42972-5 Base / 42972-9 Lid
Tuesday, November 05, 2024, 16:30: Roughing.
Tuesday, November 05, 2024, 17:04: TP1B on.
Tuesday, November 05, 2024, 17:13: TP1A on.
Tuesday, November 05, 2024, 17:21: IG1 on @ 2.41e-05T
Wednesday, November 06, 2024, 10:35: Vacuum @ 5.75e-07T. Waterline FS#5 open.
Wednesday, November 06, 2024, 16:24: TGHT/TBHT ramping to 580/230A at 2A/min
Thursday, November 07, 2024, 09:16: Increasing BIAS/EE/EZL to 30/2.5/13 kV slowly
Thursday, November 07, 2024, 11:26: as expected, no beam out to FC0. slowly increasing to bias to 45kV alongside ezl to 28kV
Thursday, November 07, 2024, 11:27: TGHT dropped out for 1s. Did not register a trip or anything. simply jumped down to 0A and immediately recovered.
Thursday, November 07, 2024, 14:40: At 45kV, there were no sparks noticed. The target assembly was brought down to 0V and ramped down to 0A/0A at -2A/min
Wednesday, November 13, 2024, 09:15: PS Off. TP off - AS.
Wednesday, November 13, 2024, 11:26: VV1 opened - BB. |