ID Date Author Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O# Statusdown Subject Text Attachments
  985   Thursday, November 16, 2023, 09:43 Aaron Schmidt LP-SIS    In progressThermal testsAurelia has been testing on the ISAC TS
since last week. Thermocouples are installed
in the end cap, left side & the ionizer.
  
  986   Monday, November 27, 2023, 16:09 Ferran Boix Pamies LP-SIS  45220-245235-13In progressHV power surge test plus mass scansMonday, November 27, 2023, 16:09 
Roughing
Monday, November 27, 2023, 17:22
  
  991   Thursday, January 18, 2024, 10:49 Aaron Schmidt LP-SIS  44139-245235-22In progressConditioning UCx HS Straight/closed TGHT tube oven installed.
SIS Assembly.
Thursday, January 18, 2024, 10:32:
  
  992   Monday, January 22, 2024, 13:55 Aaron Schmidt LP-SIS  45447-1945235-22In progressConditioning UCx HS - 2Conditioning HS for UCx. LP-SIS oven /
end caps installed
Monday, January 22, 2024, 13:53:
  
  993   Tuesday, February 06, 2024, 11:48 Aaron SchmidtSiC# (Stock)HP-SIS  41369-245235-14In progressConditioning (Stock SiC-24C) SiC HP-SISTuesday, February 06, 2024, 11:45: Roughing.
Tuesday, February 06, 2024, 13:27:
TP1B on.
  
  996   Friday, February 16, 2024, 10:30 Aaron SchmidtSiC# (Stock)HP-FEBIAD  45447-445235-21In progressConditioning stock SiC HP FEBIADFriday, February 16, 2024, 10:30: Roughing
Friday, February 16, 2024, 17:38:
TP1B on. 
 Stock_SiC_Elog_996_HP-FEBIAD_Cathode_BM_-_HV_&_Coil.docxHP-FEBIAD_Elog_996_-_Ramp_up_&_mass_scans.docxStock_SiC_Elog_996_HP-FEBIAD_Cathode_BIAS_mode_-_2.docx 
  1002   Tuesday, April 09, 2024, 16:01 Aaron SchmidtEmpty (Online)LP-FEBIADITWTM445447-2442972-8In progressConditioning empty FEBIAD for online useTuesday, April 09, 2024, 15:25: Roughing.

Wednesday, April 10, 2024,
05:41: TP1B on. 
 EE_issue_-_Conditioning_LP-FEBIAD_ITW-TM4.docx2024_-_ITW-_TM4_LP_FEBIAD.docx 
  1004   Wednesday, April 17, 2024, 14:16 Aaron SchmidtEmpty (Online)LP-FEBIADITWTM445447-2442972-8In progressConditioning empty FEBIAD for online use - Run 2https://elog.triumf.ca/TIS/Test-Stand/1003
EE Issue resolved. TS closed up.
Wednesday, April 17, 2024, 14:08:
 2024_-_ITW-_TM4_LP_FEBIAD_-_2.docx 
  1005   Friday, April 19, 2024, 11:33 Dave Neilson-LP-FEBIAD  44692-442972-10In progressDevelopment target test - Calibrated leak - Anode mode Friday, April 19, 2024, 11:32: 
 assembly installed in test stand. 
VV1 closed, pumping down
  
  1007   Friday, April 26, 2024, 13:49 Aaron SchmidtTiC#7HP-FEBIADITWTM445447-545235-15In progressConditioning TiC#7FM-SW calibrated leak installed.
Friday, April 26, 2024, 13:48: Roughing.
Friday, April 26, 2024, 14:20: TP1B
  
  1008   Thursday, May 02, 2024, 13:45 Dave Neilson-LP-SIS  44691-845235-26In progressMass marker testing Wednesday, May 01, 2024, 12:44: 
pumped down to rough vacuum, TP1B now on.
Wednesday, May 01, 2024, 12:49: 
  
  1009   Friday, May 17, 2024, 17:24 Brady BorrmannUC#LP-FEBIADITE 44692-445235-18In progressConditioning Spare Development TargetFriday, May 17, 2024, Spare FEBIAD Development
target installed
Friday, May 17, 2024, 17:00: Roughing
  
  1010   Thursday, May 30, 2024, 16:00 Aaron Schmidt LP-FEBIAD  44692-445235-18In progressConditioning spare FEBIADAnode short repaired (Should be :) )
Thursday, May 30, 2024, 15:56: Roughing.
Thursday, May 30, 2024, 16:10: Waterline
  
  1011   Wednesday, June 19, 2024, 15:50 Brady BorrmannTiC#9HP-SIS  45447-2945235-19In progressConditioning TiC#9Wednesday, June19, 2024, Spare TiC HP-SIS
target installed. TiC#24C
Wednesday, June19, 2024, 15:00: Roughing
 2024-06-21_HPTiC-24C_target_characterization.docx 
  1016   Wednesday, July 31, 2024, 18:50 Aaron SchmidtTiC SpareHP-FEBIADITWTM445447-242752-7In progressConditioning Spare for TiC#7Wednesday, July 31, 2024, 18:47: Roughing.
Wednesday, July 31, 2024, 19:24:
TP1B on.
  
  1018   Friday, August 09, 2024, 21:08 Ferran Boix PamiesTa#67 Thin foils LP-SISITETM445447-14 45235-10In progressTa#67 thin foil retestingFriday, August 09, 2024, 21:07 Insulators,
retainer and Re foil have been replaced,
source cup machined so the ion source does
 ITE-TM4-Ta#67-LP-SIS_Thin_Foil.docx 
  1026   Tuesday, October 29, 2024, 18:25 Aaron SchmidtUC#46 (assembly only)LP-IG-LISITWTM4 42972-6 / 39956-1In progressConditioning UC#46 Assembly 42972-6 Base / 39956-1 Lid
Tuesday, October 29, 2024, 18:20:
Roughing. 
  
  1027   Thursday, October 31, 2024, 13:53 Aaron Schmidt      In progressChamber empty & Fix IG6 Thursday, October 31, 2024, 13:53:
Roughing down empty chamber. U-Line installed.

Monday, November 04, 2024,
  
  1028   Tuesday, November 05, 2024, 16:40 Brady BorrmannUC #24D (Assembly only)LP-IG-LIS   44972-5 / 42972-9In progressConditioning UC#24D Assembly42972-5 Base / 42972-9 Lid
  
  1029   Wednesday, November 13, 2024, 14:36 Aaron SchmidtUC#(47) - Not includedLP-SISITETM344691-845235-24In progressConditioning UC#47 (Assembly only)Gas line is attached. 
Wednesday, November 13, 2024, 14:18:
Roughing.
 UC#47_empty_conditioning_test_1_-_Failed.docxUC#47_empty_conditioning_test_2.docx 