Message ID: 951     Entry time: Friday, December 16, 2022, 10:32
Author: Aaron Schmidt 
Target/No.#:  
Source: HP-FEBIAD-CTL 
Station:  
Module:  
Target Oven W.O#: 43104-2 
Heat Shield W.O#: 45235-12 
Status: In progress 
Subject: New anode routed FEBIAD Test - 3 

Thermocouples installed (X):

O - O

O - Anode

O - X

O - X

O - O

Same set up as test 2 other than a proper gas line connection was made.

Friday, December 16, 2022, 10:29: Roughing.

Friday, December 16, 2022, 14:46: TP1B on. 

Friday, December 16, 2022, 14:52: TP1A on.

Friday, December 16, 2022, 14:59: IG1 on. Vacuum @ 2.58e-05T & dropping.

 

 