Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Test-Stand, Page 29 of 53  Not logged in ELOG logo
Entry  Tuesday, December 13, 2022, 16:12, Aaron Schmidt, , HP-FEBIAD-CTL, , , 43104-2, 45235-12, In progress, New anode routed FEBIAD Test - 2 Re-routed_Anode_FEBIAD_12-2022_Test_2.docx
Thermocouples installed (X):
O - O
O - Anode
Entry  Friday, December 16, 2022, 10:32, Aaron Schmidt, , HP-FEBIAD-CTL, , , 43104-2, 45235-12, In progress, New anode routed FEBIAD Test - 3 
Thermocouples installed (X):
O - O
O - Anode
Entry  Thursday, January 12, 2023, 09:04, Aaron Schmidt, , LP-SIS, , , 44691-14, 44378-20, In progress,  
Test for Aurelia L. Empty LP-SIS w/ end caps in. Right side expanded.
Thermocouples installed (R - L):
X & Y For the (V) checks.
Entry  Monday, January 16, 2023, 16:02, Aaron Schmidt, , HP-FEBIAD-CTL, , , , , In progress, HP-FEBIAD tests 
Extra wraps of foil around the center block (6) + 3 full wraps around the shield.
Monday, January 16, 2023, 15:40: Roughing.
Monday, January 16, 2023, 16:10: TP1B on.
Entry  Tuesday, January 31, 2023, 10:42, Aaron Schmidt, , LP-SIS, , , 44062-1-SK, 45235-7, In progress, Conditioning UC#x assembly 
SK Series of LP-SIS targets are for conditioning only.
Tuesday, January 31, 2023, 10:39: Roughing. (Took quite a bit of effort to get the doors to shut. It's colder than usual in here. The seals were
stiff)
Entry  Thursday, February 02, 2023, 12:44, Aaron Schmidt, , LP-SIS, , , 44062-1-SK , 45235-1, In progress, Conditioning UC#x assembly 
SK Series of LP-SIS targets are for conditioning only.
Thursday, February 02, 2023, 12:41: Roughing.
Thursday, February 02, 2023, 12:43: BV1A open.
Entry  Thursday, April 13, 2023, 11:07, Aaron Schmidt, , , , , , , In progress, Installation of new IDP-15 TMS:TP2 
IDP15 Scroll Pump, Std w/ inlet.
TMS:RP2
PN: X3815-64010
Entry  Monday, April 17, 2023, 14:08, Aaron Schmidt, TiC#6, HP-FEBIAD, ITW, TM2, 44692-10, 45235-12, In progress, Conditioning TiC#6 
Monday, April 17, 2023, 14:03: Roughing.
Monday, April 17, 2023, 14:08: BV1A open.
Monday, April 17, 2023, 14:32: TP1B on.
Entry  Monday, May 01, 2023, 14:31, Aaron Schmidt, TiC#5, LP-FEBIAD, ITE, TM4, 44692-5, 45235-20, In progress, Conditioning TiC#5 TiC#5_-_44692-5_Anode_&_Coil_checks.docxTiC#5_-_44692-5_Conditioning.docx
New TiC LP-FEBIAD Target installed.
Monday, May 01, 2023, 14:23: Roughing.
Monday, May 01, 2023, 21:42: TP1B on 
Entry  Friday, May 05, 2023, 06:49, Aaron Schmidt, TiC#6, HP-FEBIAD, ITW, TM2, 44692-10, 45235-12, In progress, Conditioning TiC#6 TiC#6_Anode_&_Coil_checks.docx
Ceramic elbow installed on the anode.
Friday, May 05, 2023, 06:47: Roughing.
Friday, May 05, 2023, 07:24: TP1B on.
Entry  Tuesday, May 09, 2023, 10:40, Aaron Schmidt, SiC#45, HP-SIS, ITE, TM4, 44692-3, 45235-8, In progress, Conditioning SiC#45 SiC#45_Conditioning..docx
Tuesday, May 09, 2023, 10:28: Roughing.
Tuesday, May 09, 2023, 11:25: TP1B on. 
Tuesday, May 09, 2023, 12:38: TP1A on.
