  1008   Thursday, May 02, 2024, 13:45 Dave Neilson-LP-SIS  44691-845235-26In progressMass marker testing Wednesday, May 01, 2024, 12:44: 
pumped down to rough vacuum, TP1B now on.
Wednesday, May 01, 2024, 12:49: 
  
  1012   Tuesday, July 23, 2024, 09:43 Dave Neilson LP-SIS  44691-845235-26Donemass marker - reservoir testingWednesday, July 22, 2024, 11:41  -
target installed
Wednesday, July 22, 2024, 13:31 -
  
  1041   Tuesday, December 17, 2024, 09:46 Dave Neilson     45235-26In progressSIS P2N source cup testingMonday, December 16, 2024, 3:34   Target
loaded in test stand. Confirmed correct connection
to mass marker power supply through multipin.
  
  1021   Tuesday, September 10, 2024, 16:24 Dave NeilsonTiC #24DHP-SISITWTM345447-2745235-25 Back up target testing and conditioningTuesday, September 10, 2024, 16:21: 
 Target installed in test stand by Brady
Tuesday, September 10, 2024, 16:21:
 2024-09-11_HPTiC-24D_target_characterization.docx 
  1029   Wednesday, November 13, 2024, 14:36 Aaron SchmidtUC#(47) - Not includedLP-SISITETM344691-845235-24In progressConditioning UC#47 (Assembly only)Gas line is attached. 
Wednesday, November 13, 2024, 14:18:
Roughing.
 UC#47_empty_conditioning_test_1_-_Failed.docxUC#47_empty_conditioning_test_2.docx 
  991   Thursday, January 18, 2024, 10:49 Aaron Schmidt LP-SIS  44139-245235-22In progressConditioning UCx HS Straight/closed TGHT tube oven installed.
SIS Assembly.
Thursday, January 18, 2024, 10:32:
  
  992   Monday, January 22, 2024, 13:55 Aaron Schmidt LP-SIS  45447-1945235-22In progressConditioning UCx HS - 2Conditioning HS for UCx. LP-SIS oven /
end caps installed
Monday, January 22, 2024, 13:53:
  
  996   Friday, February 16, 2024, 10:30 Aaron SchmidtSiC# (Stock)HP-FEBIAD  45447-445235-21In progressConditioning stock SiC HP FEBIADFriday, February 16, 2024, 10:30: Roughing
Friday, February 16, 2024, 17:38:
TP1B on. 
 Stock_SiC_Elog_996_HP-FEBIAD_Cathode_BM_-_HV_&_Coil.docxHP-FEBIAD_Elog_996_-_Ramp_up_&_mass_scans.docxStock_SiC_Elog_996_HP-FEBIAD_Cathode_BIAS_mode_-_2.docx 
  960   Wednesday, March 29, 2023, 12:22 Aaron SchmidtTiC#5LP-FEBIADITETM444692-745235-20FailedConditioning TiC#5Wednesday, March 29, 2023, 09:15: Roughing.
Wednesday, March 29, 2023, 12:22:
TP1B on.
 TiC#5_conditioning.docx 
  963   Wednesday, April 26, 2023, 08:46 Aaron SchmidtTiC#5LP-FEBIADITETM444692-645235-20 Testing TiC#5 assembly w/ an empty targetAnode remade with a ceramic "elbow-cube".
Empty target oven in use for testing.
Wednesday, April 26, 2023, 08:44:
 TiC#5_empty_container_run.docxScreenshot_from_2023-04-27_21-54-15.png 
  964   Monday, May 01, 2023, 14:31 Aaron SchmidtTiC#5LP-FEBIADITETM444692-545235-20In progressConditioning TiC#5New TiC LP-FEBIAD Target installed.
Monday, May 01, 2023, 14:23: Roughing.
Monday, May 01, 2023, 21:42: TP1B
 TiC#5_-_44692-5_Anode_&_Coil_checks.docxTiC#5_-_44692-5_Conditioning.docx 
  967   Tuesday, May 16, 2023, 14:00 Aaron SchmidtTa#65LP-SISITETM445220-745235-2In progressConditioning Ta#65Calibrated window installed on the beam
line.
Tuesday, May 16, 2023, 13:45: Roughing
 Ta#65_conditioning_-_Mass_&_wire_scans.docx 
  1011   Wednesday, June 19, 2024, 15:50 Brady BorrmannTiC#9HP-SIS  45447-2945235-19In progressConditioning TiC#9Wednesday, June19, 2024, Spare TiC HP-SIS
target installed. TiC#24C
Wednesday, June19, 2024, 15:00: Roughing
 2024-06-21_HPTiC-24C_target_characterization.docx 
  1009   Friday, May 17, 2024, 17:24 Brady BorrmannUC#LP-FEBIADITE 44692-445235-18In progressConditioning Spare Development TargetFriday, May 17, 2024, Spare FEBIAD Development
target installed
Friday, May 17, 2024, 17:00: Roughing
  
  1010   Thursday, May 30, 2024, 16:00 Aaron Schmidt LP-FEBIAD  44692-445235-18In progressConditioning spare FEBIADAnode short repaired (Should be :) )
Thursday, May 30, 2024, 15:56: Roughing.
Thursday, May 30, 2024, 16:10: Waterline
  
  983   Wednesday, October 18, 2023, 15:43 Aaron Schmidt LP-SIS  45447-1245235-17In progressConditioning UC#43 (empty) w/ gas lineThermocouples attached on end plate
Indium salt @ 10 µl
3 wraps of Ta HS on oven. Gas line
 UC#43_Conditioning_empty_with_Gas_mod.docxUC#43_HS_with_gas_line_mod_-_Test_2.docxUC#43_HS_with_gas_line_mod_-_HV_Test.docx 
  1023   Thursday, October 03, 2024, 16:26 Aaron SchmidtTa#68HP-SISITETM245447-2645235-16 * Conditioning Ta#68HS note:
Base# 45235-16
Lid# 39956-8
  
  1007   Friday, April 26, 2024, 13:49 Aaron SchmidtTiC#7HP-FEBIADITWTM445447-545235-15In progressConditioning TiC#7FM-SW calibrated leak installed.
Friday, April 26, 2024, 13:48: Roughing.
Friday, April 26, 2024, 14:20: TP1B
  
  993   Tuesday, February 06, 2024, 11:48 Aaron SchmidtSiC# (Stock)HP-SIS  41369-245235-14In progressConditioning (Stock SiC-24C) SiC HP-SISTuesday, February 06, 2024, 11:45: Roughing.
Tuesday, February 06, 2024, 13:27:
TP1B on.
  
  984   Monday, October 30, 2023, 16:01 Aaron Schmidt LP-SIS  45220-245235-13In progressHV power surge test plus mass scans Monday, October 30, 2023, 16:00 
Roughing

Tuesday, October 31, 2023,
  