SK Series of LP-SIS targets are for conditioning only.
Thursday, February 02, 2023, 12:41: Roughing.
Thursday, February 02, 2023, 12:43: BV1A open.
Thursday, February 02, 2023, 13:30: TP1B on.
Thursday, February 02, 2023, 13:34: TP1B at speed. TP1A on.
Thursday, February 02, 2023, 13:43: TP1A at speed. IG1 on.
Thursday, February 02, 2023, 14:53: Waterlines opened. Vacuum Ok @ 5.38e-06T.
Thursday, February 02, 2023, 14:55: PS / Sources on. Manually tap up TGHT / TBHT to 5 A. OK.
Friday, February 03, 2023, 06:32: Vacuum @ 6.56e-07T. Auto-ramping TGHT / TBHT to 580 / 230 A @ 2 A per min.
Monday, February 06, 2023, 07:39: Vacuum @ 8.36e-07T. Auto-cooling @ 2 A per min.
Tuesday, March 28, 2023, 13:45: Power / sources off.
Tuesday, March 28, 2023, 13:47: IG1 off. TP1A & TP1B off.
Wednesday, March 29, 2023, 07:53: Venting. |