Thursday, July 06, 2023, 16:13: Roughing.

Thursday, July 06, 2023, 16:41: TP1B on.

Thursday, July 06, 2023, 16:47: TP1A on.

Thursday, July 06, 2023, 16:55: TP1A Trip, reset.

Thursday, July 06, 2023, 16:56: IG1 on.

Thursday, July 06, 2023, 16:58: Vacuum @ 1.32e-05T. Waterline FS#5 open.

Thursday, July 06, 2023, 17:02: Power's on. HV Rack is open.


Friday, July 07, 2023, 06:52: Auto-ramping TGHT / TBHT to 350 / 150 A @ 2A per minute. Vacuum at 5.02e-07T

Attempted to open IV4, however it timed out.

Friday, July 07, 2023, 08:25: IV4 reset & opened.

Friday, July 07, 2023, 09:02: HV on.

Friday, July 07, 2023, 09:40: BIAS / EE / BIAS @ 30 / -1.5 / 13 kV. 

Friday, July 07, 2023, 10:10: Auto-ramping TGHT / TBHT to 580 / 230 A @ 2A per minute. Vacuum at 6.34e-07T

Friday, July 07, 2023, 10:28: Optics set. FC0 @ 3.36e-11, set from 1uA to 100 nA.

Friday, July 07, 2023, 10:59: Reduce BIAS to 20 kV due to sparking.  

Friday, July 07, 2023, 12:24: BIAS back to 30 kV. TGHT / TBHT @ 580 / 230 A. FC0 @ 2.52e-09. Vacuum @ 1.32e-06T. Beginning mass & wire scans.

Friday, July 07, 2023, 16:57:  BIAS / EE / BIAS @ 0 kV.

Friday, July 07, 2023, 16:59: Vacuum @1.14e-06T. Auto-cooling @ 2 A per min. 

Attachment 1: Nb#10_Conditioning.docx  462 kB  Uploaded Thursday, July 13, 2023, 08:17