  1841   Tuesday, December 18, 2018, 11:13 Isaac EarleNorth Hot-CellDevelopment  NHC manipulator slave-end swap, RH test, and various other workThe following
North Hot Cell work was completed over the
last week under work permit I2018-12-12-1:
  
  1847   Friday, January 04, 2019, 14:38 Isaac EarleNorth Hot-CellDevelopment  NHC cameras testedThe NHC module support flange cameras (4
total) as well as the NHCSA camera were tested
today and confirmed to be working properly. 
 NHC_flange_East_and_West_views.JPGNHC_flange_North_and_South_views.JPGCamera_view_through_operator_viewing_window.JPG 
  1857   Friday, January 11, 2019, 13:59 Isaac EarleSafe Module ParkingDevelopment  SMP motor selection decisionSMP drivetrain design work is currently
underway.  Alejandro has selected a
suitable 1200:1 reducer which will give a
  
  1859   Friday, January 18, 2019, 10:26 Isaac EarleNorth Hot-CellDevelopment  NHC sealing improvements and repeat of RH test for LED lightsThe following NHC development work was
completed under WP I2019-01-09-4:

    Location of RH feature
  
  1860   Monday, January 21, 2019, 16:27 Isaac EarleNorth Hot-CellDevelopment  NHC in-cell camera wired to right side monitor The NHC right side monitor has been
wired to display the signal from the in-cell
camera.  This was tested using a snake
 20190121_154407.jpg 
  1864   Thursday, January 31, 2019, 14:16 Isaac EarleNorth Hot-CellDevelopment  NHC grounding approval Franco Mammarella was consulted regarding
electrical grounding of the NHC design (RS103
of Document-131915).  After discussing
 NHC_grounding.pdf 
  1865   Monday, February 11, 2019, 10:26 Isaac EarleSafe Module ParkingDevelopment  SMP shield box and vacuum vessel moved to Target Hall  On February 8th the SMP shield
box (IRH1675) and the vacuum vessel (IRH1806)
were both raised from a horizontal to vertical
 6x 
  1873   Thursday, February 21, 2019, 15:10 Isaac EarleSafe Module ParkingDevelopment  Seismic requirements for SMPDragan Mitrovic, TRIUMF structural engineer,
was consulted earlier this week regarding
seismic requirements for the SMP assembly. 
  
  1903   Monday, April 01, 2019, 14:56 Isaac EarleSafe Module ParkingDevelopment  SMP shield box and vacuum vessel installed in final location Last week drilling of the additional
required holes in the SMP shield box was
completed in the Target Hall.  This
 20190401_101459.jpg20190401_110433.jpg20190401_144133.jpg20190401_110353.jpg 
  1904   Thursday, April 04, 2019, 14:49 Isaac EarleSafe Module ParkingDevelopment  SMP vacuum vessel support roller friction checkWith the SMP vacuum vessel now installed
inside the shield box, a test was performed
to measure the torque required to rotate
 CRR_check_for_as-built_SMP_-_April_4_2019.pdf 
  1905   Friday, April 05, 2019, 13:44 chad fisherSpent Target VaultDevelopment  2019 Pail drop tests
    Drop test performed January
8, 2019 with 25 lb target, UN pail and lug
cover. Drop failed. Lug cover half removed.
  
  1909   Monday, April 29, 2019, 07:56 chad fisherSouth Hot-CellDevelopment  Pail transfersTwo pail transfers took place April 25th.
Ta#47 transfered from pail 137 to
pail 201. existing plastic bag from 137 showed
 20190425_133750.jpg20190425_134106.jpg 
  1921   Wednesday, May 15, 2019, 16:06 Isaac EarleSafe Module ParkingDevelopment  SMP module support flange installed and leak checkedThe SMP module support flange sub-assembly
(IRH1755) was installed today according to
drawing IRH1683.  Dow Corning 111 sealing
 20190515_094730.jpg20190515_094740.jpg20190515_103253.jpg20190515_103824.jpg 
  1925   Friday, May 17, 2019, 16:46 Adam NewsomeSafe Module ParkingDevelopment  SMP Controls Installation Update 
The following controls-related
 IMG_20190417_100838.jpgIMG_20190417_100843.jpgIMG_20190517_162230.jpgIMG_20190517_162305.jpg 
  1935   Friday, June 07, 2019, 13:11 David WangConditioning StationDevelopmentTM4 TCS and TM4. TM4 has been connected at TCS for HV test.
TCS water system and vacuum pumps are switched
on. 
  
  1944   Thursday, June 20, 2019, 15:09 Isaac EarleSafe Module ParkingDevelopment  SMP motor wiring inspected by electricianThe AC wiring for the SMP motor was inspected
by Randy Boehm (TRIUMF electrician) as recommended
by Franco Mammarella (TRIUMF electrical engineer). 
  
  1945   Friday, June 21, 2019, 07:16 David WangSouth Hot-CellDevelopmentTM4 TM4 new source tray leak check at SHC.New source tray was installed on TM4 yesterday.
LD was used to pump down all water lines.
Tube heater +D circuit has a big leak 
  
  1946   Thursday, July 04, 2019, 08:57 Isaac EarleSafe Module ParkingDevelopment  SMP vacuum system installed July 3:
- Assembled exhaust line flexible
hose and fittings as per ISK0529 Rev D then
 20190703_122635.jpg20190703_122646.jpg20190703_122702.jpg 
  1950   Monday, July 15, 2019, 13:29 David WangConditioning StationDevelopmentTM4 Vacuum surge when TM4 B line iwas supplied with water.Yesterday, TM4 B line was supplied with
water at TCS for testing.  TCS: IG1
and IG2 had big response on it. See attachment.
 vacuum_surge_on_B_line_with_water.png 
  1955   Friday, July 26, 2019, 15:43 Isaac EarleSafe Module ParkingDevelopment  SMP vacuum control system completed The SMP vacuum control system has
been wired and setup to be controlled from
EPICS.  Backing valve control (SMP:BV1)
 SMP_vacuum_system_EPICS_screen.png 
ELOG V2.9.2-2455