ID |
Date |
Author |
Target/No.# |
Source |
Station |
Module |
Target Oven W.O# |
Heat Shield W.O# |
Status |
Subject |
1026
|
Tuesday, October 29, 2024, 18:25 |
Aaron Schmidt | UC#46 (assembly only) | LP-IG-LIS | ITW | TM4 | | 42972-6 / 39956-1 | In progress | Conditioning UC#46 Assembly | 42972-6 Base / 39956-1 Lid
Tuesday, October 29, 2024, 18:20: Roughing.
Tuesday, October 29, 2024, 18:52: TP1B on.
Tuesday, October 29, 2024, 18:58: TP1A on.
Tuesday, October 29, 2024, 19:06: IG1 on.
Wednesday, October 30, 2024, 07:23: Vacuum @ 8.25e-07T. Waterline FS#5 open.
Wednesday, October 30, 2024, 07:25: Power on.
Wednesday, October 30, 2024, 07:32: PS for TGHT keeps timing out? Goes red. Won't start.
Tapped up TBHT to 10 A. TGHT?
Wednesday, October 30, 2024, 08:20: Manually cycled the PS. No longer trips.
Tapped up TGHT to 5 A. OK
Wednesday, October 30, 2024, 08:26: Auto-ramping TGHT / TBHT to 580 / 230 A @ 2 A per min.

Wednesday, October 30, 2024, 14:32: Auto-cooling @ 2 A per min.
Thursday, October 31, 2024, 08:30: TP/ IG1 off.
Thursday, October 31, 2024, 12:52: Venting. |
983
|
Wednesday, October 18, 2023, 15:43 |
Aaron Schmidt | | LP-SIS | | | 45447-12 | 45235-17 | In progress | Conditioning UC#43 (empty) w/ gas line | Thermocouples attached on end plate
Indium salt @ 10 µl
3 wraps of Ta HS on oven. Gas line on center block. Empty oven.
Wednesday, October 18, 2023, 15:13: Roughing
Wednesday, October 18, 2023, 15:35: Waterline FS#5 on.
Wednesday, October 18, 2023, 15:42: TP1B on.
Wednesday, October 18, 2023, 15:52: TP1A on.
Wednesday, October 18, 2023, 16:00: IG1 on.
Thursday, October 19, 2023, 07:34: Auto-ramping TGHT / TBHT to 580 / 230 A @ 2 A per min.
Thursday, October 19, 2023, 09:15: IV4 opened.
Thursday, October 19, 2023, 09:42: HV sources on.
Thursday, October 19, 2023, 09:43: BIAS / EE / EZL @ 1 / -0.5 / 1 kV.
Thursday, October 19, 2023, 09:45: Optics are set. Standard tune.
Thursday, October 19, 2023, 10:40: HV to 0 kV. Cage open.
Thursday, October 19, 2023, 12:16: Cage closed. HV sources on. Optics set.
Thursday, October 19, 2023, 13:41: 1st set of mass scans complete. Optics set to 'Fernando's Tune',
Friday, October 20, 2023, 06:29: Mass & wire scans continue.
Friday, October 20, 2023, 10:33: BIAS / EE / EZL @ 43 / -2.2 / 18.5 kV.
Friday, October 20, 2023, 11:00: Spark* Optics needed full reset.
Friday, October 20, 2023, 12:48: HV to 0 kV. HV test done
Tuesday, October 24, 2023, 09:39: PS / sources off. IV4 closed - Tripped - Reset.
Tuesday, October 24, 2023, 09:41: IG1 off. TP off. |
Attachment 1: UC#43_Conditioning_empty_with_Gas_mod.docx
|
Attachment 2: UC#43_HS_with_gas_line_mod_-_Test_2.docx
|
Attachment 3: UC#43_HS_with_gas_line_mod_-_HV_Test.docx
|
944
|
Tuesday, November 15, 2022, 11:24 |
Aaron Schmidt | UC#41 assembly | LP-SIS | ITE | TM4 | 45220-8 | 45235-4 | In progress | Conditioning UC#41 assembly | LP-SIS 45220-8 is empty & for testing only.
Tuesday, November 15, 2022, 11:00: Roughing.
Tuesday, November 15, 2022, 11:21: BV1A open.
Tuesday, November 15, 2022, 12:40: TP1B on
Tuesday, November 15, 2022, 12:47: TP1A on
Tuesday, November 15, 2022, 12:49: T1A Currently spinning up. Distinct & loud hum noted. Contacting vacuum group.
Tuesday, November 15, 2022, 12:50: TP's off.
Tuesday, November 15, 2022, 12:55: TP1B restart. ok
Tuesday, November 15, 2022, 12:56: TP1A restart. Failed
Tuesday, November 15, 2022, 13:04: TP1A restart. Failed.
Tuesday, November 15, 2022, 13:05: Controller reset TP1A restarted. Failed. Visually confirmed that it has seized.
See elog# 946
Wednesday, November 16, 2022, 14:53: TP1B on
Wednesday, November 16, 2022, 14:56: TP1B at speed.
Wednesday, November 16, 2022, 14:58: TP1A on.
