Message ID: 969     Entry time: Wednesday, May 31, 2023, 15:19
Author: Aaron Schmidt 
Target/No.#: SiC#46 
Source: HP-SIS 
Station:  
Module:  
Target Oven W.O#: 44692-2 
Heat Shield W.O#: 45235-6 
Status: In progress 
Subject: Conditioning SiC#2023A (Spare, renamed SiC-23B) - No salts 

(Spare HP-SIS SiC SiC-23B)

Wednesday, May 31, 2023, 15:18: Roughing.


Thursday, June 01, 2023, 07:30: TP1B on.  

Thursday, June 01, 2023, 07:31: TMS:TP6 & TMS:TP2 on. 

Thursday, June 01, 2023, 07:38: IG6 on. TSG:TP1A on.

Thursday, June 01, 2023, 07:48: IG1 on.

Thursday, June 01, 2023, 08:26: Waterline FS#5 on. Vacuum @ 1.40e-06T. Power on.

Thursday, June 01, 2023, 08:28: Sources on. IV4 open.

Thursday, June 01, 2023, 08:31: Optics set.

Thursday, June 01, 2023, 08:33: Quick check: Manually tap up TGHT / TBHT to 5 / 5 A

BIAS / EE / EZL @ 1 / -0.5 / 1 kV.

Thursday, June 01, 2023, 08:51: Auto-ramping TGHT / TBHT to 100 / 50 A @ 2 A per min.

Thursday, June 01, 2023, 09:55: Auto-ramping TGHT / TBHT to 300 / 100 A @ 2 A per min.

Thursday, June 01, 2023, 11:36: Auto-ramping TGHT / TBHT to 580 / 230 A @ 2 A per min.

Thursday, June 01, 2023, 13:56: BIAS / EE / EZL @ 30 / -1.5 / 13 kV. 

Thursday, June 01, 2023, 14:20: Mass & wire scans.


Friday, June 02, 2023, 07:10: Mass & wires scans complete. Auto-cooling @ 2 A per min 

Friday, June 02, 2023, 09:22: BIAS / EE / EZL @ 0 kV. 


Thursday, June 08, 2023, 07:51: IV4 closed. Power / Sources off.

Thursday, June 08, 2023, 07:53: IG1 & Turbo pumps off.

Thursday, June 08, 2023, 10:32: Venting.

Attachment 1: SiC#2023A_-_No_Salts.docx  610 kB  Uploaded Wednesday, August 16, 2023, 11:00