT2 Cooling Package Water ReleasedThe T2 cooling package water was drained
to the BL1A active sump, refilled, cycled,
and drained again.  Samples of T2 cooling
  
  71   Tuesday, January 29, 2013, 15:55 Isaac EarleMaintenanceTarget 2CoolingT2 H.E. Transported to Warm CellFriday Jan 25:
- Both sides of heat exchanger drained,
disconnected, and capped
 IMG_0860.JPGIMG_0864.JPG 
  72   Tuesday, February 05, 2013, 09:50 Isaac EarleMaintenanceTarget 2TargetT2-MK2 target moved from beam line to hot cellThe T2-MK2 target was transported from
the beam line to the RH hot cell.  The
profile monitor was secured in the 'in' position
 IMG_0868.JPG 
  73   Wednesday, March 06, 2013, 12:13 Isaac EarleMaintenanceTarget 2CoolingT2 Heat Exchanger MRO- The new tube array was picked up from
Kaltech on Feb 8th (observed vessel holding
60psi on hydro test at their shop)
 7x 
  74   Monday, March 18, 2013, 15:17 Isaac EarleMaintenanceTarget 2TargetT2-MK2 Target Maintenance and Re-Wiring- T2-MK2 target moved from beamline to
hot cell (Feb 4th)
- Steel target support shield installed
 IMG_1189.JPGIMG_1194.JPGIMG_1197.JPGIMG_1207.JPGT2-MK2_Tgt_leak_check.PDF 
  79   Wednesday, April 17, 2013, 16:43 Isaac EarleStandard OperationTarget 2TargetT2 target installed; Vacuum leak-tight; Monitors OK; T2 ready for beamThe T2-MK2 target was transferred from
the storage pit to the beam line yesterday
(April 16th).  The field was measured
  
  86   Monday, September 09, 2013, 16:13 Isaac EarleRepairTarget 2CoolingDrop in T2 Cooling Package Water Level On September 9th in the morning Ron
Kuramoto noticed that the T2 cooling package
expansion tank level was reading NOT OK for
  
  88   Wednesday, September 11, 2013, 16:13 Isaac EarleRepairTarget 2CoolingT2 Cooling Package Water Leak Repair The T2 cooling package was uncovered
this morning and a leak was found coming
from the Swagelok ball valve on the 3/4"
  
  92   Friday, November 22, 2013, 20:26 Grant MinorRepairTarget 2Water LeakT2 Water Leak - Target Assembly Removed and Water Sucked Out of B/LT2 target water leak was identified earlier
this morning.
Isaac Earle, Ron Kuramoto and Keith
 T2_tgt_water_leak_22Nov2013-006-before-suck.JPGT2_tgt_water_leak_22Nov2013-013-after-suck.JPGT2_tgt_water_leak_22Nov2013-016.JPGT2_tgt_water_leak_22Nov2013-017.JPG 
  93   Saturday, November 23, 2013, 18:37 Isaac EarleRepairTarget 2TargetT2-MK1 Installation- T2-MK1 target transported from the storage
area by Isaac and Grant and installed at
the T2 monolith.  All services were
  
  94   Tuesday, November 26, 2013, 10:33 Isaac EarleRepairTarget 2TargetT2-MK2 Water Flush The T2-MK2 target in the hot cell
was flushed with water and then purged with
air so that stagnant water is not left sitting
  
  95   Monday, January 06, 2014, 15:55 Isaac EarleRepairTarget 2TargetT2-MK2 Repair The leaking 10cm Be target was removed
from position 3 on the T2-MK2 target ladder
and the water ports were blanked-off with
 DSC_6622.JPGDSC_6623.JPGDSC_6626.JPGIMG_1809.JPG 
  96   Thursday, January 09, 2014, 15:21 Isaac EarleRepairTarget 2TargetT2-MK2 Electrical Check An electrical check was performed
on the T2-MK2 profile monitor by Bill Rawnsley.
 All signals produced the expected response,
  
  97   Wednesday, January 15, 2014, 15:38 Isaac EarleStandard OperationTarget 2Water LeakSuck Tube Drained and RinsedThe suck tube vessel was drained, rinsed,
and transported to the active sink area in
the Meson Hall Hot Cell Lab.  There
 IMG_1276.JPGIMG_1291.JPGIMG_1295.JPGIMG_1296.JPGIMG_1297.JPG 