Wednesday, November 16, 2022, 15:07: TP1A at speed. IG1 on
Thursday, November 17, 2022, 07:14: Waterline FS#5 open. Vacuum stable @ 9.59e-07T
Thursday, November 17, 2022, 07:15: IV4 open.
Thursday, November 17, 2022, 07:18: PS & Sources on.
Thursday, November 17, 2022, 07:20: Auto-ramping TGHT / TBHT to 350 / 150 A @ 2 A per min.
Thursday, November 17, 2022, 07:23: Optics set
Thursday, November 17, 2022, 07:32: BIAS / EE / EZL @ 30 / -1.5 / 13 kV.
Thursday, November 17, 2022, 07:35: BIAS / EE / EZL @ 35 / -1.8 / 15 kV.
Thursday, November 17, 2022, 07:38: BIAS / EE / EZL @ 40 / -2.0 / 17 kV
Thursday, November 17, 2022, 07:40: BIAS / EE / EZL @ 45 / -2.3 / 20 kV
Thursday, November 17, 2022, 08:40: No sparks over 1 hr.
Thursday, November 17, 2022, 08:43: HV reduced. BIAS / EE / EZL @ 30 / -1.5 / 13 kV.
Thursday, November 17, 2022, 10:06: Minor instability & sparks noted.
Thursday, November 17, 2022, 10:18: Consistent sparking. Visually confirmed on the TBHT insulator.
Thursday, November 17, 2022, 10:21: BIAS & EZL reduced to 20 / 10 kV.
Thursday, November 17, 2022, 10:51: HV stable for the last 15 minutes. Auto-ramping TGHT / TBHT to 580 / 230 A @ 2 A per min.
Thursday, November 17, 2022, 14:02: BIAS / EE / EZL @ 30 / -1.5 / 13 kV. Stable
Thursday, November 17, 2022, 14:25: Mass & wire scans complete Empty LP-SIS No salts added.
Masses showed around mass:
-130-140
-39-40
-23-28
Thursday, November 17, 2022, 14:27: Outgassing continues.
Friday, November 18, 2022, 07:39: Mass & wire scans continued.
Traces masses:
-39-40
-23
Friday, November 18, 2022, 07:48: Auto-cooling @ 2 A per min.
Friday, November 18, 2022, 08:01: HV off.
Monday, November 21, 2022, 06:44: Sources off & IV4 closed.
Monday, November 21, 2022, 06:45: IG1 off. Turbo pumps off. |
Attachment 1: UC#41_assembly_conditioning.docx
|
939
|
Tuesday, August 30, 2022, 13:58 |
Aaron Schmidt | | | | | 44062-7 | 44378-25 | In progress | Conditioning UC#40 assembly | Conditioning the UC#40 LP-SIS assembly & ISAC TS main vacuum chamber. Straight / round oven in use (TGHT only).
Tuesday, August 30, 2022, 13:55: BV1B open. Roughing.
Tuesday, August 30, 2022, 14:00: BV1A open.
Wednesday, August 31, 2022, 07:29: Vacuum @ 0.064T. TP1B on.
Wednesday, August 31, 2022, 07:35: TP1 A on.
Wednesday, August 31, 2022, 08:56: Vacuum @ 9.97e-06T. Waterline FS#5 opened.
Wednesday, August 31, 2022, 08:58: Vacuum @ 9.95e-06T. OK. Power on.
Thursday, September 01, 2022, 07:50: Vacuum @ 5.21e-06T.
Thursday, September 01, 2022, 07:54: Manually tapped up TGHT to 50 A.
Limit increased on TGHT parameter setup to 5.500e-06T.
Thursday, September 01, 2022, 07:57: Auto-ramping TGHT to 580 A @ 2 A per min.
Monday, September 12, 2022, 15:09: Vacuum @ 1.69e-06T. Auto-cooling @ 2A per min.
Monday, September 26, 2022, 10:52: Turbo pumps off.
Monday, September 26, 2022, 12:20: Venting. PS off & waterlines purged. |
936
|
Thursday, July 07, 2022, 16:52 |
Aaron Schmidt | | LP-IG-LIS | ITW | TM2 | | 42132-3 | In progress | Conditioning UC#39 assembly | No UCx target installed. Straight / blank oven in use for out gassing.
Thursday, July 07, 2022, 16:50: Roughing.
Thursday, July 07, 2022, 16:53: BV1A Open.
Thursday, July 07, 2022, 17:31: TP1B on.
Thursday, July 07, 2022, 17:36: TP1A on.
Thursday, July 07, 2022, 17:46: IG1 on. Vacuum @ 2.31e-05T
Thursday, July 07, 2022, 17:47: Waterline FS#5 Opened. Vacuum @ 2.05e-05T & continuing down.
Thursday, July 07, 2022, 18:00: Bypass on IG1. 10A TGHT Check. Ok. Back to 0A. Removed bypass. Ready for remote operation.
Friday, July 08, 2022, 10:44: Started autoramping TGHT 580A/TBHT 0A
Friday, July 08, 2022, 15:37: Autoramping complete
Saturday, July 09, 2022, 07:34 : ramp down started
Sunday, July 10, 2022, 22:14: IG1, TP1B & A off. TP6 has tripped. Sources off.
|
930
|
Tuesday, May 31, 2022, 13:35 |
Aaron Schmidt | UCx HS | | ITW | TM2 | | 44378-19 | In progress | Conditioning UC#38 assembly | Using a broken LP-FEBIAD source. TGHT only.
