ID |
Date |
Author |
Target/No.# |
Source |
Station |
Module |
Target Oven W.O# |
Heat Shield W.O# |
Status |
Subject |
Text |
|
|
897
|
Tuesday, August 31, 2021, 13:55 |
Aaron Schmidt | | | | | | | | Pump down chamber | Pump down chamber w/ empty HS |
|
|
899
|
Tuesday, September 14, 2021, 17:12 |
Aaron Schmidt | C#3 | LP-SIS | ITW | TM2 | 44691-7 | 44378-11 | In progress | C#3 Conditioning | Tuesday, September 14, 2021, 17:00: Roughing
Tuesday, September 14, 2021, 17:37:
TP1B on. |
6x |
|
900
|
Thursday, September 23, 2021, 07:16 |
Aaron Schmidt | | | | | | | | Pump down empty chamber & reboot | Thursday, September 23, 2021, 07:15: Roughing.
Waterline loop installed.
Monday, September 27, 2021, |
|
|
901
|
Monday, October 04, 2021, 15:38 |
Aaron Schmidt | | LP-IG-LIS | ITE | TM4 | | 42132-7 | In progress | Conditioning UC#35 IG-LIS HS | Monday, October 04, 2021, 15:38: Roughing.
Monday, October 04, 2021, 16:08:
TP1B on. |
|
|
902
|
Wednesday, October 06, 2021, 11:56 |
Aaron Schmidt | | | | | | | | Pump down empty chamber | Wednesday, October 06, 2021, 11:56: Roughing.
Thursday, October 14, 2021,
09:07: Venting. |
|
|
903
|
Thursday, October 14, 2021, 10:13 |
Aaron Schmidt | | LP-SIS | ITW | TM2 | | 44378-22 | In progress | Conditioning UC#36 HS | Tube / TGHT only.
Thursday, October 14, 2021, 10:11:
Roughing. |
|
|
904
|
Wednesday, October 20, 2021, 15:01 |
Aaron Schmidt | | | | | | | | Pump down empty chamber | Wednesday, October 20, 2021, 15:01: Roughing. |
|
|
906
|
Friday, November 12, 2021, 13:01 |
Aaron Schmidt | Ta#63 | LP-SIS | ITE | TM4 | 44691-11 | 44378-12 | In progress | Conditioning Ta#63 | Friday, November 12, 2021, 13:01: BV1B
open. Roughing.
Friday, November 12, 2021, 13:05: |
|
|
907
|
Tuesday, November 16, 2021, 13:45 |
Aaron Schmidt | | | | | | | | Pump down empty chamber | Tuesday, November 16, 2021, 13:44: Roughing.
Water loop installed. Lock out tag removed. |
|
|
908
|
Tuesday, December 21, 2021, 13:34 |
Aaron Schmidt | | LP-SIS | | | 44691-8 | 44378-6 | In progress | Salts test HS & Holiday Shutdown | LP-SIS modified w/ 2 holes on the center
block to accept a pair of Ta tubes that are
run to the coil PS. |
|
|
909
|
Tuesday, January 04, 2022, 13:00 |
Aaron Schmidt | | | | | | | | Post water leak | December 30th, 2021: Water poured
down around Isac test stand and probes lab |
|
|
912
|
Monday, February 28, 2022, 08:08 |
Aaron Schmidt | | LP-SIS | | | | | | Mass marker / Coil-Tube target Test #2 | Installed & roughing Friday.
Monday, February 28, 2022, 08:07:
Turbopump TP1B on. |
|
|
916
|
Tuesday, April 05, 2022, 14:01 |
Aaron Schmidt | Test FEBIAD TM2-2022 | LP-FEBIAD | ITW | TM2 | | 42752-5 | | Test FEBIAD & TS operation | Tuesday, April 05, 2022, 13:57: Roughing.
BV1B.
Tuesday, April 05, 2022, 14:04: BV1A |
|
|
917
|
Thursday, April 07, 2022, 11:19 |
Aaron Schmidt | Test FEBIAD TM2-2022 | | ITW | TM2 | | 42752-5 | | Test FEBAID & TS operation | Gas system switched on manually to
use Ar & calibrated leak.
Thursday, April 07, 2022, 10:25: |
|
|
918
|
Monday, April 11, 2022, 14:52 |
Aaron Schmidt | | | | | | | Problems/Solutions | TP6 controller | Monday, April 11, 2022, 13:58: Controller
for TP6 is dead. Literally smokes if you
try to use it. |
|
|
919
|
Wednesday, April 13, 2022, 07:46 |
Aaron Schmidt | | | | | | | Problems/Solutions | Water leak | Wednesday, April 13, 2022, 07:38: Appears
to have a water leak. Vacuum @ 8.48e-06T.
All power / sources shut off. (Had already |
|
|
920
|
Wednesday, April 20, 2022, 13:42 |
Aaron Schmidt | | | | | | | | Vent Beamline half | Aurelia to do a visual test later.
Wednesday, April 20, 2022, 13:41:
IG6 Off. TP6 & TP2 off. |
|
|
921
|
Thursday, April 21, 2022, 13:38 |
Aaron Schmidt | | | | | | | Problems/Solutions | Leak checks | https://elog.triumf.ca/TIS/Test-Stand/919
Vacuum Group LD#1
(A) Top feed through fittings upgraded |
|
|
922
|
Monday, May 02, 2022, 14:10 |
Aaron Schmidt | | P2N-SIS | | | | | | Empty Chamber PS test. | No P2N is loaded. Testing the power supplies.
Tuesday, May 03, 2022, 10:07
In the past few days, the ITS has |
|
|
923
|
Thursday, May 05, 2022, 14:43 |
Aaron Schmidt | | P2N-SIS | | | 45241-1 | 45240-1 | In progress | P2N assembly conditioning. | Thursday, May 05, 2022, 14:43: Roughing.
Open BV1B
Thursday, May 05, 2022, 14:46: Upper |
|
|