Message ID: 2541     Entry time: Monday, February 12, 2024, 18:44
Author: Carla Babcock 
Category: ITW 
Type: Maintenance 
Module:  
Target/Number:  
Subject: ITW annual HV testing 

ITW was set up for HV testing - water is running and at a high resistivity due to injected N. Einzel lens is attached to ground. Everything else is as normal. The module plug is in so no vacuum bypasses were needed. Very easy to ramp to 60kV. Sat at 60 for about 1.5hrs with maybe 1 spark (hard to say from the strip tool data). Current draw was about 176uA. Data dumped as isac/data/ITW_HVtesting_shutdown2024