Tuesday, May 31, 2022, 13:24: Roughing.
Tuesday, May 31, 2022, 13:54: TP1B on.
Tuesday, May 31, 2022, 14:06: TP1A on.
Tuesday, May 31, 2022, 14:13: IG1 on.
Wednesday, June 01, 2022, 07:41: Vacuum @ 2.13e-06T. Waterline FS#5 open.
Wednesday, June 01, 2022, 07:43: Power/Sources on.
Wednesday, June 01, 2022, 07:51: Auto-ramping TGHT to 580A @ 2A per min.

Monday, June 06, 2022, 07:09: Auto-cooling @ 2A per min.
Wednesday, June 08, 2022, 07:07: Turbo pumps off.
Wednesday, June 08, 2022, 07:53: Venting. |
903
|
Thursday, October 14, 2021, 10:13 |
Aaron Schmidt | | LP-SIS | ITW | TM2 | | 44378-22 | In progress | Conditioning UC#36 HS | Tube / TGHT only.
Thursday, October 14, 2021, 10:11: Roughing.
Thursday, October 14, 2021, 12:05: TP1B on.
Thursday, October 14, 2021, 12:10: TP1A on.
Thursday, October 14, 2021, 13:27: IG1 on.
Thursday, October 14, 2021, 16:08: Vacuum @ 3.73e-06T
Thursday, October 14, 2021, 16:10: FS#5 open. Vacuum Stable.
Thursday, October 14, 2021, 16:13: PS on. Sources on. TGHT manually tapped up to 10 A. OK. Allow vacuum to stabilize further.
Friday, October 15, 2021, 06:38: Auto-ramping TGHT to 580 A @ 2 A per min.
Friday, October 15, 2021, 21:32: Auto-Cooling @ 1 A per min.
Monday, October 18, 2021, 07:50: Sources, IG1, & turbo pumps off. |
Attachment 1: UC#36.docx
|
901
|
Monday, October 04, 2021, 15:38 |
Aaron Schmidt | | LP-IG-LIS | ITE | TM4 | | 42132-7 | In progress | Conditioning UC#35 IG-LIS HS | Monday, October 04, 2021, 15:38: Roughing.
Monday, October 04, 2021, 16:08: TP1B on.
Monday, October 04, 2021, 16:15: TP1 A on.
Monday, October 04, 2021, 16:41: IG1 on.
Tuesday, October 05, 2021, 06:47: Vacuum @ 4.09e-06T.
Tuesday, October 05, 2021, 06:49: Waterlines opened. Vacuum stable.
Tuesday, October 05, 2021, 06:50: Power / sources on.
Tuesday, October 05, 2021, 06:52: Auto-ramping TGHT to 580 A @ 2 A per min.
Wednesday, October 06, 2021, 05:44: Auto-cooling @ 3 A per min. Vacuum @ 2.37e-06T.\
Wednesday, October 06, 2021, 09:37: Power / sources off.
Wednesday, October 06, 2021, 09:38: IG1 off. TSG:TP1 A & B off.
Wednesday, October 06, 2021, 11:11: Venting. Waterlines off.
Edit* Switched from ITW to ITE. on station icon - AS.
|
Attachment 1: UC#35.docx
|
718
|
Tuesday, April 23, 2019, 14:39 |
Aaron Schmidt | | LP-SIS | | | | 42752-8 | Done | Conditioning UC#28 HS | Tuesday, April 23, 2019, 14:39: Roughing.
Tuesday, April 23, 2019, 15:09: Turbo pumps started.
Tuesday, April 23, 2019, 15:18: Ion gauge on.
Wednesday, April 24, 2019, 07:33: RGA on.
Wednesday, April 24, 2019, 07:37: Waterlines opened. Vacuum ok @ 7.99e-07T. No response on RGA
Wednesday, April 24, 2019, 07:41: Power / sources on.
Wednesday, April 24, 2019, 07:43: Auto-ramping TGHT to 575 @ 2A per min. Vacuum limit remains at 3.000e-06T.
Thursday, April 25, 2019, 14:07: Auto-cooling @ 2 A per min.
Friday, April 26, 2019, 07:53: sources off.
Friday, April 26, 2019, 07:55: RGA off. Power off.
Friday, April 26, 2019, 07:57: Turbos off.
Friday, April 26, 2019, 08:00: HS waterlines purged. |
Attachment 1: TS-2019-04-24-07-30.rga
|
Attachment 2: UC#28_HS.docx
|
717
|
Monday, April 15, 2019, 14:42 |
Aaron Schmidt | | LP-SIS | | | | 42972-1 | Done | Conditioning UC#27 HS & test FS#3 | New coil lines installed for P2N testing later.
Monday, April 15, 2019, 14:15: Roughing.
Monday, April 15, 2019, 14:49: Turbo pumps on.
Tuesday, April 16, 2019, 08:20: RGA on.
Gradually open each line. Wait 5 minutes & monitor the response.
Tuesday, April 16, 2019, 08:30: Open Return & Supply main valves.
Tuesday, April 16, 2019, 08:32: Open FS#5. Vacuum @ 4.29e-06T. No response on RGA (water).
