83
|
Friday, May 31, 2013, 16:07 |
Isaac Earle | Repair | Target 1 | Target | Power Supply Fan Failure | Today (May 31, 2013) I was contacted
regarding a burning smell and high temperatures
around the T1/T2 controls racks. Erwin |
|
84
|
Tuesday, June 04, 2013, 13:42 |
Isaac Earle | Repair | Target 1 | Target | T1 and T2 Power Supply Fans Replaced | Replacement of the power supply fans
for the T1 Power Supply, T2 Power Supply,
as well as an additional power supply in |
|
85
|
Friday, August 23, 2013, 10:39 |
Isaac Earle | Repair | Target 1 | Cooling | T1 Cooling Package Inlet Pressure (P1) Sensor | The T1 cooling package inlet pressure
(P1) has been dropping since approximately
May 5, 2013 from the regular operating pressure |
|
87
|
Monday, September 09, 2013, 16:22 |
Isaac Earle | Repair | Target 1 | Cooling | T1 P1 Transducer Replaced | The BL1A tunnel was accessed today
to assess a faulty reading from the T1 cooling
package inlet pressure transducer (T1P1). |
|
89
|
Wednesday, September 25, 2013, 14:05 |
Isaac Earle | Standard Operation | Target 1 | Active Sump | RH Lab Active Sump Level Sensor Inspected | A notification was received that the RH
lab active sump level sensor is due for annual
inspection. The sensor was tested and |
|
90
|
Wednesday, October 23, 2013, 15:30 |
Isaac Earle | Development | Target 1 | Cooling | T1 & T2 High Temp Safety Switch Tested | An end-to-end test was performed
on the new T1 and T2 high temperature safety
switches yesterday during the maintenance |
|
91
|
Tuesday, November 12, 2013, 11:49 |
Isaac Earle | Repair | Target 1 | Target | MH Hot Cell Lab Manipulator Overhaul | Complete overhaul of all manipulators
in the Remote Handling Hot Cell Lab in the
Meson Hall was performed by Peter Dudley |
|
98
|
Friday, January 17, 2014, 10:10 |
Isaac Earle | Standard Operation | Target 1 | Cooling | T1/T2 Cooling Packages & Air Amplifier Shut Off | In preparation for Edi to vent the
BL1A vacuum volume, the T1 and T2 cooling
packages were both shut off. They will |
|
99
|
Friday, January 17, 2014, 15:41 |
Isaac Earle | Standard Operation | Target 1 | Target | Water Purged from T1 & T2 Targets | Water was purged from the T1 and T2 targets
using compressed air. The water is
stored in a labeled bucket on the BL1A blocks |
|
102
|
Thursday, February 06, 2014, 17:05 |
Isaac Earle | Standard Operation | Target 1 | Cooling | T1 & T2 Cooling Package Filters Changed | Water was drained from the T1 and T2 cooling
packages, samples taken, and delivered to
RPG. |
|
112
|
Thursday, April 03, 2014, 16:35 |
Isaac Earle | Standard Operation | Target 1 | Cooling | T1 Cooling Package Started | The T1 cooling package was started
around 2pm today. There was no change
to the T1 volume vacuum during startup. |
|
118
|
Wednesday, July 02, 2014, 16:56 |
Isaac Earle | Repair | Target 1 | Cooling | T1-P2 and T2-P1 pressure transducers replaced. | The T1-P2 (outlet) pressure transducer
was replaced to address an erroneous signal.
The XTPAGE value now reads as expected. |
|
120
|
Wednesday, August 13, 2014, 16:34 |
Isaac Earle | Repair | Target 1 | Other | Amplified Air Leak Narrowed Down to T1 Area | During the maintenance day today,
amplified air to the T1 area was valved off
in an attempt to pin point the location of |
|
125
|
Friday, November 14, 2014, 17:30 |
Isaac Earle | Repair | Target 1 | Target | T1-MK1 Target Failure / T1 Target Swap | -
On Nov 13 at ~1am the BL1A vacuum went bad.
The T1 and T2 volumes were isolated |
|
126
|
Monday, November 17, 2014, 10:14 |
Isaac Earle | Development | Target 1 | Active Sump | Filter Installed Downstream of RH HC Lab Active Sump | A filter housing and filter were installed
by Dan McDonald on November 14 in the piping
section between the Remote Handling Hot Cell |
|
127
|
Monday, November 17, 2014, 10:25 |
Isaac Earle | Repair | Target 1 | Other | Amplified Air Leak In T1 Area Repaired | While the 1A blocks over the T1 area were
removed last week the opportunity was used
to investigate an air leak on the amplified |
|
128
|
Tuesday, November 18, 2014, 10:52 |
Isaac Earle | Standard Operation | Target 1 | Active Sump | RH Hot Cell Lab Active Sump Released | Release of the Remote Handling Hot
Cell Lab active sump water was completed |
|
129
|
Tuesday, December 09, 2014, 14:45 |
Isaac Earle | Repair | Target 1 | Target | T1-MK1 Repair Status (Pos'n 1 Plug Leak) | Between Nov 14 ~ Dec 9 the following
activities took place:
- The leaky 10mm Be target at pos'n |
|
134
|
Monday, January 12, 2015, 16:35 |
Isaac Earle | Standard Operation | Target 1 | Cooling | T1 & T2 MRO Status | The following tasks have been performed
at T1:
- T1 monolith painted using grey |
|
135
|
Wednesday, January 14, 2015, 13:32 |
Isaac Earle | Standard Operation | Target 1 | Target | T1-MK2 Moved from B/L to Storage Pit | The T1-MK2 target was transferred from
the beam line to the storage pit in hole
#5 using the transfer flask. A maximum |
|