Entry  Tuesday, May 16, 2023, 14:00, Aaron Schmidt, Ta#65, LP-SIS, ITE, TM4, 45220-7, 45235-2, In progress, Conditioning Ta#65 Ta#65_conditioning_-_Mass_&_wire_scans.docx
Calibrated window installed on the beam line.
Tuesday, May 16, 2023, 13:45: Roughing both the chamber & beam line.
Tuesday, May 16, 2023, 14:00: TMS:TP6 on.
Entry  Wednesday, May 31, 2023, 15:19, Aaron Schmidt, SiC#46, HP-SIS, , , 44692-2, 45235-6, In progress, Conditioning SiC#2023A (Spare, renamed SiC-23B) - No salts SiC#2023A_-_No_Salts.docx
(Spare HP-SIS SiC SiC-23B)
Wednesday, May 31, 2023, 15:18: Roughing.

Thursday, June 01, 2023, 07:30: TP1B on.  
Entry  Thursday, July 06, 2023, 16:55, Aaron Schmidt, Nb#10, LP-IG-LIS, ITW, TM2, 45447-7, 42132-2, In progress, Conditioning Nb#10 Nb#10_Conditioning.docx
Thursday, July 06, 2023, 16:13: Roughing.
Thursday, July 06, 2023, 16:41: TP1B on.
Thursday, July 06, 2023, 16:47: TP1A on.
Entry  Thursday, July 13, 2023, 18:29, Aurelia Laxdal, , LP-SIS, , , , , In progress, Spectrometer tests 
 Pumping down: TS loaded with a LP-SIS container for spectrometer test. 
Started heating up the target container: up to 300A.
Last week: the LP container was heated up to TGHT 580A and TBHT 230A, and cooled down before the weekend. 
Entry  Wednesday, August 09, 2023, 14:29, Aaron Schmidt, , LP-SIS, , , 45220-6, 45235-3, In progress, Graphite target test 1 (C2023A) Graphite_target_45220-6.docxGraphitetesting_Aug102023.xlsx
Graphite
experiment 2: ID Gr-230601, WO#45220-6 ( https://elog.triumf.ca/TIS/Evaporator_2/598
Entry  Friday, August 25, 2023, 17:21, Aaron Schmidt, Nb#11, LP-IG-LIS, ITW, TM2, 45447-9, 42132-4, In progress, Conditioning Nb#11 Nb#11_Conditioning.docx
Replacement for Nb#10
Friday, August 25, 2023, 17:15: Roughing.
Friday, August 25, 2023, 17:57: Vacuum taking a while to rough down. Vacuum @ 1.034T. Opened FS#5.
Entry  Tuesday, October 10, 2023, 15:46, Aaron Schmidt, Ta#68 (Spare), LP-SIS, , , 45220-3, 45235-11, In progress, Conditioning Ta#68 (Spare) Ta#68-Spare_Conditioning.docx
Tuesday, October 10, 2023, 15:18: Roughing.
Tuesday, October 10, 2023, 15:46: TP1B on.
Tuesday, October 10, 2023, 15:52: TP1B at speed. CG1A @ 0.113T & dropping.
Entry  Wednesday, October 18, 2023, 15:43, Aaron Schmidt, , LP-SIS, , , 45447-12, 45235-17, In progress, Conditioning UC#43 (empty) w/ gas line UC#43_Conditioning_empty_with_Gas_mod.docxUC#43_HS_with_gas_line_mod_-_Test_2.docxUC#43_HS_with_gas_line_mod_-_HV_Test.docx
Thermocouples attached on end plate
Indium salt @ 10 µl
3 wraps of Ta HS on oven. Gas line on center block. Empty oven.
Entry  Monday, October 30, 2023, 16:01, Aaron Schmidt, , LP-SIS, , , 45220-2, 45235-13, In progress, HV power surge test plus mass scans 
 Monday, October 30, 2023, 16:00  Roughing

Tuesday, October 31, 2023, 08:58 Turbos on the afternoon before, TP1A timed out which delayed for another 30min turning on both TP. Now
3e-6 Torr in IG1. - FBP
ELOG V2.9.2-2455