Tuesday, April 16, 2019, 08:37: Vacuum @ 4.37e-06T
Tuesday, April 16, 2019, 08:38: Open FS#4. Vacuum @ 4.37e-06T. No response on RGA (water).
Tuesday, April 16, 2019, 08:43 Vacuum @ 4.29e-06T
Tuesday, April 16, 2019, 08:44 Open FS#3. Vacuum @ 4.29e-06T. No response on RGA (water).
Tuesday, April 16, 2019, 08:49: Vacuum @ 4.26e-06T.
Tuesday, April 16, 2019, 08:50: Open FS#2. Vacuum @ 4.29e-06T. No response on RGA (water).
Tuesday, April 16, 2019, 08:57: Vacuum @ 4.29e-06T.
Wednesday, April 17, 2019, 08:30: Power/sources on. Vacuum @ 2.46e-06T.
Wednesday, April 17, 2019, 10:30: Auto-ramping TGHT to 150 @ 2A per min. Vacuum limit increased to 3.000e-06T.
Wednesday, April 17, 2019, 11:53: Auto-ramping TGHT to 300 @ 2A per min. Vacuum @ 2.50e-06T.
Wednesday, April 17, 2019, 13:10: Auto-ramping TGHT to 350 @ 2A per min. Vacuum @ 2.95e-06T.
Thursday, April 18, 2019, 07:23: Auto-ramping TGHT to 575 @ 2A per min. Vacuum @ 2.40e-06T.
Tuesday, April 23, 2019, 06:45: Auto-Cooling TGHT @ 2A per min. Vacuum @ 9.22e-07T.
Tuesday, April 23, 2019, 08:29: RGA error. Shut off RGA.
Tuesday, April 23, 2019, 11:34: Power/sources off.
Tuesday, April 23, 2019, 11:37: IG1 off. Turbos off.
Tuesday, April 23, 2019, 12:53: Venting. |
Attachment 1: UC#27_&_FS#3_check.docx
|
Attachment 2: TS-2019-04-16-08-20.rga
|
1028
|
Tuesday, November 05, 2024, 16:40 |
Brady Borrmann | UC #24D (Assembly only) | LP-IG-LIS | | | | 44972-5 / 42972-9 | In progress | Conditioning UC#24D Assembly | 42972-5 Base / 42972-9 Lid
Tuesday, November 05, 2024, 16:30: Roughing.
Tuesday, November 05, 2024, 17:04: TP1B on.
Tuesday, November 05, 2024, 17:13: TP1A on.
Tuesday, November 05, 2024, 17:21: IG1 on @ 2.41e-05T
Wednesday, November 06, 2024, 10:35: Vacuum @ 5.75e-07T. Waterline FS#5 open.
Wednesday, November 06, 2024, 16:24: TGHT/TBHT ramping to 580/230A at 2A/min
Thursday, November 07, 2024, 09:16: Increasing BIAS/EE/EZL to 30/2.5/13 kV slowly
Thursday, November 07, 2024, 11:26: as expected, no beam out to FC0. slowly increasing to bias to 45kV alongside ezl to 28kV
Thursday, November 07, 2024, 11:27: TGHT dropped out for 1s. Did not register a trip or anything. simply jumped down to 0A and immediately recovered.
Thursday, November 07, 2024, 14:40: At 45kV, there were no sparks noticed. The target assembly was brought down to 0V and ramped down to 0A/0A at -2A/min
Wednesday, November 13, 2024, 09:15: PS Off. TP off - AS.
Wednesday, November 13, 2024, 11:26: VV1 opened - BB. |
761
|
Wednesday, October 02, 2019, 13:42 |
Aaron Schmidt | | LP-SIS | | | 41790-9 | 43515-9 | In progress | Conditioning UC#(30) HS | Wednesday, October 02, 2019, 13:42: Roughing.
Wednesday, October 02, 2019, 14:13: Turbo Pumps started.
Wednesday, October 02, 2019, 14:19: Ion gauge on.
Wednesday, October 02, 2019, 14:24: RGA on.
Thursday, October 03, 2019, 07:35: Waterlines opened. No response on RGA. Vacuum ok @ 7.53e-07T
Thursday, October 03, 2019, 07:37: Power / Sources on.
Thursday, October 03, 2019, 07:38: Auto-ramping TGHT to 580 A @ 2 A per min.
Friday, October 04, 2019, 14:53: Auto-cooling @ 2 A per min.
Wednesday, October 16, 2019, 10:17: RGA off.
Wednesday, October 16, 2019, 10:19: Power / Sources off. IG1 off. Turbo pumps off. |
Attachment 1: UC#30.docx
|
760
|
Friday, September 27, 2019, 11:54 |
Aaron Schmidt | | LP-SIS | | | 41790-9 | 43515-6 | | Conditioning UC#(29) HS | Using broken LP-FEBIAD oven. TBHT off.
Friday, September 27, 2019, 11:53: Roughing.
Friday, September 27, 2019, 13:14: Turbo pumps on.
Friday, September 27, 2019, 13:20: Ion gauge on.
Friday, September 27, 2019, 13:24: RGA on.
Monday, September 30, 2019, 07:30: Waterlines Opened. No response on RGA. Vacuum ok @ 5.39e-07T.
