Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Test-Stand, Page 2 of 53  Not logged in ELOG logo
Entry  Thursday, May 02, 2024, 13:45, Dave Neilson, -, LP-SIS, , , 44691-8, 45235-26, In progress, Mass marker testing 
 Wednesday, May 01, 2024, 12:44:  pumped down to rough vacuum, TP1B now on.
Wednesday, May 01, 2024, 12:49:  TP1A on.
Thursday, May 02, 2024, 9:10:  water cooling on. no effect on vacuum
Entry  Tuesday, July 23, 2024, 09:43, Dave Neilson, , LP-SIS, , , 44691-8, 45235-26, Done, mass marker - reservoir testing 
Wednesday, July 22, 2024, 11:41  - target installed
Wednesday, July 22, 2024, 13:31 - pumping down
Wednesday, July 22, 2024, 14:21 - turbo pumps on
Entry  Tuesday, December 17, 2024, 09:46, Dave Neilson, , , , , , 45235-26, In progress, SIS P2N source cup testing 
Monday, December 16, 2024, 3:34   Target loaded in test stand. Confirmed correct connection to mass marker power supply through multipin. Bottom
left pin (5 PS - ) connected to grounded side of the filament, top right pin (2, PS +) connected to top end of filament.
 
Entry  Tuesday, September 10, 2024, 16:24, Dave Neilson, TiC #24D, HP-SIS, ITW, TM3, 45447-27, 45235-25, , Back up target testing and conditioning 2024-09-11_HPTiC-24D_target_characterization.docx
Tuesday, September 10, 2024, 16:21:   Target installed in test stand by Brady
Tuesday, September 10, 2024, 16:21: roughed down and turbo pumps now on.
Tuesday, September 10, 2024, 20:27   Pressure at 4.9e-6, increasing TGHT TBHT to 580A/230A at 1A/30s
Entry  Wednesday, November 13, 2024, 14:36, Aaron Schmidt, UC#(47) - Not included, LP-SIS, ITE, TM3, 44691-8, 45235-24, In progress, Conditioning UC#47 (Assembly only) UC#47_empty_conditioning_test_1_-_Failed.docxUC#47_empty_conditioning_test_2.docx
Gas line is attached. 
Wednesday, November 13, 2024, 14:18: Roughing.
Wednesday, November 13, 2024, 18:20: Closed backing valves. Vacuum @ 2.140 T? 
Entry  Thursday, January 18, 2024, 10:49, Aaron Schmidt, , LP-SIS, , , 44139-2, 45235-22, In progress, Conditioning UCx HS  
Straight/closed TGHT tube oven installed. SIS Assembly.
Thursday, January 18, 2024, 10:32: Roughing.
Thursday, January 18, 2024, 10:57: TP1B on.
Entry  Monday, January 22, 2024, 13:55, Aaron Schmidt, , LP-SIS, , , 45447-19, 45235-22, In progress, Conditioning UCx HS - 2 
Conditioning HS for UCx. LP-SIS oven / end caps installed
Monday, January 22, 2024, 13:53: Roughing.
Monday, January 22, 2024, 14:21: TP1B On.
Entry  Friday, February 16, 2024, 10:30, Aaron Schmidt, SiC# (Stock), HP-FEBIAD, , , 45447-4, 45235-21, In progress, Conditioning stock SiC HP FEBIAD Stock_SiC_Elog_996_HP-FEBIAD_Cathode_BM_-_HV_&_Coil.docxHP-FEBIAD_Elog_996_-_Ramp_up_&_mass_scans.docxStock_SiC_Elog_996_HP-FEBIAD_Cathode_BIAS_mode_-_2.docx
Friday, February 16, 2024, 10:30: Roughing
Friday, February 16, 2024, 17:38: TP1B on. 
Friday, February 16, 2024, 17:47: TP1A on. 
Entry  Wednesday, March 29, 2023, 12:22, Aaron Schmidt, TiC#5, LP-FEBIAD, ITE, TM4, 44692-7, 45235-20, Failed, Conditioning TiC#5 TiC#5_conditioning.docx
Wednesday, March 29, 2023, 09:15: Roughing.
Wednesday, March 29, 2023, 12:22: TP1B on.
Wednesday, March 29, 2023, 12:40: TP1A on.
Entry  Wednesday, April 26, 2023, 08:46, Aaron Schmidt, TiC#5, LP-FEBIAD, ITE, TM4, 44692-6, 45235-20, , Testing TiC#5 assembly w/ an empty target TiC#5_empty_container_run.docxScreenshot_from_2023-04-27_21-54-15.png
Anode remade with a ceramic "elbow-cube". Empty target oven in use for testing.
