2211
|
Wednesday, April 21, 2021, 11:18 |
David Wang | Cooling | Maintenance | | | Refilling high active wtaer system and starting HA water pumps. | High active water system is refilled. Air
are drained out of system before pump
to be started. Following sequence are used |
|
2215
|
Monday, May 03, 2021, 15:14 |
Frank Song | ITE | Maintenance | | | High voltage test in ITE | Anders and I prepared ITE high voltage
test in April 30 ( Friday morning), The MAA
is locked for this. |
|
2218
|
Tuesday, May 25, 2021, 16:20 |
Anders Mjos | Conditioning Station | Maintenance | | | Chiller maintenance | A contractor on site today for chiller
maintenance. CP2 and CP3 circuit is leaking
and shall not be used. CP1 can still be used. |
|
2219
|
Tuesday, May 25, 2021, 16:20 |
Anders Mjos | Conditioning Station | Maintenance | | | TK2 refilled | Tank refilled from 12 in to 25 in using
the new valve. |
|
2231
|
Wednesday, July 07, 2021, 11:59 |
Adam Newsome | Safe Module Parking | Maintenance | | | Annual Electrical and Mechanical Inspection | An annual electrical and mechanical inspection
was performed on the SMP today by Adam Newsome,
Dan McDonald, and Jason Zhang as per Work |
|
2282
|
Wednesday, January 05, 2022, 09:38 |
Frank Song | ITE | Maintenance | TM4 | Ta #63 | TM4 SIS with Target and No external Connections | electric check done in ITE. |
|
2283
|
Wednesday, January 05, 2022, 12:45 |
Frank Song | ITW | Maintenance | TM2 | UC#36 | TM2 SIS with Target and No external Connections | electrical checked in ITW |
|
2288
|
Tuesday, January 11, 2022, 11:50 |
David Wang | ITW | Maintenance | | | ITW Exit module 1 side sqaure panel O-ing seal replacement. | Frank and I replaced ITW Exit module 1
side square service panel o-ring seal. Also,
The target module pit top flange o-ring seal |
|
2307
|
Thursday, February 17, 2022, 13:24 |
David Wang | Spent Target Vault | Maintenance | | UCx #34 | Repackage of UCx #34in NHC. | UCX34# in pail 258(Vault lot 7C) has been
repacked today. It is an investigation to
find a possible leak source of radioactive |
|
2308
|
Thursday, February 24, 2022, 13:23 |
David Wang | ITE/ITW | Maintenance | | | Polyurethane water cooling lines replacement in ITE and ITW. | Polyurethane water cooling lines
in ITE and ITW HV shroud are replaced.
Both stations Ta, Tu, MSP, HS, Coil , EE |
|
2310
|
Tuesday, March 01, 2022, 11:51 |
David Wang | Spent Target Vault | Maintenance | | | UCx #32 has been repacked in NHC. | UCx 32# P2N target in vault slot 1B is
repacked is morning for Ferran to take out
his samples( in two small plastic containers) |
|
2314
|
Wednesday, April 13, 2022, 11:54 |
Carla Babcock | South Hot-Cell | Maintenance | TM2 | | EZL cable change | Chad changed the EZL cable and plugs on
TM2. New cable runs along the cable trays. |
|
2318
|
Friday, May 06, 2022, 10:12 |
Adam Newsome | Spent Target Vault | Maintenance | | | Annual Inspection of Mini-Storage Vault | The annual inspection of the mini-storage
vault was performed today. The following
items were checked: |
|
2344
|
Monday, July 04, 2022, 11:54 |
Nadia Jorgenson | Spent Target Vault | Maintenance | | | Added Lubrication,fittings need to be changed | Dan lubricated components on the target
storage vault (This was an outstand task
from annual inspection). No issues on the |
|
2369
|
Wednesday, September 28, 2022, 13:15 |
Matthew Gareau | North Hot-Cell | Maintenance | | | topped up the NHC window oil through the oil expansion tank | Myself and Maico were able to top up the
NHC window oil.
The oil was filled through the expansion |
|
2371
|
Monday, October 03, 2022, 14:28 |
Keith C Ng | Assembly/Bench Test | Maintenance | | | ITA2826 rev E assembly | A fully built steerer sub assembly ITA2826
revision E was boxed and sealed and put on
rack storage in ISAC B2 South Hot Cell area. |
|
2391
|
Tuesday, November 22, 2022, 14:53 |
Carla Babcock | North Hot-Cell | Maintenance | TM4 | | Multipin connector alignment pin on TM4 module loose | The pin on TM4 has become loose again,
making it very difficult to remove the multipin
connector with the last target, C#4. For |
|
2406
|
Tuesday, January 24, 2023, 07:21 |
David Wang | ITW | Maintenance | | | ITW pit general clean up. | ITW was cleaned with vacuum
canister in Jan 10th. HV cage inside
and blue nylon insulators were wiped. |
|
2416
|
Monday, February 13, 2023, 09:57 |
David Wang | ITW | Maintenance | | | ITW/ITE primary vacuum back up lines and BVs leak check in target pit. | In past two weeks, ITW/ ITE primary vacuum
back up lines and BVs in ITW/ITE pit have
been leak checked. ITW BV1 and BV2 |
|
2419
|
Wednesday, March 01, 2023, 09:27 |
David Wang | Cooling | Maintenance | | | Two filters on HALCW resin circuit have been replaced. | Two filters on HALCW resin circuit have
been replaced. O-ring 235# were changed on
both filter cartridge houses. 25micron |
|