Monday, September 30, 2019, 07:34: Power / Sources on.
Monday, September 30, 2019, 07:35: Auto-ramping TGHT to 580 A @ 2 A per min.
Tuesday, October 01, 2019, 14:29: Auto-Cooling TGHT @ 2A per min.
Wednesday, October 02, 2019, 08:24: Power / sources off.
Wednesday, October 02, 2019, 08:25: RGA off.
Wednesday, October 02, 2019, 08:26: Ion gauge & Turbo pumps off.
Wednesday, October 02, 2019, 12:50: Venting & Waterlines purged. |
1011
|
Wednesday, June 19, 2024, 15:50 |
Brady Borrmann | TiC#9 | HP-SIS | | | 45447-29 | 45235-19 | In progress | Conditioning TiC#9 | Wednesday, June19, 2024, Spare TiC HP-SIS target installed. TiC#24C
Wednesday, June19, 2024, 15:00: Roughing
Wednesday, June19, 2024, 17:25: TP1B started.
Wednesday, June 19, 2024, 15:30: TP1B Green. OK.
Wednesday, June 19, 2024, 15:30 : TP1A on.
Wednesday, June 19, 2024, 15:40: Time out on TP1A
Wednesday, June 19, 2024, 15:43: Turn on BV1A & TP1A
Wednesday, June 19, 2024, 15:43 : TP1A Green. OK.
Wednesday, June 19, 2024, 15:44: IG1 turned on @ 3.92e-05 T
_________ dave neilson
Thursday, June 20, 2024, 10:23: Water cooling valves opened. no effect on vacuum.
Thursday, June 20, 2024, 11:19: Power on. Increasing TGHT TBHT to 440A 290A at 1A/30s
Thursday, June 20, 2024, 15:59 increasing BIAS / EE / EZL to 30 / -1.5 / 13 kV.
Thursday, June 20, 2024, 16:21 slowly increasing BIAS to test for high voltage sparking --- sparked at 33.6kV, sparked at 34kV. 34.6kV, 37.8kV sparking infrequent (period >5min)
Thursday, June 20, 2024, 17:18 decreasing high voltages to 0
Thursday, June 20, 2024, 17:36 decreased TGHT to 300A overnight.
Friday, June 21, 2024, 09:16 Increasing TGHT to 580A (1A/30s) for testing
Friday, June 21, 2024, 12:28 increasing BIAS / EE / EZL to 30 / -1.5 / 13 kV.
Friday, June 21, 2024, 16:31 decreasing BIAS / EE / EZL to 0
Tuesday, June 25, 2024, 10:05 : TP1A TP1B off. preparing to vent chamber for target replacement.
Wednesday, July 10, 2024, 12:22: Venting - AS
Wednesday, July 10, 2024, 14:57: Roughing.
|
Attachment 1: 2024-06-21_HPTiC-24C_target_characterization.docx
|
1007
|
Friday, April 26, 2024, 13:49 |
Aaron Schmidt | TiC#7 | HP-FEBIAD | ITW | TM4 | 45447-5 | 45235-15 | In progress | Conditioning TiC#7 | FM-SW calibrated leak installed.
Friday, April 26, 2024, 13:48: Roughing.
Friday, April 26, 2024, 14:20: TP1B started.
Friday, April 26, 2024, 14:26: TP1B Green. OK.
Friday, April 26, 2024, 14:30: TP1A on.
Monday, April 29, 2024, 08:44: Vacuum @ 4.58e-07T. Waterline FS#5 open. Vacuum ok.
Monday, April 29, 2024, 08:50: Power / sources on. Tap up check. TGHT / TBHT to 5 / 5 A. BIAS / EE / EZL to 1 / -0.5 / 1 kV. Anode to 100 V. Coil to 4 A. Ok. Tap back down.
Monday, April 29, 2024, 10:44: IV4 open.
-BB:
Monday, April 29, 2024, 11:07: BIAS / EE / EZL @ 30 / -1.5 / 13 kV.
Monday, April 29, 2024, 11:12: BIAS / EE / EZL @ 40 / -1.8 -2.0 / 17 kV.
Monday, April 29, 2024, 11:19: BIAS / EE / EZL @ 43 / -2.0 / 19 kV.
Monday, April 29, 2024, 11:23: BIAS / EE / EZL @ 45 / -2.0 / 19 kV.
Monday, April 29, 2024, 11:27: BIAS / EE / EZL @ 47.5 / -2.2 / 22 kV.
Monday, April 29, 2024, 11:33: BIAS / EE / EZL @ 50 / -2.5 / 25 kV.
Monday, April 29, 2024, 12:05: 30 minutes @ 50 kV. 3 sparks at the very end. 2 inside and 1 outside.
Monday, April 29, 2024, 12:09: BIAS / EE / EZL @ 30 / -1.5 / 13 kV. Vacuum @ 4.67e-07T. Start tapping up coil.
Monday, April 29, 2024, 12:32: Coil @ 80 A. Tapped up manually at 4 A per min approx. Vacuum @ 5.2e-07T
Monday, April 29, 2024, 14:00: Vacuum @ 7.20e-07T (30-60 min depending on whether the out gassing levels or begins to decrease)
Monday, April 29, 2024, 14:02: Coil @ 0 A.