Wednesday, April 26, 2023, 08:44: BV1B open. Roughing.
Wednesday, April 26, 2023, 08:46: BV1A open
Entry  Monday, May 01, 2023, 14:31, Aaron Schmidt, TiC#5, LP-FEBIAD, ITE, TM4, 44692-5, 45235-20, In progress, Conditioning TiC#5 TiC#5_-_44692-5_Anode_&_Coil_checks.docxTiC#5_-_44692-5_Conditioning.docx
New TiC LP-FEBIAD Target installed.
Monday, May 01, 2023, 14:23: Roughing.
Monday, May 01, 2023, 21:42: TP1B on 
Entry  Tuesday, May 16, 2023, 14:00, Aaron Schmidt, Ta#65, LP-SIS, ITE, TM4, 45220-7, 45235-2, In progress, Conditioning Ta#65 Ta#65_conditioning_-_Mass_&_wire_scans.docx
Calibrated window installed on the beam line.
Tuesday, May 16, 2023, 13:45: Roughing both the chamber & beam line.
Tuesday, May 16, 2023, 14:00: TMS:TP6 on.
Entry  Wednesday, June 19, 2024, 15:50, Brady Borrmann, TiC#9, HP-SIS, , , 45447-29, 45235-19, In progress, Conditioning TiC#9 2024-06-21_HPTiC-24C_target_characterization.docx
Wednesday, June19, 2024, Spare TiC HP-SIS target installed. TiC#24C
Wednesday, June19, 2024, 15:00: Roughing
Wednesday, June19, 2024, 17:25:  TP1B started.
Entry  Friday, May 17, 2024, 17:24, Brady Borrmann, UC#, LP-FEBIAD, ITE, , 44692-4, 45235-18, In progress, Conditioning Spare Development Target 
Friday, May 17, 2024, Spare FEBIAD Development target installed
Friday, May 17, 2024, 17:00: Roughing
Friday, May 17, 2024, 17:38:  TP1B started.
Entry  Thursday, May 30, 2024, 16:00, Aaron Schmidt, , LP-FEBIAD, , , 44692-4, 45235-18, In progress, Conditioning spare FEBIAD 
Anode short repaired (Should be :) )
Thursday, May 30, 2024, 15:56: Roughing.
Thursday, May 30, 2024, 16:10: Waterline FS#5 open. Vacuum ok & roughing down.
Entry  Wednesday, October 18, 2023, 15:43, Aaron Schmidt, , LP-SIS, , , 45447-12, 45235-17, In progress, Conditioning UC#43 (empty) w/ gas line UC#43_Conditioning_empty_with_Gas_mod.docxUC#43_HS_with_gas_line_mod_-_Test_2.docxUC#43_HS_with_gas_line_mod_-_HV_Test.docx
Thermocouples attached on end plate
Indium salt @ 10 µl
3 wraps of Ta HS on oven. Gas line on center block. Empty oven.
Entry  Thursday, October 03, 2024, 16:26, Aaron Schmidt, Ta#68, HP-SIS, ITE, TM2, 45447-26, 45235-16 *, , Conditioning Ta#68 
HS note:
Base# 45235-16
Lid# 39956-8
Entry  Friday, April 26, 2024, 13:49, Aaron Schmidt, TiC#7, HP-FEBIAD, ITW, TM4, 45447-5, 45235-15, In progress, Conditioning TiC#7 
FM-SW calibrated leak installed.
Friday, April 26, 2024, 13:48: Roughing.
Friday, April 26, 2024, 14:20: TP1B started.
Entry  Tuesday, February 06, 2024, 11:48, Aaron Schmidt, SiC# (Stock), HP-SIS, , , 41369-2, 45235-14, In progress, Conditioning (Stock SiC-24C) SiC HP-SIS 
Tuesday, February 06, 2024, 11:45: Roughing.
Tuesday, February 06, 2024, 13:27: TP1B on.
Tuesday, February 06, 2024, 13:33: TP1A on.
Entry  Monday, October 30, 2023, 16:01, Aaron Schmidt, , LP-SIS, , , 45220-2, 45235-13, In progress, HV power surge test plus mass scans 
 Monday, October 30, 2023, 16:00  Roughing

Tuesday, October 31, 2023, 08:58 Turbos on the afternoon before, TP1A timed out which delayed for another 30min turning on both TP. Now
3e-6 Torr in IG1. - FBP
ELOG V2.9.2-2455