Message ID: 717     Entry time: Monday, April 15, 2019, 14:42
Author: Aaron Schmidt 
Target/No.#:  
Source: LP-SIS 
Station:  
Module:  
Target Oven W.O#:  
Heat Shield W.O#: 42972-1 
Status: Done 
Subject: Conditioning UC#27 HS & test FS#3 

New coil lines installed for P2N testing later.

Monday, April 15, 2019, 14:15: Roughing.

Monday, April 15, 2019, 14:49: Turbo pumps on.


Tuesday, April 16, 2019, 08:20: RGA on.

Gradually open each line. Wait 5 minutes & monitor the response.

Tuesday, April 16, 2019, 08:30: Open Return & Supply main valves.

Tuesday, April 16, 2019, 08:32: Open FS#5. Vacuum @ 4.29e-06T. No response on RGA (water).

Tuesday, April 16, 2019, 08:37: Vacuum @ 4.37e-06T

Tuesday, April 16, 2019, 08:38: Open FS#4. Vacuum @ 4.37e-06T. No response on RGA (water).

Tuesday, April 16, 2019, 08:43 Vacuum @ 4.29e-06T

Tuesday, April 16, 2019, 08:44 Open FS#3. Vacuum @ 4.29e-06T. No response on RGA (water).

Tuesday, April 16, 2019, 08:49: Vacuum @ 4.26e-06T.

Tuesday, April 16, 2019, 08:50: Open FS#2. Vacuum @ 4.29e-06T. No response on RGA (water).

Tuesday, April 16, 2019, 08:57: Vacuum @ 4.29e-06T.


Wednesday, April 17, 2019, 08:30: Power/sources on. Vacuum @ 2.46e-06T.

Wednesday, April 17, 2019, 10:30: Auto-ramping TGHT  to 150 @ 2A per min. Vacuum limit increased to 3.000e-06T.

Wednesday, April 17, 2019, 11:53: Auto-ramping TGHT  to 300 @ 2A per min. Vacuum @ 2.50e-06T.

Wednesday, April 17, 2019, 13:10: Auto-ramping TGHT  to 350 @ 2A per min. Vacuum @ 2.95e-06T.


Thursday, April 18, 2019, 07:23: Auto-ramping TGHT  to 575 @ 2A per min. Vacuum @ 2.40e-06T.


Tuesday, April 23, 2019, 06:45: Auto-Cooling TGHT @ 2A per min. Vacuum @ 9.22e-07T. 

Tuesday, April 23, 2019, 08:29: RGA error. Shut off RGA.

Tuesday, April 23, 2019, 11:34: Power/sources off.

Tuesday, April 23, 2019, 11:37: IG1 off. Turbos off.

Tuesday, April 23, 2019, 12:53: Venting.

Attachment 1: UC#27_&_FS#3_check.docx  1.141 MB  Uploaded Tuesday, April 23, 2019, 15:41
Attachment 2: TS-2019-04-16-08-20.rga  5.097 MB  Uploaded Tuesday, April 23, 2019, 15:41