ID Date Author Category Type Specific Subject Text Attachments
  278   Thursday, March 10, 2022, 13:57 Adam NewsomeMaintenanceTarget 1CoolingChanged paddle wheel, o-ring, and shaft in flow sensors at T1 cooling packageThe paddle wheels, o-rings, and shafts
were changed at the T1 cooling package for
the following sensors:
  
  277   Thursday, March 10, 2022, 11:18 Adam NewsomeMaintenanceTarget 2CoolingChanged paddle wheel, o-ring, and shaft in flow sensors at T2 cooling packageThe paddle wheels, o-rings, and shafts
were changed at the T2 cooling package for
the following sensors:
 PXL_20220310_173802512.jpgPXL_20220310_173759444.jpg 
  276   Thursday, February 17, 2022, 13:03 Matthew GareauMaintenanceTarget 1TargetT1 MK2 wire scanner and protect monitor test removal and reattachment with pin straightening this Work was done on 09 Dec 2021.
Since Isaac Earle was leaving Triumf
he was giving us (maico, chad, adam, and
 IMG_20211207_140443.jpgIMG_20211207_140508.jpgIMG_20211207_140735.jpgIMG_20211207_122631.jpgIMG_20211207_142836.jpg 
  275   Wednesday, April 14, 2021, 14:30 Isaac EarleStandard OperationOtherActive SumpRH Lab Active Sump pumped out The RH Lab Active Sump reached the
high level sensor at some point overnight
before the April 8th work day.  Maico
  
  274   Friday, April 09, 2021, 12:42 Matthew GareauMaintenanceTarget 2CoolingChanged the paddle wheel, o ring, and shaft in the Collimator A flow meter at the T2 packageWith the assistance of Maico we changed
the paddle wheel, o ring, and shaft in the
Collimator A flow meter (Q4) at the T2 package.
  
  273   Wednesday, March 31, 2021, 16:15 Matthew GareauStandard OperationTarget 1TargetT1-MK1 target exchange March 29 Monday
- moved T1-MK1 target from beamline
to hotcell  (field from target 15mSv/hr
 IMG_20210330_140744.jpgIMG_20210330_141059.jpgIMG_20210330_141455.jpgT1-MK1_-_2021.pdf 
  272   Wednesday, February 17, 2021, 10:39 Isaac EarleDevelopmentOtherUCNUCN Target Cask TestingA trial run of remote removal of the UCN
target was performed using the shielded target
cask (TTA0335) developed in 2020.  The
 8x 
  271   Tuesday, November 24, 2020, 15:10 Isaac EarleStandard OperationTarget 2TargetAdditional targets added to T2-MK1 ladder The following work on the T2-MK1
target was completed sporadically over the
last few months:
  
  270   Tuesday, October 27, 2020, 14:01 Isaac EarleRepairTarget 2CoolingT2 Collimator flow meter paddle wheel replacedThe T2 Collimator A flow meter signal (B1A:T2:FGCOLA)
began fluctuating and occasionally reading
0gpm on Sunday Oct 25 causing BL1A trips
  
  269   Wednesday, August 19, 2020, 12:57 Isaac EarleMaintenanceTarget 1CoolingT1/T2 MRO summary for 2020 shutdownThe following work was completed during
the 2020 shutdown period for BL1A (Jan-Aug
2020):
  
  268   Thursday, July 09, 2020, 06:44 Isaac EarleDevelopmentOtherM9Alignment of M9 Q1Q2 magnets complete Mike Vogel reported that alignment
of the Q1Q2 assembly w.r.t. the T2 and B1
flanges was completed on July 7.  This
  
  267   Tuesday, July 07, 2020, 15:13 Isaac EarleDevelopmentOtherM9M9 Q1Q2 service stand Lemo connector wiringThe diagram below shows the wiring for
the two connectors on the service stand (the
wires running from the stand to the power
 Lemo_pin_wiring.PNG 
  266   Tuesday, July 07, 2020, 13:22 Isaac EarleDevelopmentOtherM9M9 Q1Q2 The M9 Q1Q2 magnet assembly lift
beam has been installed according to drawing
TB23401.  The side-to-side as well as
 8.jpg1.jpg4.jpg6.jpg 
  265   Friday, June 12, 2020, 13:54 Isaac EarleDevelopmentOtherM9M9 Q1Q2 water header installedThe Q1Q2 water header (TB23481) was mounted
this morning as per installation drawing
TB23400.
 2.jpg1.jpg 
  264   Wednesday, June 10, 2020, 08:58 Isaac EarleDevelopmentOtherM9T2-M9 and M9-B1 flange scan data Laser tracker scan data from 2017
and 2019 attached as a backup.  Original
files from Beamlines Group who also keep
 2017-03-28_meson_hall_t2_with_import_of_2015_data.xit642019-25-01_meson_hall_t2_data.xit64 
  263   Tuesday, June 09, 2020, 17:01 Isaac EarleDevelopmentOtherM9Cables and helium leak check line installed to M9 service stand The 10-pin thermal switch wire, 2-pin
steering wire for Q2, and a 1/4" copper
tube for remote helium leak check were installed
  
  262   Monday, April 06, 2020, 15:02 Isaac EarleStandard OperationTarget 2M9M9 beam blocker returned to beamlineThe M9 beam blocker was returned to the
beamline today using the RH shielded transport
flask.  The top flange o-ring was replaced
  
  261   Monday, March 23, 2020, 16:13 Isaac EarleMaintenanceOtherOtherM9 beam blocker MRO completedM9 beam blocker MRO work was completed
in the hot cell today.  This included
replacement of the main shaft seals and replacement
  
  260   Wednesday, March 11, 2020, 10:29 Isaac EarleDevelopmentOtherM9M9 Q1Q2 service stand foot plate installed The M9 Q1Q2 "foot" plate
(TB23363) has been installed over the floor
plate.  A nominal gap between the plates
  
  259   Wednesday, March 04, 2020, 13:42 Ron KuramotoRepairOtherOtherB/L 1A vacuum air leak repair A 4” Marmon aluminum blank-off
flange and o-ring were replaced on the south
port of the T1 target monolith vacuum vessel. This
 1AT1_Vacuum_Leak_Repair-Feb2020.pdf 