  Test-Stand, Page 7 of 53  Not logged in ELOG logo
ID Date Author Target/No.# Source Station Moduledown Target Oven W.O# Heat Shield W.O# Status Subject Text Attachments
  596   Monday, July 10, 2017, 13:27 Aaron SchmidtTa#53HP-SISITWTM242218-641751-6In progressConditioning Ta#53Monday, July 10, 2017, 14:03: Roughing.
Monday, July 10, 2017, 14:27: Turbo
pumps started.
 7x 
  605   Wednesday, September 20, 2017, 14:11 Aaron SchmidtTa#54HP-SISITWTM242218-10 In progressConditioning Ta#54Wednesday, September 20, 2017, 14:08: Roughing.
Wednesday, September 20, 2017, 14:28:
Turbos on.
 6x 
  649   Friday, March 16, 2018, 08:15 Aaron SchmidtNb#8HP-SISITWTM238817-242738-12In progressConditioning Nb#08Friday, March 16, 2018, 08:42: Roughing.
Friday, March 16, 2018, 10:34: Turbo
pumps started.
 6x 
  664   Monday, May 28, 2018, 08:46 Aaron Schmidt LP-FEBIAD TM241790-942752-5In progressNew TM source tray swap out. Monday, May 28, 2018, 08:45: Venting. Prep
For removal.
Close FS#8. Clean up water
 New_TM_Source_Tray_2018.docxTS-2018-05-30-06-30.rgaER-580-310-30kV-m28.txtER-580-320-30kV-M39.txt2018_TM2_Source_Tray_in_Test_Stand_-_Test_Results.docx 
  675   Monday, July 23, 2018, 14:25 Aaron SchmidtUC#23LP-FEBIAD-CTLITETM2  In progressConditioning Heat Shield for UC#23Monday, July 23, 2018, 14:20: Roughing.
Monday, July 23, 2018, 14:54: Turbo
pumps on. 
 UC#23_emit.dat_error.docxTS-2018-07-2-08-07.rgaTS-2018-07-24-07-20.rgaUC#23.docx 
  683   Friday, August 31, 2018, 12:27 Aaron SchmidtnSiC#1LP-SISITWTM243044-142752-4In progressConditioning nSiC#1Friday, August 31, 2018, 12:27: Roughing.
Friday, August 31, 2018, 13:19: Turbo
pumps started.
 15x 
  685   Monday, September 17, 2018, 11:52 Aaron SchmidtUC#25LP-SISITWTM2 42752-9In progressConditioning Heat Shield for UC#25Monday, September 17, 2018, 11:47: Roughing*.
Doors not sealing, help acq'd 
Monday, September 17, 2018, 11:51:
 OMEGA_OM-DAQPRO-5300_24-Sep-18_08.08.26.dlpTS-2018-09-17-14-10.rgaUC#25.docx 
  719   Friday, April 26, 2019, 13:45 Aaron SchmidtTa#58LP-SISITETM243044-442972-7In progressConditioning Ta#58 HSFriday, April 26, 2019, 13:43: Roughing.
Friday, April 26, 2019, 14:12: Turbo
pumps on.
 7x 
  721   Tuesday, May 07, 2019, 13:16 Aaron SchmidtTa#58LP-SISITETM243044-4 In progress9-pin connection configuration (Using Ta#58)Ref:
https://elog.triumf.ca/TIS/Test-Stand/679
Pin configuration between top 9-pin
 HV_Tests_2019_-_AL_-_1.docxTS-2019-05-08-08-12.rgaTS-2019-05-08-14-20.rga 
  722   Tuesday, May 14, 2019, 10:22 Aaron SchmidtZrC#8LP-SISITETM243044-542972-3In progressConditioning ZrC#8 HSTuesday, May 14, 2019, 10:21: Roughing
Tuesday, May 14, 2019, 10:51: Turbo
pumps on.
