ID |
Date |
Author |
Category |
Type |
Specific |
Subject |
Text |
|
55
|
Friday, September 07, 2012, 16:35 |
Isaac Earle | Repair | Target 2 | Target | T2-MK1 Target Repair Completed | - Profile monitor wiring harness
checked by Bill Rawnsley using resistor pack
--> OK |
|
61
|
Wednesday, October 24, 2012, 17:38 |
Isaac Earle | Repair | Target 2 | Target | T1 & T2 Target Ladder Control System Status | During the recent shutdown for the
T2/M9 joint repair Graham Waters replaced
the corrupted application code on the controller |
|
65
|
Tuesday, January 08, 2013, 09:27 |
Isaac Earle | Standard Operation | Target 2 | Target | BL1A Air Amplifier turned off for duration of shutdown. | The BL1A air amplifier
has been shut down by closing the air supply |
|
66
|
Tuesday, January 08, 2013, 10:52 |
Isaac Earle | Maintenance | Target 2 | Target | T2-MK1 Target Maintenance | - T2-MK1 target transported from storage
pit to hot cell
- Proximity sensor removed |
|
68
|
Monday, January 14, 2013, 16:55 |
Isaac Earle | Standard Operation | Target 2 | Target | Target Move & Damaged Profile Monitor | The T2-MK1 target (spare T2 target) was
transported from the hot cell to the storage
pit today. |
|
69
|
Monday, January 21, 2013, 11:57 |
Isaac Earle | Repair | Target 2 | Target | Flask Repair | On January 15th, when attempting
to move the T2 target from the beam line
to the hot cell, the latch mechanism on the |
|
70
|
Monday, January 21, 2013, 16:18 |
Isaac Earle | Standard Operation | Target 2 | Target | T2 Cooling Package Water Released | The T2 cooling package water was drained
to the BL1A active sump, refilled, cycled,
and drained again. Samples of T2 cooling |
|
71
|
Tuesday, January 29, 2013, 15:55 |
Isaac Earle | Maintenance | Target 2 | Cooling | T2 H.E. Transported to Warm Cell | Friday Jan 25:
- Both sides of heat exchanger drained,
disconnected, and capped |
|
72
|
Tuesday, February 05, 2013, 09:50 |
Isaac Earle | Maintenance | Target 2 | Target | T2-MK2 target moved from beam line to hot cell | The T2-MK2 target was transported from
the beam line to the RH hot cell. The
profile monitor was secured in the 'in' position |
|
73
|
Wednesday, March 06, 2013, 12:13 |
Isaac Earle | Maintenance | Target 2 | Cooling | T2 Heat Exchanger MRO | - The new tube array was picked up from
Kaltech on Feb 8th (observed vessel holding
60psi on hydro test at their shop) |
7x |
74
|
Monday, March 18, 2013, 15:17 |
Isaac Earle | Maintenance | Target 2 | Target | T2-MK2 Target Maintenance and Re-Wiring | - T2-MK2 target moved from beamline to
hot cell (Feb 4th)
- Steel target support shield installed |
|
79
|
Wednesday, April 17, 2013, 16:43 |
Isaac Earle | Standard Operation | Target 2 | Target | T2 target installed; Vacuum leak-tight; Monitors OK; T2 ready for beam | The T2-MK2 target was transferred from
the storage pit to the beam line yesterday
(April 16th). The field was measured |
|
86
|
Monday, September 09, 2013, 16:13 |
Isaac Earle | Repair | Target 2 | Cooling | Drop in T2 Cooling Package Water Level | On September 9th in the morning Ron
Kuramoto noticed that the T2 cooling package
expansion tank level was reading NOT OK for |
|
88
|
Wednesday, September 11, 2013, 16:13 |
Isaac Earle | Repair | Target 2 | Cooling | T2 Cooling Package Water Leak Repair | The T2 cooling package was uncovered
this morning and a leak was found coming
from the Swagelok ball valve on the 3/4" |
|
92
|
Friday, November 22, 2013, 20:26 |
Grant Minor | Repair | Target 2 | Water Leak | T2 Water Leak - Target Assembly Removed and Water Sucked Out of B/L | T2 target water leak was identified earlier
this morning.
Isaac Earle, Ron Kuramoto and Keith |
|
93
|
Saturday, November 23, 2013, 18:37 |
Isaac Earle | Repair | Target 2 | Target | T2-MK1 Installation | - T2-MK1 target transported from the storage
area by Isaac and Grant and installed at
the T2 monolith. All services were |
|
94
|
Tuesday, November 26, 2013, 10:33 |
Isaac Earle | Repair | Target 2 | Target | T2-MK2 Water Flush | The T2-MK2 target in the hot cell
was flushed with water and then purged with
air so that stagnant water is not left sitting |
|
95
|
Monday, January 06, 2014, 15:55 |
Isaac Earle | Repair | Target 2 | Target | T2-MK2 Repair | The leaking 10cm Be target was removed
from position 3 on the T2-MK2 target ladder
and the water ports were blanked-off with |
|
96
|
Thursday, January 09, 2014, 15:21 |
Isaac Earle | Repair | Target 2 | Target | T2-MK2 Electrical Check | An electrical check was performed
on the T2-MK2 profile monitor by Bill Rawnsley.
All signals produced the expected response, |
|
97
|
Wednesday, January 15, 2014, 15:38 |
Isaac Earle | Standard Operation | Target 2 | Water Leak | Suck Tube Drained and Rinsed | The suck tube vessel was drained, rinsed,
and transported to the active sink area in
the Meson Hall Hot Cell Lab. There |
|