Message ID: 965     Entry time: Friday, May 05, 2023, 06:49
Author: Aaron Schmidt 
Target/No.#: TiC#6 
Source: HP-FEBIAD 
Station: ITW 
Module: TM2 
Target Oven W.O#: 44692-10 
Heat Shield W.O#: 45235-12 
Status: In progress 
Subject: Conditioning TiC#6 

Ceramic elbow installed on the anode.

Friday, May 05, 2023, 06:47: Roughing.

Friday, May 05, 2023, 07:24: TP1B on.

Friday, May 05, 2023, 07:34: TP1A on.

Friday, May 05, 2023, 07:43: IG1 on.

Friday, May 05, 2023, 12:12: Vacuum @ 6.91e-06T. FS#5 opened. Vacuum stable.

Friday, May 05, 2023, 12:16: Power/sources on. Gases set

Friday, May 05, 2023, 12:19: Optics on / set.

Friday, May 05, 2023, 12:21: Quick System ready check - OK. Manually set. 

TGHT / TBHT @ 5 / 5 A

BIAS / EE / EZL @ 1 / -0.5 / 1 kV

Anode @ 100 V - 7.326mA

Coil @ 10 A.

Friday, May 05, 2023, 12:23: Ready for operation. All sources back to 0 A / 0 V. Optics remain. Vacuum continues down @ 6.70e-06T.


Monday, May 08, 2023, 08:21: IV4 open.

Monday, May 08, 2023, 08:25: Tap up Anode in steps @ 20 v per 20 seconds.

Anode @ 100 V = 4.884 mA

Anode @ 200 V = 6.105 mA

Anode @ 300 V = 7.326 mA

Anode @ 400 V = 7.326 mA  

Monday, May 08, 2023, 08:42: Anode tapped down to 20 V. 

Monday, May 08, 2023, 08:52: Coil tapped up to 70 A @ 7 A per minute. 

Monday, May 08, 2023, 09:12: Coil tapped back down to 0 A @ 7 A per minute.  

Monday, May 08, 2023, 09:15: Auto-ramping TGHT / TBHT to 580 / 290 A @ 2 / 1 A per min.  

Monday, May 08, 2023, 09:20: BIAS / EE / EZL set to 10 / -1.0 / 5 kV. 

Monday, May 08, 2023, 14:37: TGHT / TBHT @ 580 / 290 A. BIAS / EE / EZL set to 30 / -1.5 / 13 kV. 

Monday, May 08, 2023, 14:38: Anode tapped up to 100 V @ 20 V per 20 seconds. Begin mass & wire scans.  

Monday, May 08, 2023, 15:01: Mass & wire scans complete. 

Monday, May 08, 2023, 18:59: Tap up Anode in steps @ 20 v per 20 seconds from 100 V.

Anode @ 100 V = 9.768 mA

Anode @ 200 V = 12.210 mA

Anode @ 300 V = 14.652 mA

Monday, May 08, 2023, 19:05: Anode @ 400 V = 17.094 mA

Monday, May 08, 2023, 19:18: Anode tapped down to 20 V. 

Monday, May 08, 2023, 19:24: BIAS / EE / EZL @ 1 / -0.5 / 1 kV 

Monday, May 08, 2023, 19:35: Coil tapped up to 70 A @ 7 A per minute. 

Monday, May 08, 2023, 19:49: Coil tapped back down to 0 A @ 7 A per minute. Vacuum rose to 6.20e-06T @ 70A. Stabilized back down around 2.24e-06T.

Monday, May 08, 2023, 19:53: Auto-cooling @ 1 A per minute. 


Tuesday, May 09, 2023, 06:59: Anode, & HV sources to 0 V. IV4 closed.

Tuesday, May 09, 2023, 07:35: SV5 closed. Power / sources off.

Tuesday, May 09, 2023, 07:38: IG1 off. TP1B & TP1A off.

Tuesday, May 09, 2023, 08:49: Venting.

Attachment 1: TiC#6_Anode_&_Coil_checks.docx  174 kB  Uploaded Monday, May 08, 2023, 10:13