Monday, April 29, 2024, 14:05: Anode @ 100 V.
Monday, April 29, 2024, 14:07: Anode @ 200 V.
Monday, April 29, 2024, 14:09: Anode @ 500 V.
Monday, April 29, 2024, 14:11: Anode @ 0 V.
Monday, April 29, 2024, 14:33: HV @ 0 V.
Monday, April 29, 2024, 14:34: Auto-ramping TGHT / TBHT to 350 / 150 @ 2A per minute.
Tuesday, April 30, 2024, 07:18: Auto-ramping TGHT / TBHT to 580 / 290 @ 2A per minute.
Tuesday, April 30, 2024, 13:44: Gas lines purged & refilled with Ar.
Tuesday, April 30, 2024, 13:48: optics set.
Tuesday, April 30, 2024, 13:51: BIAS / EE / EZL @ 30 / -1.5 / 13 kV.
Tuesday, April 30, 2024, 13:56: Anode @ 100 V. Coil @ 20 A
Tuesday, April 30, 2024, 13:59: Reset / Cfg MB1
Tuesday, April 30, 2024, 14:40: Initial mass & wire scans complete.
Tuesday, April 30, 2024, 15:07: Argon gas lines purged.
Tuesday, April 30, 2024, 15:07: Mass scan repeated.
Tuesday, April 30, 2024, 15:42: Gas on. Magnet set to 40.1 mass/charge. Anode & coil vs fc6 output optimization scan started. 0-90A coil and 0-400V anode.
Tuesday, April 30, 2024, 15:55: Vacuum is noticeably rising. If it reaches 5e-6T, will terminate the scan.
Tuesday, April 30, 2024, 15:59: rate of increase appears to be slowing and reaching a plateau.
Tuesday, April 30, 2024, 16:01: optimization data at measure_id=6058. image at bottom.
Tuesday, April 30, 2024, 16:03: COIL and anode set to 0. decreasing BIAS/EZL/EE to 0V
Tuesday, April 30, 2024, 16:12: decreasing TGHT TBHT at 1A/30s to 0
Wednesday, May 01, 2024, 09:38: TP1B and TP1A turned off, winding down
Wednesday, May 01, 2024, 10:1: VV1 open, venting. Water cooling off. purged lines

|
962
|
Monday, April 17, 2023, 14:08 |
Aaron Schmidt | TiC#6 | HP-FEBIAD | ITW | TM2 | 44692-10 | 45235-12 | In progress | Conditioning TiC#6 | Monday, April 17, 2023, 14:03: Roughing.
Monday, April 17, 2023, 14:08: BV1A open.
Monday, April 17, 2023, 14:32: TP1B on.
Monday, April 17, 2023, 14:38: TP1A on.
Monday, April 17, 2023, 14:47: TP1A Timed out. Restarted it within 30 seconds & it's up to speed. IG1 on.
Tuesday, April 18, 2023, 11:49: Vacuum @ 3.68e-07T. Waterline FS#5 opened. Vacuum stable.
Tuesday, April 18, 2023, 11:52: Power / Sources on.
Tuesday, April 25, 2023, 12:20: Power / Sources off
Tuesday, April 25, 2023, 12:26: IG1 Off. TP1B & TP1A off. |
965
|
Friday, May 05, 2023, 06:49 |
Aaron Schmidt | TiC#6 | HP-FEBIAD | ITW | TM2 | 44692-10 | 45235-12 | In progress | Conditioning TiC#6 | Ceramic elbow installed on the anode.
Friday, May 05, 2023, 06:47: Roughing.
Friday, May 05, 2023, 07:24: TP1B on.
Friday, May 05, 2023, 07:34: TP1A on.
Friday, May 05, 2023, 07:43: IG1 on.
Friday, May 05, 2023, 12:12: Vacuum @ 6.91e-06T. FS#5 opened. Vacuum stable.
Friday, May 05, 2023, 12:16: Power/sources on. Gases set
Friday, May 05, 2023, 12:19: Optics on / set.
Friday, May 05, 2023, 12:21: Quick System ready check - OK. Manually set.
TGHT / TBHT @ 5 / 5 A
BIAS / EE / EZL @ 1 / -0.5 / 1 kV
Anode @ 100 V - 7.326mA
Coil @ 10 A.
Friday, May 05, 2023, 12:23: Ready for operation. All sources back to 0 A / 0 V. Optics remain. Vacuum continues down @ 6.70e-06T.
Monday, May 08, 2023, 08:21: IV4 open.
Monday, May 08, 2023, 08:25: Tap up Anode in steps @ 20 v per 20 seconds.
Anode @ 100 V = 4.884 mA
Anode @ 200 V = 6.105 mA
Anode @ 300 V = 7.326 mA
Anode @ 400 V = 7.326 mA
Monday, May 08, 2023, 08:42: Anode tapped down to 20 V.
Monday, May 08, 2023, 08:52: Coil tapped up to 70 A @ 7 A per minute.
Monday, May 08, 2023, 09:12: Coil tapped back down to 0 A @ 7 A per minute.
Monday, May 08, 2023, 09:15: Auto-ramping TGHT / TBHT to 580 / 290 A @ 2 / 1 A per min.
