ID Date Author Category Typedown Specific Subject Text Attachments
  51   Tuesday, July 17, 2012, 15:30 Isaac EarleDevelopmentTarget 1CoolingT1 & T2 Expansion Tank Level Warnings Added Mike Mouat and Juan Pon have modified
the control system so that the control room
will receive a message when the warning or
  
  52   Monday, July 23, 2012, 16:01 Isaac EarleDevelopmentTarget 1TargetTarget Flask Seismic Restraint Clamps Installed Installation of the seismic restraint
clamps has been completed for the MK1 and
MK2 target flasks in the Remote Handling
 IMG_0427.JPGIMG_0428.JPGIMG_0429.JPG 
  53   Friday, July 27, 2012, 14:48 Isaac EarleRepairTarget 1TargetT1-MK1 Target Repair Update- T1MK1 target transferred from storage
pit to hot cell (max field: 4700 
  
  54   Wednesday, August 08, 2012, 14:40 Isaac EarleRepairTarget 1TargetT1-MK1 Target Repair Complete- Re-wired profile monitor was received
from Probes Group and installed on the target
  
  56   Friday, September 07, 2012, 16:39 Isaac EarleRepairTarget 1TargetRH Lab Crane Repaired The "west" button on the
crane pendant was broken, and the crane would
occasionally continue moving west when the
  
  57   Thursday, September 13, 2012, 18:09 Isaac EarleMaintenanceTarget 1CoolingSeptember Shutdown T1 & T2 MRO The following tasks were performed
during the 2012 September Shutdown:
- Both targets moved to position
 IMG_0624.JPGIMG_0658.JPG 
  58   Tuesday, September 25, 2012, 16:31 Isaac EarleRepairTarget 1TargetT1/T2 Controls - The target control software was
modified to reference the correct pot. look-up
table for the target at T1 (T1-MK1)
  
  59   Friday, September 28, 2012, 15:19 Isaac EarleRepairTarget 1TargetT1-MK2 Delta Seal Leak  After removal of the leaky
target cassette at position 3, plugs were
installed on the target ladder and a leak
  
  60   Wednesday, October 24, 2012, 17:34 Isaac EarleRepairTarget 1TargetT1-MK2 Target Repair CompleteThe target ladder was detached, old delta
seals removed, sealing surfaces cleaned using
scotchbrite pad and a dremel tool, and delta
  
  62   Tuesday, November 13, 2012, 16:26 Isaac EarleRepairTarget 1TargetManipulator Repair Complete Repair of the west side manipulator
in the west hot cell was completed today.
 Part of the repair was done by entering
  
  63   Thursday, November 22, 2012, 17:22 Isaac EarleStandard OperationTarget 1Active SumpRH Lab Active Sump Released On Wednesday November 21 at approximately
9am the level of the Remote Handling active
sump was inspected and found to be at approximately
  
  64   Monday, December 10, 2012, 15:42 Isaac EarleMaintenanceTarget 1TargetT1-MK2 Target Maintenance- T1-MK2 target moved from storage pit
to hot cell
- Removed unused proximity sensor
  
  67   Friday, January 11, 2013, 15:48 Isaac EarleStandard OperationTarget 1TargetBL1A Tunnel Accessed The BL1A tunnel was accessed to drain
and sample T2 cooling package water.  A
puddle of water was noticed in the South
 IMG_0801.JPGIMG_0802.JPG 
  75   Tuesday, March 26, 2013, 10:55 Isaac EarleMaintenanceTarget 1TargetT1-MK1 Re-wiring and MRO Complete The following work was performed
on the T1-MK1 target:
- Unused proximity sensor removed
 T1-MK1_Tgt_leak_check.PDF 
  76   Tuesday, April 09, 2013, 17:06 Isaac EarleRepairTarget 1TargetT1 Target Electronics CheckThe T1-MK1 target protect and profile monitor
electronics were 'blip' tested by Bill Rawnsley
on April 5, 2013.  The response from
  
  77   Friday, April 12, 2013, 13:28 Isaac EarleStandard OperationTarget 1CoolingCooling Packages Leak Tight The T1 and T2 expansion tanks were
filled on Monday April 8th.  There was
no change in the level when inspected today
  
  78   Friday, April 12, 2013, 17:33 Isaac EarleDevelopmentTarget 1CoolingT1 & T2 high-temp limit switch installation, wiring, and commissioning completeInstallation, wiring, and commissioning
of the high temperature limit switches for
the T1 and T2 cooling packages was completed
  
  80   Wednesday, April 17, 2013, 16:45 Isaac EarleStandard OperationTarget 1TargetT1-MK1 Target Leak Checked The T1-MK1 target was leak checked
on April 15th at the T1 monolith by Ron Kuramoto
and Edi Dalla Valle.  No leaks were
  
  81   Friday, April 19, 2013, 09:55 Isaac EarleDevelopmentTarget 1CoolingT1&T2 cooling package safety/standards compliance upgrade complete (SASP0120)Yesterday (April 18th) the T1 and T2 cooling
package PRV outlet lines were routed to the
active drain in the 1A tunnel.  All
  
  82   Tuesday, May 14, 2013, 13:26 Isaac EarleDevelopmentTarget 1TargetT1 & T2 Profile ScanThe T1 and T2 profile monitors were used
during today's development shift.  Target
ladder movement for T1 was done at the panel
  