Message ID: 936     Entry time: Thursday, July 07, 2022, 16:52
Author: Aaron Schmidt 
Target/No.#:  
Source: LP-IG-LIS 
Station: ITW 
Module: TM2 
Target Oven W.O#:  
Heat Shield W.O#: 42132-3 
Status: In progress 
Subject: Conditioning UC#39 assembly 

No UCx target installed. Straight / blank oven in use for out gassing.

Thursday, July 07, 2022, 16:50: Roughing.

Thursday, July 07, 2022, 16:53: BV1A Open.

Thursday, July 07, 2022, 17:31: TP1B on.

Thursday, July 07, 2022, 17:36: TP1A on.

Thursday, July 07, 2022, 17:46: IG1 on. Vacuum @ 2.31e-05T

Thursday, July 07, 2022, 17:47: Waterline FS#5 Opened. Vacuum @ 2.05e-05T & continuing down.

Thursday, July 07, 2022, 18:00: Bypass on IG1. 10A TGHT Check. Ok. Back to 0A. Removed bypass. Ready for remote operation.


Friday, July 08, 2022, 10:44: Started autoramping TGHT 580A/TBHT 0A

Friday, July 08, 2022, 15:37: Autoramping complete


Saturday, July 09, 2022, 07:34 : ramp down started


Sunday, July 10, 2022, 22:14: IG1, TP1B & A off. TP6 has tripped. Sources off.  
 