ID |
Date |
Author |
Category |
Type |
Specific |
Subject |
Text |
 |
264
|
Wednesday, June 10, 2020, 08:58 |
Isaac Earle | Development | Other | M9 | T2-M9 and M9-B1 flange scan data | Laser tracker scan data from 2017
and 2019 attached as a backup. Original
files from Beamlines Group who also keep |
 |
263
|
Tuesday, June 09, 2020, 17:01 |
Isaac Earle | Development | Other | M9 | Cables and helium leak check line installed to M9 service stand | The 10-pin thermal switch wire, 2-pin
steering wire for Q2, and a 1/4" copper
tube for remote helium leak check were installed |
|
262
|
Monday, April 06, 2020, 15:02 |
Isaac Earle | Standard Operation | Target 2 | M9 | M9 beam blocker returned to beamline | The M9 beam blocker was returned to the
beamline today using the RH shielded transport
flask. The top flange o-ring was replaced |
|
261
|
Monday, March 23, 2020, 16:13 |
Isaac Earle | Maintenance | Other | Other | M9 beam blocker MRO completed | M9 beam blocker MRO work was completed
in the hot cell today. This included
replacement of the main shaft seals and replacement |
|
260
|
Wednesday, March 11, 2020, 10:29 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 service stand foot plate installed | The M9 Q1Q2 "foot" plate
(TB23363) has been installed over the floor
plate. A nominal gap between the plates |
|
259
|
Wednesday, March 04, 2020, 13:42 |
Ron Kuramoto | Repair | Other | Other | B/L 1A vacuum air leak repair | A 4” Marmon aluminum blank-off
flange and o-ring were replaced on the south
port of the T1 target monolith vacuum vessel. This |
|
258
|
Friday, February 28, 2020, 09:06 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 service stand floor plate installed | The M9 service stand floor plate
(TB23351) was installed in the M9 pit yesterday.
Prior to installation all 5 threaded inserts |
|
257
|
Monday, February 10, 2020, 14:51 |
Isaac Earle | Maintenance | Other | Other | T1-MK2 target and M9BB moved | The T1-MK2 target was moved from
the hot cell to Hole #5 in the storage pit.
The M9 beam blocker was then moved from the |
|
256
|
Wednesday, February 05, 2020, 14:53 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 & T2 cooling package MRO work completed | Annual MRO work on the T1 and T2
cooling packages is now complete. The
following tasks were performed: |
|
255
|
Thursday, January 30, 2020, 17:55 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 target assembly repair completed in hot cell | The following work was done to the T1-MK2
target in the hotcell between the dates of
May 24, 2019 - Jan 30, 2020 (See E-Log #251 |
    |
254
|
Monday, January 20, 2020, 16:07 |
Isaac Earle | Other | Other | Other | Second 55-gal drum moved to cyclotron east vault tunnel | The second (and final) 55 gallon
drum containing active items from the Meson
Hall East Hot Cell was transported today |
|
253
|
Tuesday, December 17, 2019, 12:39 |
Isaac Earle | Standard Operation | Other | Other | 55 gallon drum and old M9 service stand moved to Rad Waste Pit | The following items were moved today from
the Warm Cell to the Rad Waste Pit for long
term storage: |
    |
252
|
Monday, June 24, 2019, 14:29 |
Isaac Earle | Development | Target 1 | Target | T1 and T2 target alignment frames overhauled | The following work was completed on both
the T1 and T2 target alignment frames
One of the short taper |
8x |
251
|
Wednesday, May 22, 2019, 14:25 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 target moved to HC; T1-MK1 target moved to BL | After extensive
testing over the last 2 weeks it was determined |
|
250
|
Tuesday, April 16, 2019, 15:35 |
Keith C Ng | Repair | Other | M9 | M9 project post shutdown summary | Completed work at m9 beam line:
- Removed existing service stand
and associated cable and water services. |
|
249
|
Tuesday, February 26, 2019, 10:55 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 and T2 MRO work and solenoid valve change summary | The following work was completed between
Jan 16 - Feb 19, 2019:
T1 and T2 cooling packages |
|
248
|
Friday, January 25, 2019, 10:53 |
maicodallavalle | Repair | Other | Cyclotron electrical | Cyclotron Elevating system Motor electrical wire repairs | 2018 Cyclotron lid up problem. Station
#9 was found to have the motor
wires along the beam plain had damaged wire |
|
247
|
Thursday, January 10, 2019, 13:51 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 and T2 cooling packages inspected | The T1 and T2 cooling packages were inspected
today while running. No water leaks
were observed at either package including |
|
246
|
Thursday, November 01, 2018, 13:57 |
Keith C Ng | Other | Other | Other | nuclear venillation in hot cells not working | Randomly checked on the nuclear ventilation
for the Meson Hall Hotcells and discovered
they were not running again (both magnahelic |
|
245
|
Thursday, October 25, 2018, 08:58 |
Keith C Ng | Repair | Other | Other | T1 collimator valve solenoid coil replaced again | On
23rd October we restarted the T1 and T2 water
packages after the mini shutdown and after |
|