Monday, May 08, 2023, 09:20: BIAS / EE / EZL set to 10 / -1.0 / 5 kV.
Monday, May 08, 2023, 14:37: TGHT / TBHT @ 580 / 290 A. BIAS / EE / EZL set to 30 / -1.5 / 13 kV.
Monday, May 08, 2023, 14:38: Anode tapped up to 100 V @ 20 V per 20 seconds. Begin mass & wire scans.
Monday, May 08, 2023, 15:01: Mass & wire scans complete.
Monday, May 08, 2023, 18:59: Tap up Anode in steps @ 20 v per 20 seconds from 100 V.
Anode @ 100 V = 9.768 mA
Anode @ 200 V = 12.210 mA
Anode @ 300 V = 14.652 mA
Monday, May 08, 2023, 19:05: Anode @ 400 V = 17.094 mA
Monday, May 08, 2023, 19:18: Anode tapped down to 20 V.
Monday, May 08, 2023, 19:24: BIAS / EE / EZL @ 1 / -0.5 / 1 kV
Monday, May 08, 2023, 19:35: Coil tapped up to 70 A @ 7 A per minute.
Monday, May 08, 2023, 19:49: Coil tapped back down to 0 A @ 7 A per minute. Vacuum rose to 6.20e-06T @ 70A. Stabilized back down around 2.24e-06T.
Monday, May 08, 2023, 19:53: Auto-cooling @ 1 A per minute.
Tuesday, May 09, 2023, 06:59: Anode, & HV sources to 0 V. IV4 closed.
Tuesday, May 09, 2023, 07:35: SV5 closed. Power / sources off.
Tuesday, May 09, 2023, 07:38: IG1 off. TP1B & TP1A off.
Tuesday, May 09, 2023, 08:49: Venting. |
Attachment 1: TiC#6_Anode_&_Coil_checks.docx
|
960
|
Wednesday, March 29, 2023, 12:22 |
Aaron Schmidt | TiC#5 | LP-FEBIAD | ITE | TM4 | 44692-7 | 45235-20 | Failed | Conditioning TiC#5 | Wednesday, March 29, 2023, 09:15: Roughing.
Wednesday, March 29, 2023, 12:22: TP1B on.
Wednesday, March 29, 2023, 12:40: TP1A on.
Wednesday, March 29, 2023, 13:03: IG1 on.
Thursday, March 30, 2023, 08:23: Vacuum @ 3.42e-07T.
Thursday, March 30, 2023, 08:24: Waterline FS#5 open. Vacuum ok.
Thursday, March 30, 2023, 08:31: Manual Checks:
TGHT / TBHT @ 5 / 5 A ok
BIAS / EE / EZL @ 1 / 0.5 / 1 kV ok.
Thursday, March 30, 2023, 08:32: Anode @ 100 V ok. Coil @ 10 A ok.
Thursday, March 30, 2023, 08:56: Auto-ramping TGHT / TBHT to 350 / 100 A @ 2 A per minute.
Thursday, March 30, 2023, 11:45: Abort heating. TGHT / TBHT @ 233 / 100 A.
Thursday, March 30, 2023, 13:53: Auto-cooling @ 2 A per min
Thursday, April 13, 2023, 11:07: New TMS:RP2 roughing pump installed: Elog 961
Thursday, April 13, 2023, 12:06: Gas lines opened. Ar gas @ 50 kPa
Thursday, April 13, 2023, 13:34: IG1 @ 2.27e-07T / IG6 @ 6.46e-06T. Open IV4
Thursday, April 13, 2023, 13:35: IG1 @ 3.66e-07T / IG6 @ 6.31e-06T7.
Thursday, April 13, 2023, 13:39: IG1 @ 4.03e-07T / IG6 @ 6.24e-06T. Power / Sources on.
Thursday, April 13, 2023, 13:42: Optics still require vacuum below 5.01e-06T on IG6. Wait.
Friday, April 14, 2023, 06:30: Optics still not configuring on TMS:Q2,Q5 or TMS:CB1. Controls group notified.
Friday, April 14, 2023, 06:42: Auto-ramping TGHT / TBHT to 350 / 150 A @ 2A per minute.
Friday, April 14, 2023, 11:26: Optics fixed / set. Continue ramping to 580 / 270 A @ 2A per minute.
Friday, April 14, 2023, 12:27: Halt & hold ramping. Vacuum @ 5.01e-06T.
Friday, April 14, 2023, 13:54: Ramping continued.
Friday, April 14, 2023, 14:57: Halt & hold ramping. Vacuum @ 5.01e-06T.
Friday, April 14, 2023, 15:38: Ramping continued.
Friday, April 14, 2023, 15:47: TGHT / TBHT @ 580 / 290 A.
BIAS / EE / EZL @ 30 / -1.5 / 13 kV. Anode @ 100 V. Coil @ 10 A
Friday, April 14, 2023, 15:51: Anode @ 400 V.
Friday, April 14, 2023, 15:52: Anode back to 300 V / 41 mA. . Limited around 350 V. Current limit 50 mA.
Friday, April 14, 2023, 15:55: Adjusted current limit. Anode @ 400 V / 72.039 mA.
