Tuesday, April 05, 2022, 13:57: Roughing. BV1B.
Tuesday, April 05, 2022, 14:04: BV1A on.
Tuesday, April 05, 2022, 14:28: TP1B on.
Tuesday, April 05, 2022, 14:36: TP1A on.
Tuesday, April 05, 2022, 14:46: IG1 on.
Wednesday, April 06, 2022, 07:42: Vacuum @ 2.50e-06T.
Wednesday, April 06, 2022, 07:44: Waterlines opened. Vacuum Remains stable.
Wednesday, April 06, 2022, 07:59: Cage fully closed up. Power/sources on.
Wednesday, April 06, 2022, 08:00: COIL / TGHT / TBHT @ 10 A manually. Check - Ok.
Wednesday, April 06, 2022, 08:02: Anode @ 50V - Ok.
Wednesday, April 06, 2022, 08:04: BIAS / EE / EZL @ 1 / -0.5 / 1 kV. Check - Ok.
Wednesday, April 06, 2022, 08:10: BIAS / EE / EZL @ 10 / -1 / 10 kV.
Wednesday, April 06, 2022, 08:16: BIAS / EE / EZL @ 30 / -1.5 / 13 kV. Ok. Vacuum @ 2.39e-06T.
Wednesday, April 06, 2022, 08:46: 1/2 hour. Stable.
Wednesday, April 06, 2022, 08:50: All sources off. PS off. Open Cage.
Wednesday, April 06, 2022, 08:54: Begin cycling source gas control.
Wednesday, April 06, 2022, 08:57: SV5 open.
Wednesday, April 06, 2022, 08:58: SV3 & SV4 open. Vacuum stable @2.32e-06T.
Wednesday, April 06, 2022, 09:02: Cage closed. Sources / PS on. IV4 open.
Wednesday, April 06, 2022, 09:04: Auto-ramping TGHT / TBHT to 350 / 150 @ 2 A per min.
Wednesday, April 06, 2022, 09:05: Anode @ 50 V. Coil @ 10 A.
Wednesday, April 06, 2022, 09:10: Optics set.
Wednesday, April 06, 2022, 11:37: Gas lines closed. Abort ramping. TGHT / TBHT @ 306 / 150 A. HV lockout. Open cage.
***Gas bottles are not in the old configuration*** No gas.
Wednesday, April 06, 2022, 11:50: Begin Auto-cooling @ 2 A per min.
Thursday, April 07, 2022, 08:13: IG1 off. Turbo pumps off. Power off.
Thursday, April 07, 2022, 09:17: Venting.
|