 ZrC#8.docxTS-2019-05-14-11-05.rgaTS-2019-05-16-07-30.rgaTS-2019-05-21-07-10.rgaITE-TM2-ZrC#8-LP-SIS_Test_Stand.docx 
  748   Sunday, July 28, 2019, 14:22 Luca EgoritiP2N - 1HP-FEBIADITETM2p2n - test1p2n - test1Problems/Solutionsp2n heating test 3Friday. July 26th 2019 
A new electrical configuration of
the test stand was decided and installed.
 20190728_-_p2n_heating_3.PNG 
  749   Tuesday, July 30, 2019, 12:19 Luca EgoritiP2N - 1HP-FEBIADITETM2  Problems/Solutionsp2n heating test - target inspectionThe p2n target was taken out of the test
stand for inspection. Comments and measurements
on the container below:
 IMG_20190730_110927.jpgIMG_20190730_113437.jpgIMG_20190730_105629.jpg 
  751   Wednesday, August 07, 2019, 08:18 Luca EgoritiP2N - 1 ITETM2  Problems/Solutionsp2n heating test 4Tuesday, August 06, 2019, 16:00
Start ramp up to 300+300 = 600 A
 
 IMG_20190806_182939.jpgIMG_20190806_182953.jpg 
  758   Monday, September 23, 2019, 13:30 Aaron SchmidtTa#59LP-SISITETM244062-542752-10In progressConditioning Ta#59 AssyMonday, September 23, 2019, 13:28: Roughing.
Monday, September 23, 2019, 13:38:
Closed BV1A / Opened BV1 A & B to open
 9x 
  762   Friday, October 18, 2019, 15:01 Aaron SchmidtSiC#38HP-FEBIADITETM242464-442752-1In progressConditioning SiC#38 HP-FEBIADFriday, October 18, 2019, 14:58: Roughing.
Friday, October 18, 2019, 15:30:
Turbo pumps on.
 12x 
  790   Tuesday, March 17, 2020, 11:40 Aaron SchmidtSiC#40HP-SISITWTM242218-843515-8In progressConditioning SiC#40Tuesday, March 17, 2020, 11:37: Roughing.
FS# 3 re-connected. All waterlines
re-opened except FS#5 (HS cooling).
 SiC#40_-_Conditioning.docxER-580-230-30kV-m7.txtER-580-230-30kV-m23.txtER-580-230-30kV-m38.txtITW-TM2-SiC#40-HP-SIS_Test_Stand.docx 
  794   Wednesday, June 10, 2020, 08:23 Aaron SchmidtC#1LP-SISITWTM243044-843515-3In progressConditioning C#1Salts: 
Li - 10 uL
Na - 10 uL
 7x 
  795   Tuesday, June 16, 2020, 11:03 Aaron SchmidtTa#60LP-SISITWTM244139-1343515-5In progressConditioning Ta#60 Tuesday, June 16, 2020, 11:01: Turbo pumps
on.

Wednesday, June 17, 2020,
 Ta#60_Conditioning.docxITW-TM2-Ta#60-LP-SIS_Test_Stand.docxER-580-230-30kV-m8.txtER-580-230-30kV-m40.txt 
  814   Wednesday, September 30, 2020, 06:23 Aaron SchmidtC#2LP-SISITWTM244139-943515-2In progressConditioning C#2Wednesday, September 30, 2020, 06:14: Power
/ sources on.
Wednesday, September 30, 2020, 06:17:
 C#2_-_Short_-_EZL.docxC#2_Conditioning.docxITW-TM2-C#2-LP-SIS_Test_Stand.docx 
  817   Tuesday, October 27, 2020, 08:54 Aaron SchmidtNb#9 LP-SISITWTM244508-243515-4In progressNb#9 ConditioningTuesday, October 27, 2020, 08:40: Roughing.
Tuesday, October 27, 2020, 09:13:
TP1B on.
 Nb#9_Conditioning.docxER-580-230-30kV-M133.txtER-580-230-30kV-M23.txt 