Friday, April 14, 2023, 15:58: Adjust Anode current limit further. 300 mA.
Friday, April 14, 2023, 16:06: Anode stable. Reduced current limit to 150 mA. Anode @ 400 A / 91.575 mA
Friday, April 14, 2023, 16:35: Spark* during mass scan. Current limited on the Anode. Reset optics as well.
Friday, April 14, 2023, 16:41: Reduced Anode to 100 V / 30.525 mA. Current limit reduced to 100 mA.
Friday, April 14, 2023, 19:45: Auto-Cooling @ 2 A per min. HV, Coil, & Anode to 0.
Monday, April 17, 2023, 07:35: Coil manually tapped up to 80 A @ 8 A per min.
Monday, April 17, 2023, 08:39: IV4 closed.
Monday, April 17, 2023, 08:44: Power ? Sources off.
Monday, April 17, 2023, 08:45: IG1 off. Turbos pump TP1B & TP1A off.
Monday, April 17, 2023, 13:24: Venting.
Monday, April 17, 2023, 13:26: Odd, the venting is going very slowly. "Aiding" the venting process.
Target oven was inspected post TS. Risks of cracking due to crystallization. |
Attachment 1: TiC#5_conditioning.docx
|
964
|
Monday, May 01, 2023, 14:31 |
Aaron Schmidt | TiC#5 | LP-FEBIAD | ITE | TM4 | 44692-5 | 45235-20 | In progress | Conditioning TiC#5 | New TiC LP-FEBIAD Target installed.
Monday, May 01, 2023, 14:23: Roughing.
Monday, May 01, 2023, 21:42: TP1B on
Monday, May 01, 2023, 21:49: TP1A on.
Monday, May 01, 2023, 21:57: IG1 on.
Tuesday, May 02, 2023, 08:39: Vacuum @ 1.16e-06T. Waterline FS#5 opened.
Tuesday, May 02, 2023, 08:48: Power / sources on. Source gas set. SV5 remains open.
Tuesday, May 02, 2023, 09:00: Optics set.
Tuesday, May 02, 2023, 09:13: System ready check - OK. Manually set.
TGHT / TBHT @ 5 / 5 A
BIAS / EE / EZL @ 1 / -0.5 / 1 kV
Anode @ 100 V - 10.989 mA
Coil @ 10 A.
Tuesday, May 02, 2023, 10:12: Coil @ 70 A. Tapped up manually @ 7 A per minute.
Tuesday, May 02, 2023, 12:20:
Tap up Anode in steps @ 20 v per 20 seconds.
Anode @ 100 V = 10.989 mA
Anode @ 200 V = 12.210 mA
Anode @ 300 V = 12.210 mA
Anode @ 400 V = 13.431 mA
Tuesday, May 02, 2023, 12:36: Anode @ 20 V.
Tuesday, May 02, 2023, 12:53: BIAS / EE / EZL @ 10 / -0.5 / 5 kV
Wednesday, May 03, 2023, 04:30: Auto-ramping TGHT / TBHT to 550 / 280 A @ 1 A per minute.
Wednesday, May 03, 2023, 10:42: BIAS / EE / EZL @ 30 / -1.5 / 13 kV.
TGHT / TBHT @ 360 / 280 A. Ramping ongoing.
Wednesday, May 03, 2023, 14:04: TGHT / TBHT @ 550 / 280 A
Wednesday, May 03, 2023, 14:10: Anode tapped up to 100 V @ 20 V per 20 seconds.
Wednesday, May 03, 2023, 14:25: Large spark*. Reset Optics.
Wednesday, May 03, 2023, 14:46: Mass & wire scans complete.
Wednesday, May 03, 2023, 17:05: Anode & coil checks complete. Auto-cooling of TGHT / TBHT @ 1 / 2 A per minute.
Wednesday, May 03, 2023, 22:51: IV4 closed.
Thursday, May 04, 2023, 07:35: SV5 closed. Sources / Power off.
Thursday, May 04, 2023, 07:37: IG1 off. TP off.
Thursday, May 04, 2023, 09:17: Venting. |
Attachment 1: TiC#5_-_44692-5_Anode_&_Coil_checks.docx
|
Attachment 2: TiC#5_-_44692-5_Conditioning.docx
|
367
|
Friday, March 28, 2014, 10:39 |
Anders Mjos | TiC#4 | HP-SIS | ITE | TM3 | | | In progress | Conditioning TiC#4 | NOTE:
TBHT Power Supply is 600A. EPICS thinks it is 500. Multiply current setting with 1.2 for actual current to the tube.
Friday, March 28, 2014, 10:38: Stopped turbos. Vacuum at 1.3E-7 T
Friday, March 28, 2014, 15:05: Venting
By RM
Friday, March 28, 2014, 15:22: Target assembly installed
Friday, March 28, 2014, 15:43: Chamber Roughing started
Friday, March 28, 2014, 15:58: Turbos started
Friday, March 28, 2014, 16:03: TP1B at speed
Friday, March 28, 2014, 16:06: TP1A at speed
Friday, March 28, 2014, 16:07: IG1 Turned on - reading 1.29e-05T
By R.M.
Monday, March 31, 2014, 09:55: Water to heatshield line turned on, no change in vacuum: 1.31e-07 T
|
|