  2420   Wednesday, March 01, 2023, 09:34 David WangCoolingMaintenance  Visual inspection of HALCW for possible small water leak or drip. I visually inspected HALCW system including
water station section, both target pits,
and de-ionizer system.  No small leak
  
  2424   Wednesday, March 08, 2023, 06:32 David WangCoolingMaintenance  HALCW flow sensors replacement. HALCW flow sensors replacement job is done.
All ITE/ITW(except ITE HS) return line water
flow sensors including paddle wheels and
  
  2432   Tuesday, April 18, 2023, 07:28 chad fisherNorth Hot-CellMaintenance  NHC entry summaryNHC was entered on April 17, 2023 for inspection
and maintenance. Summary :
Compressible and non-compressible
  
  2433   Monday, April 24, 2023, 10:18 David WangCoolingMaintenance  HALCW flowmeter transmotters inspetion and calibration. ITW, ITE, ITW +ITE total , and low active
cooling water return flow meter transmitters
are inspected and calibrated.  Result:
  
  2436   Wednesday, May 03, 2023, 11:04 Adam NewsomeCraneMaintenance  Pail Handling Tool - Annual InspectionThe pail handling tool which is used to
move 5 gallon pails around the target hall
was inspected by A. Newsome, N. Jorgenson,
 PXL_20230503_172503014.jpgPXL_20230503_172457837.jpgPXL_20230503_172454009.jpg 
  2446   Thursday, May 25, 2023, 13:10 David WangConditioning StationMaintenanceTM2 TCS MP1 is replaced due to poor performace. TCS MP1 is replaced due to poor performance(
system shows unstable and high reading on
TCSCG1A and high TP1,TP2 current draw) .
  
  2452   Tuesday, June 06, 2023, 15:10 Antoniette YapSpent Target VaultMaintenance   Annual Inspection of Main and Mini Storage VaultsThe annual inspection of the mini-storage
vault and main storage vault was completed
June 23, 2023. The following items were checked:
  
  2462   Wednesday, June 21, 2023, 14:39 Adam NewsomeSafe Module ParkingMaintenance  Annual electrical and mechanical inspection of Safe Module ParkingAn annual electrical and mechanical inspection
was performed on the  SMP today by Adam Newsome,
Travis Cave, Eric Lahe, Maico Dalla Valle,
 PXL_20230621_210144119.MP.jpgPXL_20230621_210546559.jpgPXL_20230621_210146892.jpg 
  2468   Friday, July 28, 2023, 10:09 Adam NewsomeSpent Target VaultMaintenance  Main Storage Vault: Bearing LubricationBearings for the main storage vault door
were lubricated on 2023-07-28. It is unknown
when this was last done. It is suggested
  
  2469   Friday, July 28, 2023, 10:21 Adam NewsomeSpent Target VaultMaintenance  Mini Storage Vault: Bearing LubricationThe bearings on the mini storage vault
were lubricated. It is suspected that this
has never been done. It is suggested that
 PXL_20230728_162515733.jpg 
  2495   Friday, October 13, 2023, 11:46 David WangCoolingMaintenance  HALCW system O2 sensor service and calibration.HALCW system O2 sensor service and calibration
were done in Sep 26th. electrolyte and membrane
on rose mount sensor 499ADO were refilled
  
  2496   Friday, October 13, 2023, 11:51 David WangITE/ITWMaintenance  ITH:MP1 is replaced due to its poor performance. ITH:MP1 is replaced this morning due to
its poor performance started yesterday afternoon.
The general field in pit is about 260usv/hr.
  
  2502   Friday, November 17, 2023, 11:28 Adam NewsomeSpent Target VaultMaintenance  Storage vault: issue observed with door openingDuring operation today, it was observed
that the main vault door had issues opening..
typically when the door was around 80-90%
 PXL_20231117_200245076.jpgPXL_20231124_210005281.jpg 
  2503   Monday, November 20, 2023, 12:28 Eric LaheSouth Hot-CellMaintenance  Light Bulb Replacement - South Hot Cell roof lights 3 light bulbs replaced in the ISAC
South Hot Cell - North West light, South
west light, and South East light bulbs. Northeast
  
  2506   Monday, November 27, 2023, 12:01 chad fisherSouth Hot-CellMaintenance  Manipulator tong cable and wrist replacementBroken tong cable on SW manipulator (serial
#8106) of SHC was replaced today. 
Following ISAC Hot Cell entry procedure,
  
  2538   Tuesday, February 06, 2024, 13:28 David WangITWMaintenance  ITW exit 1 module has been disconnected and reconnected for o ring replacementITW exit 1 module was disconnected 
for Exit module flange o -ring replacement
yesterday. After oring replacement, the module
  
  2539   Tuesday, February 06, 2024, 13:36 David WangITWMaintenance  ITW exit 1 module tank flange o ring has been replaced. ITW exit 1 module tank flange o ring has
been replaced. the old o r-ing was completely
flat in slot without elastic property. 
  
  2541   Monday, February 12, 2024, 18:44 Carla BabcockITWMaintenance  ITW annual HV testingITW was set up for HV testing - water is
running and at a high resistivity due to
injected N. Einzel lens is attached to ground.
 Screenshot_from_2024-02-12_18-44-03.png 
  2547   Friday, February 16, 2024, 11:48 David WangCoolingMaintenance  high active water transferr to holding tank100 liters of high active water from HALCW
system( mostly from s-tank and pipe lines
closing to pumps) are transferred to holding
  
  2548   Friday, February 23, 2024, 06:36 David WangITEMaintenance  ITE entrance module has been disconnected.ITE entrance module has been disconnected
per document 190510. Its a preparation job
for next month module moving out to SHC.
  