ID Date Author Category Typedown Specific Subject Text Attachments
  136   Wednesday, January 14, 2015, 15:06 Isaac EarleStandard OperationTarget 1OtherActive Item Stored in East Hot CellThe active item discovered on January 9,
2015 outside the BL1A bootbox has been moved
to the Meson Hall east hot cell for storage.
  
  138   Tuesday, January 27, 2015, 17:38 Isaac EarleRepairTarget 1CoolingT1 Cooling Package 3/4" Valves Rebuilt - T1 MRO Complete- Both 3/4" ball valves on the T1
cooling package target water circuit were
rebuilt, leak tested with house air pressure,
  
  140   Friday, February 06, 2015, 12:39 Isaac EarleRepairTarget 1TargetT1-MK1 Repair Status (Pos'n 1 Plug Leak) The T1-MK1 target is currently in
the hot cell for repair of a leak at position
1.  See E-Log #129 for details on previous
 IMG_4603.JPG 
  141   Wednesday, February 18, 2015, 14:49 Isaac EarleRepairTarget 1TargetT1-MK1 Repair CompleteThis is a continuation of work detailed
in E-Log #129 and #140.
- Static water test performed on
 IMG_4638.JPGIMG_4646.JPGIMG_4647.JPG 
  143   Friday, February 27, 2015, 18:06 Isaac EarleDevelopmentTarget 1TargetT1 Rotary Collimator Water and Air Line Investigation Ron Kuramoto, Keith Ng, John McKinnon,
and myself spent some time today investigating
water and air lines related to the T1 Rotary
  
  149   Tuesday, April 21, 2015, 12:59 Isaac EarleStandard OperationTarget 1TargetT1-MK2 target moved from storage pit to beam line The T1-MK2 target was transported
from the storage pit to the beamline.  The
target measured approximately 10mSv/hr at
  
  150   Tuesday, April 21, 2015, 13:38 Isaac EarleStandard OperationTarget 1TargetAir Amplifier Started. T1 & T2 Profile Monitor Actuation Checked The lower air amplifier has been
started, and air supplied to the T1 and T2
areas by opening the appropriate ball valves
  
  151   Wednesday, April 22, 2015, 09:46 Isaac EarleDevelopmentTarget 1TargetWater Sensors Installed on T1 Monolith Four water sensors have been installed
on top of the T1 monolith.  These water
sensors were wired and brought to the area
 T1_Water_Sensors.jpgIMG_4859.JPGIMG_4860.JPG 
  152   Wednesday, April 22, 2015, 15:15 Isaac EarleStandard OperationTarget 1CoolingT1 and T2 Cooling Packages ReadyBoth cooling packages are running steadily
with the targets in Position 0.  
The demin flow (Q2) for both was
  
  153   Wednesday, April 22, 2015, 15:17 Isaac EarleDevelopmentTarget 1TargetT1-MK2 wired for version identification The T1-MK2 target was wired for automatic
target version detection by the new PLC control
system (A to C jumper  in POT/CAM MS
  
  155   Thursday, April 23, 2015, 16:29 Isaac EarleStandard OperationTarget 1TargetT1 & T2 Profile and Protect Monitors Electrical Check CompletedAn electrical check has been completed
for the T1 & T2 Profile and Protect Monitors
by Dave Cameron and Mike Russell.  They
  
  157   Tuesday, April 28, 2015, 15:55 Isaac EarleDevelopmentTarget 1TargetTarget Version Jumper Wires Installed for T1-MK1 and T2-MK1 The T1-MK1 and T2-MK1 targets have
been re-wired to allow version identification.
 Work was performed in the target storage
  
  158   Friday, May 01, 2015, 16:01 Isaac EarleRepairTarget 1OtherRH Warm Cell Used by Beamlines Group for TNF Heat Exchanger Leak CheckThe Meson Hall RH Lab Warm Cell was used
by Beamlines Group for hydrostatic testing
of the TNF heat exchanger.  The location
 IMG_1510.JPGIMG_1511.JPGIMG_1512.JPG 
  160   Tuesday, May 12, 2015, 21:20 Grant MinorStandard OperationTarget 1TargetT1 & T2 Targets moved from pos. 0 to pos. 4Grant moved the T1 and T2 targets from
position 0 to position 4 this evening at
around 9pm.
  
  161   Monday, May 25, 2015, 12:48 Isaac EarleRepairTarget 1ControlsT1/T2 Controls System CrashAt 9:15am this morning BL1A tripped off
due to loss of the watchdog signals for the
T1/T2 control system.  Graham Waters
  
  165   Wednesday, July 08, 2015, 16:21 Isaac EarleDevelopmentTarget 1Target0.003" 347 SS Sheet for T1/T2 Targets Received A 5lb roll of 347SS sheet was received
today.  This alloy is to be used for
the target windows of the new T1 and T2 beryllium
 347SS_Mill_Spec_Test_Report_-_July_8_2015.pdf 
  167   Wednesday, July 15, 2015, 10:33 Isaac EarleStandard OperationTarget 1CoolingT1 & T2 Cooling System Check- All T1 and T2 values on XTPAGE were stripped
back to April 1, 2015:  All systems
appear to be functioning normally, nothing
  
  168   Friday, July 17, 2015, 10:14 Isaac EarleDevelopmentTarget 1TargetT1/T2 Be Target Failure History & Replacement PlanT1 and T2 beryllium target failure history
was investigated back to 2000 (as far as
XSTRIP records were readily available).  For
 T1_and_T2_Be_Target_History_-_July_17_2015.pdf 
  176   Friday, October 02, 2015, 17:25 Ron KuramotoStandard OperationTarget 1TargetRaise Target to lower Rad levels for 1AM7 repairToday the T1MK2 target was moved from Position
4 to Position 0 to lower the Rad fields for
the 1AM7 repair in the 1A Tunnel. The Rad
  
  181   Friday, October 09, 2015, 15:52 Isaac EarleRepairTarget 1TargetT1-MK2 Protect Monitor Replacement and InspectionWhen the damage to the T2 Protect Monitor
was found to be caused by flying debris from
a vacuum spike (see e-log #179), it was decided
 12x 