ID |
Date |
Author |
Target/No.# |
Source |
Station |
Module |
Target Oven W.O# |
Heat Shield W.O# |
Status |
Subject |
Text |
|
1008
|
Thursday, May 02, 2024, 13:45 |
Dave Neilson | - | LP-SIS | | | 44691-8 | 45235-26 | In progress | Mass marker testing | Wednesday, May 01, 2024, 12:44:
pumped down to rough vacuum, TP1B now on.
Wednesday, May 01, 2024, 12:49: |
|
1012
|
Tuesday, July 23, 2024, 09:43 |
Dave Neilson | | LP-SIS | | | 44691-8 | 45235-26 | Done | mass marker - reservoir testing | Wednesday, July 22, 2024, 11:41 -
target installed
Wednesday, July 22, 2024, 13:31 - |
|
1041
|
Tuesday, December 17, 2024, 09:46 |
Dave Neilson | | | | | | 45235-26 | In progress | SIS P2N source cup testing | Monday, December 16, 2024, 3:34 Target
loaded in test stand. Confirmed correct connection
to mass marker power supply through multipin. |
|
1021
|
Tuesday, September 10, 2024, 16:24 |
Dave Neilson | TiC #24D | HP-SIS | ITW | TM3 | 45447-27 | 45235-25 | | Back up target testing and conditioning | Tuesday, September 10, 2024, 16:21:
Target installed in test stand by Brady
Tuesday, September 10, 2024, 16:21: |
|
1029
|
Wednesday, November 13, 2024, 14:36 |
Aaron Schmidt | UC#(47) - Not included | LP-SIS | ITE | TM3 | 44691-8 | 45235-24 | In progress | Conditioning UC#47 (Assembly only) | Gas line is attached.
Wednesday, November 13, 2024, 14:18:
Roughing. |
|
991
|
Thursday, January 18, 2024, 10:49 |
Aaron Schmidt | | LP-SIS | | | 44139-2 | 45235-22 | In progress | Conditioning UCx HS | Straight/closed TGHT tube oven installed.
SIS Assembly.
Thursday, January 18, 2024, 10:32: |
|
992
|
Monday, January 22, 2024, 13:55 |
Aaron Schmidt | | LP-SIS | | | 45447-19 | 45235-22 | In progress | Conditioning UCx HS - 2 | Conditioning HS for UCx. LP-SIS oven /
end caps installed
Monday, January 22, 2024, 13:53: |
|
996
|
Friday, February 16, 2024, 10:30 |
Aaron Schmidt | SiC# (Stock) | HP-FEBIAD | | | 45447-4 | 45235-21 | In progress | Conditioning stock SiC HP FEBIAD | Friday, February 16, 2024, 10:30: Roughing
Friday, February 16, 2024, 17:38:
TP1B on. |
|
960
|
Wednesday, March 29, 2023, 12:22 |
Aaron Schmidt | TiC#5 | LP-FEBIAD | ITE | TM4 | 44692-7 | 45235-20 | Failed | Conditioning TiC#5 | Wednesday, March 29, 2023, 09:15: Roughing.
Wednesday, March 29, 2023, 12:22:
TP1B on. |
|
963
|
Wednesday, April 26, 2023, 08:46 |
Aaron Schmidt | TiC#5 | LP-FEBIAD | ITE | TM4 | 44692-6 | 45235-20 | | Testing TiC#5 assembly w/ an empty target | Anode remade with a ceramic "elbow-cube".
Empty target oven in use for testing.
Wednesday, April 26, 2023, 08:44: |
|
964
|
Monday, May 01, 2023, 14:31 |
Aaron Schmidt | TiC#5 | LP-FEBIAD | ITE | TM4 | 44692-5 | 45235-20 | In progress | Conditioning TiC#5 | New TiC LP-FEBIAD Target installed.
Monday, May 01, 2023, 14:23: Roughing.
Monday, May 01, 2023, 21:42: TP1B |
|
967
|
Tuesday, May 16, 2023, 14:00 |
Aaron Schmidt | Ta#65 | LP-SIS | ITE | TM4 | 45220-7 | 45235-2 | In progress | Conditioning Ta#65 | Calibrated window installed on the beam
line.
Tuesday, May 16, 2023, 13:45: Roughing |
|
1011
|
Wednesday, June 19, 2024, 15:50 |
Brady Borrmann | TiC#9 | HP-SIS | | | 45447-29 | 45235-19 | In progress | Conditioning TiC#9 | Wednesday, June19, 2024, Spare TiC HP-SIS
target installed. TiC#24C
Wednesday, June19, 2024, 15:00: Roughing |
|
1009
|
Friday, May 17, 2024, 17:24 |
Brady Borrmann | UC# | LP-FEBIAD | ITE | | 44692-4 | 45235-18 | In progress | Conditioning Spare Development Target | Friday, May 17, 2024, Spare FEBIAD Development
target installed
Friday, May 17, 2024, 17:00: Roughing |
|
1010
|
Thursday, May 30, 2024, 16:00 |
Aaron Schmidt | | LP-FEBIAD | | | 44692-4 | 45235-18 | In progress | Conditioning spare FEBIAD | Anode short repaired (Should be :) )
Thursday, May 30, 2024, 15:56: Roughing.
Thursday, May 30, 2024, 16:10: Waterline |
|
983
|
Wednesday, October 18, 2023, 15:43 |
Aaron Schmidt | | LP-SIS | | | 45447-12 | 45235-17 | In progress | Conditioning UC#43 (empty) w/ gas line | Thermocouples attached on end plate
Indium salt @ 10 µl
3 wraps of Ta HS on oven. Gas line |
|
1023
|
Thursday, October 03, 2024, 16:26 |
Aaron Schmidt | Ta#68 | HP-SIS | ITE | TM2 | 45447-26 | 45235-16 * | | Conditioning Ta#68 | HS note:
Base# 45235-16
Lid# 39956-8 |
|
1007
|
Friday, April 26, 2024, 13:49 |
Aaron Schmidt | TiC#7 | HP-FEBIAD | ITW | TM4 | 45447-5 | 45235-15 | In progress | Conditioning TiC#7 | FM-SW calibrated leak installed.
Friday, April 26, 2024, 13:48: Roughing.
Friday, April 26, 2024, 14:20: TP1B |
|
993
|
Tuesday, February 06, 2024, 11:48 |
Aaron Schmidt | SiC# (Stock) | HP-SIS | | | 41369-2 | 45235-14 | In progress | Conditioning (Stock SiC-24C) SiC HP-SIS | Tuesday, February 06, 2024, 11:45: Roughing.
Tuesday, February 06, 2024, 13:27:
TP1B on. |
|
984
|
Monday, October 30, 2023, 16:01 |
Aaron Schmidt | | LP-SIS | | | 45220-2 | 45235-13 | In progress | HV power surge test plus mass scans | Monday, October 30, 2023, 16:00
Roughing
Tuesday, October 31, 2023, |
|
|